RE PHS Non-Motorized SEPAStacey,
The SEPA is supposed to cover both Phase 1 and 2. The NEPA does cover both phases. It is a bit of a different project as we have 4 different Federal Aid grants that are being distributed
at different times. We have a grant for design cost, and a second for right of way that cover both phases of the project so we had to have the NEPA cover both phases. We have two different
grants for each phase of construction, but we don’t get the Phase 2 funds until 2026.
Hope that helps.
Thanks
John Mulkey, P.E.
Senior Civil Engineer
City of Federal Way
Public Works Department
33325 8th Avenue S
Federal Way, WA 98003-6325
Phone: 253-835-2722
Fax: 253-835-2709
From: Stacey Welsh <Stacey.Welsh@cityoffederalway.com>
Sent: Friday, February 23, 2024 12:04 PM
To: John Mulkey <John.Mulkey@cityoffederalway.com>
Subject: PHS Non-Motorized SEPA
Hi John,
I’m reviewing the PHS Non-Motorized SEPA submittal (24-100477-SE). I need clarification on whether this SEPA is for just Phase 1 (as indicated on the Master Land Use Application) or
both Phases (as indicated in the Adoption of Existing Environmental Document form). Many of the submitted materials discuss/show both phases.
Thank you,
Stacey
Stacey Welsh, AICP
Principal Planner
[cid:image001.jpg@01D999D9.70663640]
Community Development Department- Planning Division
33325 8th Avenue South, 2nd Floor