20-103894-Permit FinalCity of Federal Way
Community Development Dept.
33325 8th Ave S
Federal Way, WA 98003
Ph: (253) 835-2607 Fax: (253) 835-2609
Project Name: MERIDIAN COURT APARTMENTS 31510
Project Address: 31510 23RD AVE S
Building - Multi Family
Permit 9:20-103894-00-MF
Inspection Request Line: (253) 835-3050
Parcel Number: 092104 9190
Project Description: BLUEBEAIVI - Tax credit rehab of existing senior apartments. Upgrades to include accessibility
of dwelling units and common areas; other dwelling units to have kitchen, bath and finish
upgrades.
Owner
Applicant
Contractor
Lender
FAIRFIELD MERIDIAN COURT LP
BRIAN MEISTERBAU MEISTER
FAIRFIELD DEVELOPMENT WA
R-4 CAPITAL
;55 MIRA SORRENTO PL SUITE 11
STUDIO CORP
LP
780 3RD AVE FLOOR 16
6755 SARANAC ST
355 MIRA SORRENTO PL SUITE 10
NEW YORK NY 10017
SAN DIEGO CA 92121
SAN DIEGO CA 92115
SAN DIEGO CA 92121
Census Category: 434 - Residential alt/add - no change in number of units
Includes:
# 1
#2
93
#4
Occu anc Class:
Construction ape:
Occupancy Load:
Floor Area (sq. ft.)
Additional Permit Information
Mechanical to be Included? ............... I..................... No
Is this an Online or O.T.C. application? .................. No
Plumbing to be Included? ........................................ No
Number of Stories ................................................... 2
Permit for Building Shell Only? .............................. No
No Fixtures Associated With This Permit ll
PERMIT EXPIRES Monday, 19 July, 2021
Permit Issued on Wednesday, January 20, 2021
I hereby certify that the above information is correct and that the construction on the above described property
and the occupancy and the use will be in accordance with the laws, rules and regulations of the State of
i ton e City of Federal Way.
E
Owner or agent: _ mate
_N�
CITY OF
Federal Way
THIS CARD IS TO REMAIN ON -SITE
Construction Inspection Record
INSPECTION REQUESTS; (253) 835-3050
PERMIT #: 20 103894 00 Address: 31510 23RD AVE S
Project: FAIRFIELI) MERIDIAN Couwr I.P FIA)ERAL WAY WA 98003
Scheduled inspections may be failed if this card is not on -site. DO NOT LOSE THIS C'.AIU). Inspections are listed as close to sequential order as possible
(read left to right, top to bottom). Please schedule inspections as appropriate. Work must not be covered until it is approved. Check with your inspector if
you are unsure about any of the inspections or the inspection sequence. On -going inspections are logged ryryon the back of this card.
❑ Footings/Setback (4110) ElFoundation Wall (4115) IJ Drainage/Downspout (4040)
Approved to place concrete Approved to place concrete Approved to backfill
By Date By Date By Date
❑
Re -steel (4215)
❑
Slab/Concrete Floor (4255)
El
Underfloor Framing (4285)
Approved to place concrete or grout
Approved to place concrete
Approved to sheath floor
By
Date
By
Date
By
Date
FJ
By
Floor Sheathing (4105)
Approved to install flooring
Date
❑
By
Shear Walls (4245)
Approved to install siding
Date
❑
By
Roof Sheathing (4220)
Approved to install roofing
Date
❑
Fire/Draft Stops (4095)
Prior to scheduling a Framing inspection;.
Framing (4120)
Approved
Electrical, Plumbing & Mechanical Rough -in I
Approved to insulate
and Fire/Draft Stop inspections must be signed -
By
Date
off and approved. IBC 109.3.4
By
Date
❑
Insulation (4150)
El
Gypsum Wallboard Nailing (4130)
Suspended Ceiling Grid (4265)
Approved to install wallboard
Approved to install mud & tape
Approved to drop tile
By
Date
By
Date
By
Date
El
Final - S K F & R (4060)
❑
Final - Planning
E7
Final - Public Works (4080)
Approved
Approved
Approved
By
Date
By
Date
By
Date
❑
Final - Building (4050)
Approved
By
Date 11 a
❑ Rough Electrical ❑ Final Electrical ❑ Right of Way
Approved Approved Approved
By Date By Date By Date