21-100627-Permit FinalCity of Federal Way
Community Development Dept.
33325 8th Ave S
Federal Way, WA 98003
Ph: (253) 835-2607 Fax: (253) 835-2609
Project Name: MERIDIAN COURT APARTMENTS, BUILDING 1
Project Address: 31420 23RD AVE S
Building - Multi Family
Permit #:21-100627-00-MF
Inspection Request Line: (253) 835-3050
Parcel Number: 092104 9190
Project Description: BLUEBEAM - Sheetrock and firestopping for penetration of fire -rated wall system.
Owner
Applicant
Contractor
Lender
FAIRFIELD MERIDIAN COURT LP
CHRISTOPHER FARIASBUILDING
BUILDING RESOURCES INC
OWNER IS LENDER
;55 MIRA SORRENTO PL SUITE 11
RESOURCES INC
18386 REDMOND WAY
SAN DIEGO CA 92121
386 REDMOND WAY NE UNIT 183
REDMOND WA 98052
REDMOND WA 98052
Census Category: 434 - Residential alt/add - no change in number of units
Includes:
# 1
#2
#3
#4
Occupancy Class:
Construction Type:
Occupancy Load:
Floor Area (sq. ft.)
Additional Permit Information
Mechanical to be Included? .................................... No Number of Stories .... ......................... ___ .......... 1—. 2
Is this an Online or O.T.C. application? .................. No Permit for Building Shell Only?.............................. No
Plumbing to be Included? ........................................ No
Total Valuation: 7,000.00
No Fixtures Associated With This Permit I+
PERMIT EXPIRES Sunday, 29 August, 2021
Permit Issued on Tuesday, March 2, 2021
I hereby certify that the above information is correct and that the construction on the above described property
and the occupancy and the use will be in accordance with the laws, rules and regulations of the State of
Washington and the City of Federal Way.
Owner or agent: Date:
V�Iool)l
CITY OF
Federal Way
THIS CARD IS TO REMAIN ON -SITE
Construction Inspection Record
INSPECTION REQUESTS: (253) 835-3050
PERMIT #: 21 100627 00 Address: 31420 23RD AVE S
Project: FAIRFIELD MERIDIAN COURT LP FEDERAL WAY WA 98003-5550
Scheduled inspections may be failed if this card is not on -site. DO NOT LOSE THIS CARD. Inspections are listed as close to sequential order as possible
(read left to right, top to bottom). Please schedule inspections as appropriate. Work must not be covered until it is approved. Check with your inspector if
you are unsure about any of the inspections or the inspection sequence. On -going inspections are logged on the back of this card.
Q Footings/Setback (4110) ® Foundation Wall (4115) 0 Drainage/Downspout (4040)
Approved to place concrete Approved to place concrete Approved to backfi[I
By Date By Date By Date
Re -steel (4215)
5❑
Slab/Concrete Floor (4255)
®
Underfloor Framing (4285)
Approved to place concrete or grout
Approved to place concrete
Approved to sheath floor
By
Date
By
Date
By
Date
0
Floor Sheathing (4105)
®
Shear Walls (4245)
Roof Sheathing (4220)
Approved to install flooring
Approved to install siding
Approved to install roofing
By
Date
By
Date
By
Date
10
Fire/Draft Stops (4095)
Prior to scheduling a Framing inspection;
11
Framing (4120)
Approved
Electrical, Plumbing & Mechanical Rough -in
Approved to insulate
and Fire/Draft Stop inspections must be signed -
By
Date
13
off and approved. IBC 109.3.4
Gypsum Wallboard Nailing (4130)
By
14
Date
Suspended Ceiling Grid (4265)
1? Insulation (4150)
Approved to install wallboard
Approved to install mud & tape
Approved to drop tile
By
Date
By
Date
By
Date
Final - S K F & R (4060)
16 Final - Building (4050)
By
Approved
Date
By
Approved
#31J Date 3I;2j 1j',
Q
Rough Electrical
Final Electrical
Right of Way
Approved
Approved
Approved
By
Date
By
Date
By
Date