21-103092City of Federal Way
Community Development Dept.
33325 8th Ave S
Federal Way, WA 98003
Ph: (253) 835-2607 Fax: (253) 835-2609
Project Name: VILLA CAPRI BLDG D
Project Address: 2511 S 286TH PL
Building - Multi Family
Permit #:21-103092-00-MF
Inspection Request Line: (253) 835-3050
Parcel Number: 552900 0200
Project Description: BLUEBEAM - Install a box (2x10 fire treated lumber with a size approx 48" x 19") below the
1-Hour rated ceiling to house an ERV in the main living area. The ERV is contained in the
mechanical permit. The box could not be inspected from the mechanical permit. 26 Units. 1 per
unit.
Owner
Applicant
Con tr
Lender
MSC GP 2 LLC
CRAIG CHRISTENSENRESICON
RESICON ENERAL)
1200 S 336TH ST
LLC
I. ST
FEDERAL WAY WA 98003
3914 CENTER ST
98409
rMA
TACOMA WA 98409
d' r
Census Category: 434 - Residential algadd - no chan nlber of units
Includes:
#1 "
42
#3
#4
Occupancy Class:
Construction Type:
Occupancy Load:
#
Floor Area
Additional Permit Information
Mechanical to be Included? .................... .... No Number of Stories................................................... I
Is this an Online or O.T,C p 'cat ............... No Permit for Building Shell Only?.............................. No
Plumbing to be Included..11 No
Total Valuation: 2,600.00NJ
No Fixtures ted With This Permit It
CONDITIONS:
Fire inspection is not required.
PERMIT EXPIRES Sunday, 13 February, 2022
Permit Issued on Tuesday, August 17, 2021
I hereby certify that the above information is correct and that the construction on the above described property
and the occupancy and the use will rda hIF e,With the laws, rules and regulations of the State of
Was " d tof Federal Way.
C
Owner or agent: Date:
CITY OF 401�&
Federal Way
THIS CARD IS TO REMAIN ON -SITE
Construction Inspection Record
INSPECTION REQU TS: (253) 835-3050
PERMIT #: 21 103092 00 Address: 2511 S 286TH PL Bldg D
Project: MSC GP 2 LLC FEDERAL WAY WA
Scheduled inspections may be failed if this card is not on -site. DO NOT LOSE THIS CARD. Inspections are listed as close to sequential order as possible
(read left to right, top to bottom). Please schedule inspections as appropriate. Work must not be covered until it is approved. Check with your inspector if
you are unsure about any of the inspections or the inspection sequence. On -going inspections are logged on the back of this card.
1❑ Initial Erosion Control (4365) ® Footings/Setback (4110) Foundation Wall (4115)
To be done PRIOR to breaking ground Approved to place concrete Approved to place concrete
By Date By Date By Date
El Drainage/Downspout (4040) Re -steel (4215) ® Slab/Concrete Floor (4255)
Approved to backfill Approved to place concrete or grout Approved to place concrete
By Date By Date By Date
®
Underfloor Framing (4285)
®
Floor Sheathing (4105)
®
Shear Walls (4245)
Approved to sheath floor
Approved to install flooring
Approved to install siding
By
Date
By
Date
By
Date
i�
Roof Sheathing (4220)
11
Fire/Draft Stops (4095)
9 z
Interim Erosion Control (4370)
Approved to install roofing
Approved
Approved
By
Date
By
Date
By
Date
EElectrical,
rior to scheduling a Framing inspection; 13 Framing (4120) 14 Insulation (4150)
Plumbing & Mechanical Rough -in Approved to insulate Approved to install wallboard
Fire/Draft Stop inspections must be signed -
off and approved. IBC 109.3.4 By Date By Date
5
Gypsum Wallboard Nailing (4130)
7S
Suspended Ceiling Grid (4265)
EE
Final - S K F & R (4060)
Approved to install mud & tape
Approved to drop tile
Approved
By
Date
By
Date
By
Date
i Il
Final - Planning
Final Erosion Control (4375)
xt]
Final - Building (4050)
Approved
Approved
Approved
By
Date
By
Date
By
Date
Rough Electrical
Final Electrical
Right of Way
Approved
Approved
Approved
By
Date
By
Date
By
Date