21-102929-UP-Drainage Technical Information Report-07-16-2021-V1
Civil Engineers ● Structural Engineers ● Landscape Architects ● Community Planners ● Land Surveyors
Technical Information Report
PREPARED FOR:
Federal Way Public Schools
33330 8th Avenue South
Federal Way, WA 98003
PROJECT:
Federal Way High School
Pre-Apprenticeship Space
30611 16th Avenue South
Federal Way, WA 98003
2210134.10
2210134.10PREPARED BY:
James A. Daley, EIT
Project Engineer
REVIEWED BY:
Lucas Johnson, PE, LEED AP
Project Manager
DATE:
July 2021
Technical Information Report
PREPARED FOR:
Federal Way Public Schools
33330 8th Avenue South
Federal Way, WA 98003
PROJECT:
Federal Way High School
Pre-Apprenticeship Space
30611 16th Avenue South
Federal Way, WA 98003
2210134.10
2210134.10PREPARED BY:
James A. Daley, EIT
Project Engineer
REVIEWED BY:
Lucas Johnson, PE, LEED AP
Project Manager
DATE:
July 2021
I hereby state that this Technical
Information Report for the Federal Way
High School Pre-Apprenticeship Space
project was prepared by me or under my
supervision, and meets the standard of
care and expertise that is usual and
customary in this community for
professional engineers. I understand that
King County does not and will not assume
liability for the sufficiency, suitability, or
performance of drainage facilities
prepared by me.
07/08/2021
0
Technical Information Report
Federal Way High School Pre-Apprenticeship Space i
2210134.10
Table of Contents
Section Page
1.0 Project Overview ......................................................................................................................... 1-1
Purpose and Scope.......................................................................................................... 1-1
Existing Conditions........................................................................................................... 1-1
Post-Development Conditions ......................................................................................... 1-2
Section 1.0 Figures
Figure 1-1 ......... TIR Worksheet
Figure 1-2 ......... Site Location Map
Figure 1-3 ......... Drainage Basin and Site Map
Figure 1-4 ......... Table A
2.0 Conditions and Requirements Summary ................................................................................. 2-1
Core Requirements .......................................................................................................... 2-1
2.1.1 CR 1 - Discharge at the Natural Location ........................................................... 2-1
2.1.2 CR 2 - Offsite Analysis ........................................................................................ 2-1
2.1.3 CR 3 - Flow Control ............................................................................................ 2-1
2.1.4 CR 4 - Conveyance System ................................................................................ 2-1
2.1.5 CR 5 - Erosion and Sediment Control................................................................. 2-1
2.1.6 CR 6 - Maintenance and Operations .................................................................. 2-1
2.1.7 CR 7 - Financial Guarantees and Liability .......................................................... 2-2
2.1.8 CR 8 - Water Quality ........................................................................................... 2-2
2.1.9 CR 9 – Flow Control Best Management Practices (BMPs) ................................ 2-2
Special Requirements ...................................................................................................... 2-2
2.2.1 SR 1 - Other Adopted Area-Specific Requirements ........................................... 2-2
2.2.2 SR 2 - Floodplain/Floodway Delineation ............................................................. 2-2
2.2.3 SR 3 - Flood Protection Facilities........................................................................ 2-2
2.2.4 SR 4 - Source Control ......................................................................................... 2-2
2.2.5 SR 5 - Oil Control ................................................................................................ 2-3
Section 2.0 Figures
Figure 2-1 ......... Flood Insurance Rate Map
Figure 2-2 ......... Bioretention Sizing Calculations
Technical Information Report
Federal Way High School Pre-Apprenticeship Space ii
2210134.10
3.0 Offsite Analysis ........................................................................................................................... 3-1
4.0 Flow Control and Water Quality Facilities Analysis and Design ........................................... 4-1
Flow Control ..................................................................................................................... 4-1
4.1.1 Existing Site Hydrology (Part A) .......................................................................... 4-1
4.1.2 Post Development Site Hydrology (Part B) ......................................................... 4-1
4.1.3 Performance Standards (Part C) ........................................................................ 4-1
4.1.4 Flow Control System (Part D) ............................................................................. 4-1
4.1.5 Water Quality System (Part E) ............................................................................ 4-1
5.0 Conveyance System Analysis and Design ............................................................................... 5-1
Section 5.0 Figures
Figure 5-1 ......... Conveyance Calculations
6.0 Special Reports and Studies ..................................................................................................... 6-1
Section 6.0 Figures
Figure 6-1 ......... Technical Information Report (Springline Design, LLC, August 1, 2014)
Figure 6-2 ......... Geotechnical Engineering Report (Associated Earth Sciences, Inc.,
February 8, 2021)
7.0 Other Permits .............................................................................................................................. 7-1
8.0 CSWPPP Analysis and Design .................................................................................................. 8-1
ESC Plan Analysis and Design (Part A) .......................................................................... 8-1
8.1.1 ESC Maintenance ............................................................................................... 8-2
8.1.2 ESC Supervisor................................................................................................... 8-2
8.1.3 Documentation .................................................................................................... 8-2
8.1.4 Review Timing ..................................................................................................... 8-2
Stormwater Pollution Prevention and Spill (SWPPS) Plan Design (Part B) .................... 8-2
8.2.1 Pollution and Spill Prevention Source Controls and BMPs ................................ 8-3
8.2.2 Responsible Personnel and Contact Information ............................................... 8-4
8.2.3 Pollution and Spill Prevention Worksheets ......................................................... 8-5
8.2.4 Disposal Methods................................................................................................ 8-5
Section 8.0 Figures
Figure 8-1 ......... ESC Maintenance Report
Figure 8-2 ......... CSWPP Forms
Figure 8-3 ......... Pollution Prevention Inspection Reports, Spill Prevention Monitoring, and
Spill Incident Reports
Technical Information Report
Federal Way High School Pre-Apprenticeship Space iii
2210134.10
9.0 Bond Quantities, Facilities Summaries, and Declarations of Covenant ............................... 9-1
Section 9.0 Figures
Figure 9-1 ......... Stormwater Facility Summary Sheet
Figure 9-2 ......... Stormwater Facility Sketches
Figure 9-3 ......... Declaration of Covenant for Inspection and Maintenance of Stormwater
Facilities and BMPs
10.0 Operations and Maintenance Plan .......................................................................................... 10-1
Facility Descriptions ....................................................................................................... 10-1
10.1.1 Bioretention BMP .............................................................................................. 10-1
10.1.2 Conveyance Pipes and Ditches ........................................................................ 10-1
Maintenance Requirements ........................................................................................... 10-1
Section 10.0 Figures
Figure 10-1 ....... Maintenance Requirements for Flow Control, Conveyance, and Water
Quality Facilities
11.0 Conclusion ................................................................................................................................. 11-1
Technical Information Report
Federal Way High School Pre-Apprenticeship Space
2210134.10
Section 1
Project Overview
Technical Information Report
Federal Way High School Pre-Apprenticeship Space 1-1
2210134.10
1.0 Project Overview
Purpose and Scope
This report accompanies the civil engineering plans and documents for the Federal Way High
School Pre-Apprenticeship Space. Federal Way High School is located at 30611 16th Avenue
South, Federal Way, Washington. The location of work is between the Federal Way High School
main building to the east and 14th Avenue South to the west, north of South 308th Street. The site
is to be accessed via 14th Avenue South. The site is located on Tax Parcel No. 0821049001 in
Section 8, Township 21 North, Range 4 East of the Willamette Meridian, city of Federal Way,
King County, Washington. Refer to Figure 1-1 for the Technical Information Report (TIR)
Worksheet and Figure 1-2 for the Site Location Map.
The Federal Way High School Pre-Apprenticeship Space project proposes the construction of a
new 1,152-square foot pole barn building, along with associated outdoor student seating, a rain
garden, and gravel surfacing. Stormwater generated from the pole barn roof will be collected via
downspouts and roof drains and conveyed to a bioretention facility (rain garden). Stormwater
generated by other impervious surfaces will maintain existing drainage patterns and flow into an
existing catch basin located at the east side of the Pre-Apprenticeship Space site.
The Federal Way High School property is completely developed and includes paved roadways
and parking lots, landscaped areas, sport/recreation fields and facilities, and a detention pond.
Currently the site is a 7,151-square foot landscaped area on the Federal Way High School
property. The project proposes 6,915 square feet of new impervious surfaces , including a
1,152-square foot roof, three 50-square foot seating walls, and 5,613 square feet of gravel
surfacing. No pollution generating impervious surfaces (PGIS) are proposed for this site.
The project site is located in the Lower Puget Sound Drainage Basin. There are no critical areas
on or adjacent to the site.
All construction proposed has been designed to meet the 2016 King County Surface Water
Design Manual (KCSWDM), as adopted by City Federal Way per the Addendum to the King
County Surface Water Manual (Addendum), January 8, 2017.
Existing Conditions
The property is currently fully developed and consists of the Federal Way High School main
building, sport/recreational fields and facilities with sidewalks, paved roadways and parking lots,
landscaped areas, and a detention pond. In the existing condition, the site and immediate
adjacent areas generally slope down from northeast to southwest, with elevations ranging from
467 to 460.
The site is located north of an existing parking lot, east of 14th Avenue South, south of existing
landscaped areas, and west of the high school main building. Stormwater on the existing site
sheet flows to an existing yard drain and existing catch basins. Stormwater is conveyed through
pipes to the existing stormwater detention pond. Refer to Figure 1-3 for a Drainage Basin and
Site Map.
Technical Information Report
Federal Way High School Pre-Apprenticeship Space 1-2
2210134.10
Post-Development Conditions
The project proposes to construct a new pole barn structure, along with associated student
seating walls, gravel surfacing, and a bioretention facility (rain garden). The pole barn will be
located in the central-western portion of the project site, with the associated student seating walls
in the northeast corner and the bioretention facility on the west side of the site. Stormwater runoff
from the roof of the new pole barn will be collected via downspouts and roof drain s and conveyed
to a new bioretention facility. Stormwater runoff from the gravel surfacing and seating walls will
sheet flow to the existing catch basins and associated existing stormwater facilities. The existing
stormwater facilities have been sized to accommodate roughly one additional acre of impervious
surfaces. Refer to the attached TIR by Springline Design, LLC (Figure 6-1) detailing the capacity
of the existing detention pond. The proposed developed site, including grading and drainage
amenities, can be viewed in Figure 1-4.
Technical Information Report
Federal Way High School Pre-Apprenticeship Space
2210134.10
Section 1.0 Figures
Figure 1-1 ......... TIR Worksheet
Figure 1-2 ......... Site Location Map
Figure 1-3 ......... Drainage Basin and Site Map
Figure 1-4 ......... Table A
CITY OF RENTON SURFACE WATER DESIGN MANUAL
2017 City of Renton Surface Water Design Manual 12/12/2016 8-A-1
REFERENCE 8-A
TECHNICAL INFORMATION REPORT (TIR)
WORKSHEET
Part 1 PROJECT OWNER AND
PROJECT ENGINEER Part 2 PROJECT LOCATION AND
DESCRIPTION
Project Owner _____________________________
Phone ___________________________________
Address __________________________________
_________________________________________
Project Engineer ___________________________
Company _________________________________
Phone ___________________________________
Project Name __________________________
CED Permit # ________________________
Location Township ________________
Range __________________
Section _________________
Site Address __________________________
_____________________________________
Part 3 TYPE OF PERMIT APPLICATION Part 4 OTHER REVIEWS AND PERMITS
Land Use (e.g., Subdivision / Short Subd.)
Building (e.g., M/F / Commercial / SFR)
Grading
Right-of-Way Use
Other _______________________
DFW HPA
COE 404
DOE Dam Safety
FEMA Floodplain
COE Wetlands
Other ________
Shoreline
Management
Structural
Rockery/Vault/_____
ESA Section 7
Part 5 PLAN AND REPORT INFORMATION
Technical Information Report Site Improvement Plan (Engr. Plans)
Type of Drainage Review
(check one):
Date (include revision
dates):
Date of Final:
Full
Targeted
Simplified
Large Project
Directed
__________________
__________________
__________________
Plan Type (check
one):
Date (include revision
dates):
Date of Final:
Full
Modified
Simplified
__________________
__________________
__________________
Figure 1-1
33330 8th Avenue South,
Federal Way, WA 98003
James A. Daley, EIT
AHBL, Inc.
(253) 383-2422
Federal Way Public Schools
(253) 261-5506
Federal Way High School
Pre-Apprenticeship Space
21 N
4 E
8
30611 16th Avenue South
Federal Way, WA 98003
X
X
X
Use Process 1 and
Engineering Permits
July 2021
Version 1July 2021
Version 1
REFERENCE 8: PLAN REVIEW FORMS AND WORKSHEET
TECHNICAL INFORMATION REPORT (TIR) WORKSHEET
12/12/2016 2017 City of Renton Surface Water Design Manual 8-A-2
Part 6 SWDM ADJUSTMENT APPROVALS
Type (circle one): Standard / Blanket
Description: (include conditions in TIR Section 2)
____________________________________________________________________________________
____________________________________________________________________________________
____________________________________________________________________________________
Approved Adjustment No. ______________________ Date of Approval: _______________________
Part 7 MONITORING REQUIREMENTS
Monitoring Required: Yes / No
Start Date: _______________________
Completion Date: _______________________
Describe: _________________________________
_________________________________________
_________________________________________
Re: SWDM Adjustment No. ________________
Part 8 SITE COMMUNITY AND DRAINAGE BASIN
Community Plan: ____________________________________________________________________
Special District Overlays: ______________________________________________________________
Drainage Basin: _____________________________________________________________________
Stormwater Requirements: _____________________________________________________________
Part 9 ONSITE AND ADJACENT SENSITIVE AREAS
River/Stream ________________________
Lake ______________________________
Wetlands ____________________________
Closed Depression ____________________
Floodplain ___________________________
Other _______________________________
_______________________________
Steep Slope __________________________
Erosion Hazard _______________________
Landslide Hazard ______________________
Coal Mine Hazard ______________________
Seismic Hazard _______________________
Habitat Protection ______________________
_____________________________________
N/A
Federal Way High School
Lower Puget Sound
REFERENCE 8-A: TECHNICAL INFORMATION REPORT (TIR) WORKSHEET
TECHNICAL INFORMATION REPORT (TIR) WORKSHEET
2017 City of Renton Surface Water Design Manual 12/12/2016 Ref 8-A-3
Part 10 SOILS
Soil Type
______________________
______________________
______________________
______________________
Slopes
________________________
________________________
________________________
________________________
Erosion Potential
_________________________
_________________________
_________________________
_________________________
High Groundwater Table (within 5 feet)
Other ________________________________
Sole Source Aquifer
Seeps/Springs
Additional Sheets Attached
Part 11 DRAINAGE DESIGN LIMITATIONS
REFERENCE
Core 2 – Offsite Analysis_________________
Sensitive/Critical Areas__________________
SEPA________________________________
LID Infeasibility________________________
Other________________________________
_____________________________________
LIMITATION / SITE CONSTRAINT
_______________________________________
_______________________________________
_______________________________________
_______________________________________
_______________________________________
_______________________________________
Additional Sheets Attached
Part 12 TIR SUMMARY SHEET (provide one TIR Summary Sheet
per Threshold Discharge Area)
Threshold Discharge Area:
(name or description)
Core Requirements (all 8 apply):
Discharge at Natural Location Number of Natural Discharge Locations:
Offsite Analysis Level: 1 / 2 / 3 dated:__________________
Flow Control (include facility
summary sheet)
Standard: _______________________________
or Exemption Number: ____________
On-site BMPs: _______________________________
Conveyance System Spill containment located at: _____________________________
Erosion and Sediment Control /
Construction Stormwater Pollution
Prevention
CSWPP/CESCL/ESC Site Supervisor: _____________________
Contact Phone: _________________________
After Hours Phone: _________________________
1-5%, at site MinimalSilty Fine to Medium Sand
with Gravel
1
Bioretention
TBD
REFERENCE 8: PLAN REVIEW FORMS AND WORKSHEET
TECHNICAL INFORMATION REPORT (TIR) WORKSHEET
12/12/2016 2017 City of Renton Surface Water Design Manual 8-A-4
Part 12 TIR SUMMARY SHEET (provide one TIR Summary Sheet
per Threshold Discharge Area)
Maintenance and Operation Responsibility (circle one): Private / Public
If Private, Maintenance Log Required: Yes / No
Financial Guarantees and Liability Provided: Yes / No
Water Quality (include facility
summary sheet)
Type (circle one): Basic / Sens. Lake / Enhanced Basic / Bog
or Exemption No. _______________________
Special Requirements (as applicable):
Area Specific Drainage
Requirements
Type: SDO / MDP / BP / Shared Fac. / None
Name: ________________________
Floodplain/Floodway Delineation Type (circle one): Major / Minor / Exemption / None
100-year Base Flood Elevation (or range): _______________
Datum:
Flood Protection Facilities Describe:
Source Control
(commercial / industrial land use)
Describe land use:
Describe any structural controls:
Oil Control High-Use Site: Yes / No
Treatment BMP: _________________________________
Maintenance Agreement: Yes / No
with whom? _____________________________________
Other Drainage Structures
Describe:
N/A
Commercial (public school)
Conveyance pipes.
236 square foot bioretention (rain garden).
No Pollution Generating Surfaces
REFERENCE 8-A: TECHNICAL INFORMATION REPORT (TIR) WORKSHEET
TECHNICAL INFORMATION REPORT (TIR) WORKSHEET
2017 City of Renton Surface Water Design Manual 12/12/2016 Ref 8-A-5
Part 13 EROSION AND SEDIMENT CONTROL REQUIREMENTS
MINIMUM ESC REQUIREMENTS
DURING CONSTRUCTION
Clearing Limits
Cover Measures
Perimeter Protection
Traffic Area Stabilization
Sediment Retention
Surface Water Collection
Dewatering Control
Dust Control
Flow Control
Control Pollutants
Protect Existing and Proposed
BMPs/Facilities
Maintain Protective BMPs / Manage
Project
MINIMUM ESC REQUIREMENTS
AFTER CONSTRUCTION
Stabilize exposed surfaces
Remove and restore Temporary ESC Facilities
Clean and remove all silt and debris, ensure
operation of Permanent BMPs/Facilities, restore
operation of BMPs/Facilities as necessary
Flag limits of sensitive areas and open space
preservation areas
Other _______________________
Part 14 STORMWATER FACILITY DESCRIPTIONS (Note: Include Facility Summary and Sketch)
Flow Control Type/Description Water Quality Type/Description
Detention
Infiltration
Regional Facility
Shared Facility
On-site BMPs
Other
________________
________________
________________
________________
________________
________________
Vegetated Flowpath
Wetpool
Filtration
Oil Control
Spill Control
On-site BMPs
Other
________________
________________
________________
________________
________________
________________
________________
Part 15 EASEMENTS/TRACTS Part 16 STRUCTURAL ANALYSIS
Drainage Easement
Covenant
Native Growth Protection Covenant
Tract
Other ____________________________
Cast in Place Vault
Retaining Wall
Rockery > 4′ High
Structural on Steep Slope
Other _______________________________
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x Bioretention
(rain garden)
REFERENCE 8: PLAN REVIEW FORMS AND WORKSHEET
TECHNICAL INFORMATION REPORT (TIR) WORKSHEET
12/12/2016 2017 City of Renton Surface Water Design Manual 8-A-6
Part 17 SIGNATURE OF PROFESSIONAL ENGINEER
I, or a civil engineer under my supervision, have visited the site. Actual site conditions as observed were
incorporated into this worksheet and the attached Technical Information Report. To the best of my
knowledge the information provided here is accurate.
____________________________________________________________________________________
Signed/Date
David Nason, PE AHBL Inc.
DRAWN BY:DATE:JOB NO.:
2215 North 30th Street, Suite 300
Tacoma, WA 98403
253.383.2422 TEL 253.383.2572 FAX
Fairwood Golf and Country Club Improvements
Site Location Map
James A. Daley 07/2/2021 2210134.10
1-2
Site
2215 North 30th StreetSuite 300Tacoma, WA 98403253.383.2422 TEL253.383.2572 FAXFederal Way High School Pre-Apprenticeship SpaceDrainage Basin and Site MapFigure1-3PROJECT BASIN0.00 AC PERVIOUS0.16 AC IMPERVIOUSBIORETENTION CELL(MANAGES ROOF RUNOFF)PROPOSED BUILDING - 1,152 SFEXISTING CATCH BASIN TOREMAIN, COLLECT RUNOFFFROM GRAVEL SURFACINGEXISTING STORM PIPE,CONVEYS RUNOFF TOEXISTING DETENTIONPOND ON WEST SIDEOF PROJECT PARCEL
Table A
Proposed Impervious Surface: Fill in all applicable blanks below to list the square footage of all new and
existing impervious surface areas on your parcel. When calculating impervious surface areas for
buildings do not list the living/useable space square-footage, instead list the building roof square-
footage measured to the outside edge of the eve or gutter.
Impervious New Existing Total
Roof Area
(House, Attached Garage,
Covered Patio, Covered Deck, sq. ft. sq. ft. sq. ft.
Covered Porch)
Roof Area
(Detached Garage) sq. ft. sq. ft. sq. ft.
Roof Area
(All Out Buildings) sq. ft. sq. ft. sq. ft.
On-site Driveway Area sq. ft. sq. ft. sq. ft.
Off-site Driveway Area sq. ft. sq. ft. sq. ft.
Walkways / Sidewalks / Stepping Stone Area sq. ft. sq. ft. sq. ft.
Uncovered Porch and / or Patios Area sq. ft. sq. ft. sq. ft.
Uncovered Decks Area sq. ft. sq. ft. sq. ft.
Replaced Impervious Area
(Considered New Impervious) sq. ft. sq. ft. sq. ft.
All Other Impervious Areas sq. ft. sq. ft. sq. ft.
Total New Impervious Surface Area sq. ft.
Total Existing Impervious Surface Area sq. ft.
Total Impervious Areas sq. ft.
Total Clearing Limits, Site Disturbance / Graded Areas
(Include Septic Drainfields Primary and Reserve) sq. ft.
Total New Pervious Areas
[(Total Clearing Limits, Site Disturbance/Graded Areas) – (Total New Impervious Areas)] sq. ft.
Total of Excavation Volume Cubic Yard
Total of Fill Volume (Exported) Cubic Yard
Total of Fill Volume (Imported) Cubic Yard
For DPER Staff Use ONLY
Parcel Number: Application Number:
Approved By: Date:
5,7635,763
6,915
0
6,915
7,151
236
70 (FILL)
0
40
0
1,152 0 1,152
0 0 0
0 0
0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
Technical Information Report
Federal Way High School Pre-Apprenticeship Space
2210134.10
Section 2
Conditions and Requirements Summary
Technical Information Report
Federal Way High School Pre-Apprenticeship Space 2-1
2210134.10
2.0 Conditions and Requirements Summary
Core Requirements
2.1.1 CR 1 - Discharge at the Natural Location
The project site currently slopes from north to south. Stormwater drains by means of overland
flow to one of two onsite catch basins. The catch basins are connected to an enclosed pipe
network that conveys stormwater to an existing detention pond located at the west side of the
project parcel.
In the developed condition, stormwater from the building roof will be conveyed to a bioretention
facility (rain garden) that will overflow to the existing storm pipe system. Runoff generated by
other hard surfaces will maintain existing drainage patterns and will be collected by the existing
catch basins to remain.
Stormwater discharge created by the proposed improvements will not adversely affect
downstream properties or drainage systems.
2.1.2 CR 2 - Offsite Analysis
An offsite analysis is required for this project and is discussed in Section 3.0.
2.1.3 CR 3 - Flow Control
This project proposes 6,915 square feet (0.16 acre) of new non-pollution generating impervious
(NPGIS) surfaces. The existing stormwater detention pond was designed with the capacity for an
additional 0.94 acre of impervious surfaces in the case of redevelopment. This project proposes
to use the additional capacity. Post-redevelopment will leave the pond with an additional capacity
of 0.78 acre of impervious surfaces for future redevelopment. Because of this, flow control
measures are not required. Refer to page 23 of the 2014 Federal Way High School TIR,
Section IV – Flow Control and Water Quality Facility Analysis and Design (Figure 6-1 in this
report).
2.1.4 CR 4 - Conveyance System
The proposed conveyance systems for this project are composed of underground piped. The
design and calculations for the proposed conveyance systems are included in Section 5.0. The
conveyance systems meet all requirements for new systems outlined in Section 1.2.4.1 of the
KCSWDM.
2.1.5 CR 5 - Erosion and Sediment Control
An erosion and sediment control plan was developed for this site in accordance with the
KCSWDM and to conform to the requirements of the National Pollutant Discharge Elimination
System (NPDES) Construction Stormwater General Permit, issued by the Department of Ecology
(DOE). The full erosion and sediment control plan is described in Section 8.0 and is depicted on
the project drawings.
2.1.6 CR 6 - Maintenance and Operations
The onsite drainage facilities will be privately maintained by Federal Way Public Schools. An
Operations and Maintenance Manual is provided in Section 10.0.
Technical Information Report
Federal Way High School Pre-Apprenticeship Space 2-2
2210134.10
2.1.7 CR 7 - Financial Guarantees and Liability
The owner and contractor will obtain all necessary permits required by City of Federal Way prior
to the beginning of construction. Federal Way Public Schools is exempt from typical bonding
requirements because it is a public agency. Because of this, a Bond Quantity Worksheet is not
required and has not been prepared.
2.1.8 CR 8 - Water Quality
The proposed project does not include PGIS, and therefore water treatment is not required.
2.1.9 CR 9 – Flow Control Best Management Practices (BMPs)
The Federal Way High School Pre-Apprenticeship Space site is classified as a Large Lot BMP
per Section 1.2.9.2.2 of the KCSWDM. Below is a summary of the flow control BMPs that were
considered.
1. Full Dispersion – This BMP is infeasible because there is insufficient area available to
disperse stormwater.
2. Full Infiltration of Roof Runoff – Onsite soils consist of glacial till, which is not suitable for
stormwater infiltration. This BMP is infeasible because of the poorly infiltrating soils.
3. Bioretention – A bioretention cell is proposed to manage stormwater from the building roof.
Refer to Figure 2-2 for Bioretention Sizing Calculations. Refer to Section 4.0 for more
information on the proposed bioretention facility. No further flow control BMPs ar e
required.
Special Requirements
2.2.1 SR 1 - Other Adopted Area-Specific Requirements
To our knowledge, no other adopted area-specific requirements are applicable to the project site.
2.2.2 SR 2 - Floodplain/Floodway Delineation
Federal Emergency Management Agency (FEMA) Flood Insurance Rate Map No. 53033C1230G
was reviewed for this project. It indicates that the project site is within a Zone X area. This area
is determined to be outside of the 500-year floodplain. Refer to Figure 2-1 for the Flood
Insurance Rate Map.
2.2.3 SR 3 - Flood Protection Facilities
The project site does not contain, nor is it adjacent to, any existing flood protection facilities.
Project improvements do not include flood protection measures.
2.2.4 SR 4 - Source Control
The King County Stormwater Pollution Prevention Manual (KCSPPM) will be referenced for
source control measures, in addition to erosion and sediment control measures, during
construction. For construction source controls, see Section 8.0, CSWPPP Analysis and Design.
For post-construction source controls, see Section 10.0, Operations and Maintenance Plan.
Technical Information Report
Federal Way High School Pre-Apprenticeship Space 2-3
2210134.10
2.2.5 SR 5 - Oil Control
The project site is not considered a high-use site. Therefore, it is not subject to oil control
requirements.
Technical Information Report
Federal Way High School Pre-Apprenticeship Space
2210134.10
Section 2.0 Figures
Figure 2-1 ......... Flood Insurance Rate Map
Figure 2-2 ......... Bioretention Sizing Calculations
Civil Engineers
Structural Engineers
Landscape Architects
Community Planners
Land Surveyors
Neighbors
TACOMA
2215 North 30th Street
Suite 300
Tacoma, WA 98403-3350
253.383.2422 TEL
www.ahbl.com
Project__________________________
Subject _________________________
With/To_________________________
Address_________________________
Date____________________________
Project No.______________________
Phone__________________________
FAX # _________________________
# Faxed Pages ___________________
By_____________________________
Page _____ of _____
Calculations
Fax
Memorandum
Meeting Minutes
Telephone Memo
Please contact AHBL with any questions, comments, or concerns about the above calculations. Thank you.
1. Bioretention sized per section 1.2.9.2.1 of the KCSWDM:
- The project is within the Urban Growth Area (UGA)
- On-site soils are described as till soils per the USDA soils data
- Bioretention volume based on 0.6 inches of equivalent storage depth
2. Area draining to bioretention ~ 1152 sf
- Bioretention Volume = (1152 sf)*(0.6 inch)*(1 ft/ 12 inch) = 57.60 CF
3. The bioretention facility will be 1 foot deep with a bottom area of 6.5' x
13.5' and a top area of 12.5' x 19.5'. The bioretention facility has a capacity
of 60 cubic feet.
Technical Information Report
Federal Way High School Pre-Apprenticeship Space
2210134.10
Section 3
Offsite Analysis
Technical Information Report
Federal Way High School Pre-Apprenticeship Space 3-1
2210134.10
3.0 Offsite Analysis
An offsite analysis was performed by Springline Design, LLC as part of the recent Federal Way
High School construction project. Refer to the Springline Design TIR, Section III, in Figure 6-1 of
this report. The analysis has been reviewed by AHBL and is confirmed as accurate.
Technical Information Report
Federal Way High School Pre-Apprenticeship Space
2210134.10
Section 4
Flow Control and Water Quality Facilities Analysis and
Design
Technical Information Report
Federal Way High School Pre-Apprenticeship Space 4-1
2210134.10
4.0 Flow Control and Water Quality Facilities Analysis and Design
Flow Control
4.1.1 Existing Site Hydrology (Part A)
The existing site drains by means of overland flow to an existing yard drain and catch basin
located within the project limits. Stormwater is conveyed in an enclosed pipe network to the
existing detention pond located along the west side of the project parcel.
4.1.2 Post Development Site Hydrology (Part B)
The new Pre-Apprenticeship Space will replace an existing landscaped area. A network of roof
downspouts and roof drains will be installed to capture runoff generated by the pole barn roof and
convey it to the proposed bioretention facility. Runoff generated by other hard surfaces will
maintain the current flow path and will flow into the existing catchment structures located in the
project limits.
A bioretention facility is proposed to provide flow control for the pole barn roof. The bioretention
facility was sized using the guidelines in the KCSWDM. Refer to Figure 2-2 for Bioretention
Sizing Calculations.
4.1.3 Performance Standards (Part C)
Flow control is provided by an existing stormwater detention pond located along the west side of
the project parcel. The project will apply flow control BMPs in the form of a bioretention facility to
meet Core Requirement (CR) 9. As discussed further in Section 5.0, the proposed conveyance
system was designed to convey the 100-year, 24-hour design storm event (refer to Figure 5-1 for
conveyance calculations). No pollution generating surfaces are proposed, and therefore water
treatment will not be provided.
4.1.4 Flow Control System (Part D)
As discussed in Section 2.1.9, the project proposes a bioretention facility as a flow control BMP.
Refer to Figure 2-2 for Bioretention Sizing Calculations and Figure 9-2 for a sketch and location of
the proposed bioretention facility.
4.1.5 Water Quality System (Part E)
As discussed in Section 2.1.8, the project is exempt from water quality requirements. The project
will not add pollution generating surfaces.
Technical Information Report
Federal Way High School Pre-Apprenticeship Space
2210134.10
Section 5
Conveyance System Analysis and Design
Technical Information Report
Federal Way High School Pre-Apprenticeship Space 5-1
2210134.10
5.0 Conveyance System Analysis and Design
Based on Section 1.2.4.1 of the KCSWDM, the pipe system was designed to convey and contain
at least the peak runoff rate of the 25-year design storm and the 100-year storm event without
creating or aggravating a severe flooding or erosion problem. The new conveyance line is a
6-inch pipe with at least a 0.5 percent slope. The size, material, and slope of the pipes chosen
are sufficient to convey the 100-year, 24-hour storm.
A conveyance analysis was completed using StormSHED2G software and the Santa Barbara
Urban Hydrograph (SBUH) method. Refer to Figure 5-1 for the Conveyance Calculations.
Technical Information Report
Federal Way High School Pre-Apprenticeship Space
2210134.10
Section 5.0 Figures
Figure 5-1 ......... Conveyance Calculations
Project: Federal Way High School Pre-Apprenticeship Space Project No.: 2210134.10
Subject: Conveyance Calculations Date: 07.03.2021
By: Lucas Johnson
The Lake City Community Church expansion project stormwater conveyance system has been designed
to convey the 25-year, 24-hour peak flowrate. This flowrate was calculated with StormShed2G™
software, using the Santa Barbara Urban Hydrograph (SBUH) method. The following parameters were
used in the design of the stormwater conveyance system:
Design storms: 100-year, 24-hour
Rainfall values: 4.2 inches (KCSWDM Figure 3.2.1.D)
Methodology: Santa Barbara Urban Hydrograph (SBUH)
Rainfall distribution: Type 1A (per USDA Urban Hydrology for Small Watersheds TR-55
Figure B-2)
Curve Numbers: Impervious surfaces – 98
Pervious surfaces – NA
Manning’s coefficient: 0.012 (PVC pipe)
Appended on: 06:58:50 Saturday, July 03, 2021
DEV Event Summary
Event Peak Q (cfs) Peak T (hrs) Hyd Vol (acft) Area (ac) Method Raintype
100 year 0.0288 8.00 0.0099 0.0300 SBUH TYPE1A
Record Id: DEV
Design Method SBUH Rainfall type TYPE1A
Hyd Intv 10.00 min Peaking Factor 484.00
Abstraction Coeff 0.20
Pervious Area (AMC 2) 0.00 ac DCIA 0.03 ac
Pervious CN 0.00 DC CN 98.00
Pervious TC 0.00 min DC TC 5.00 min
Directly Connected CN Calc
Description SubArea Sub cn
Impervious surfaces (pavements, roofs, etc) 0.03 ac 98.00
DC Composited CN (AMC 2) 98.00
Directly Connected TC Calc
Type Description Length Slope Coeff Misc TT
Fixed 5.00 min
Directly Connected TC 5.00min
Licensed to: AHBL
Project Description
Friction Method Manning Formula
Solve For Normal Depth
Input Data
Roughness Coefficient 0.012
Channel Slope 0.00500 ft/ft
Diameter 0.50 ft
Discharge 0.03 ft³/s
Results
Normal Depth 0.09 ft
Flow Area 0.02 ft²
Wetted Perimeter 0.43 ft
Hydraulic Radius 0.05 ft
Top Width 0.38 ft
Critical Depth 0.08 ft
Percent Full 17.5 %
Critical Slope 0.00640 ft/ft
Velocity 1.24 ft/s
Velocity Head 0.02 ft
Specific Energy 0.11 ft
Froude Number 0.89
Maximum Discharge 0.46 ft³/s
Discharge Full 0.43 ft³/s
Slope Full 0.00002 ft/ft
Flow Type SubCritical
GVF Input Data
Downstream Depth 0.00 ft
Length 0.00 ft
Number Of Steps 0
GVF Output Data
Upstream Depth 0.00 ft
Profile Description
Profile Headloss 0.00 ft
Average End Depth Over Rise 0.00 %
Normal Depth Over Rise 17.53 %
Downstream Velocity Infinity ft/s
FWHS Pre-Apprenticeship Space
7/3/2021 7:04:36 AM
Bentley Systems, Inc. Haestad Methods Solution CenterBentley FlowMaster V8i (SELECTseries 1) [08.11.01.03]
27 Siemons Company Drive Suite 200 W Watertown, CT 06795 USA +1-203-755-1666 2of1Page
Proposed pipes have
capacity to convey
100-year 24-hour storm.
GVF Output Data
Upstream Velocity Infinity ft/s
Normal Depth 0.09 ft
Critical Depth 0.08 ft
Channel Slope 0.00500 ft/ft
Critical Slope 0.00640 ft/ft
FWHS Pre-Apprenticeship Space
7/3/2021 7:04:36 AM
Bentley Systems, Inc. Haestad Methods Solution CenterBentley FlowMaster V8i (SELECTseries 1) [08.11.01.03]
27 Siemons Company Drive Suite 200 W Watertown, CT 06795 USA +1-203-755-1666 2of2Page
Technical Information Report
Federal Way High School Pre-Apprenticeship Space
2210134.10
Section 6
Special Reports and Studies
Technical Information Report
Federal Way High School Pre-Apprenticeship Space 6-1
2210134.10
6.0 Special Reports and Studies
A Technical Information Report (TIR) was prepared by Springline Design, LLC, dated August 1,
2014, which is included as Figure 6-1 of this report. The 2014 TIR was prepared for the recently
constructed Federal Way High School and describes the extra capacity provided by the existing
pond, the storm drainage system located downstream from the project site, and other relevant
information.
A Geotechnical Engineering Report was prepared by Associated Earth Sciences, Inc., dated
February 8, 2021, which is included as Figure 6-2.
Technical Information Report
Federal Way High School Pre-Apprenticeship Space
2210134.10
Section 6.0 Figures
Figure 6-1 ......... Technical Information Report
(Springline Design, LLC, August 1, 2014)
Figure 6-2 ......... Geotechnical Engineering Report
(Associated Earth Sciences, Inc., February 8, 2021)
TECHNICAL INFORMATION REPORT
Project: Federal Way High School
30611 16th Ave S
Federal Way, WA 98003
Prepared For: SRG Partnership, Inc.
110 Union Street, Suite 300
Seattle, WA 98101
Fed. Way Proj. #13-101307-00-PC
Prepared By: Max Berde, PE
Reviewed By: Marc Errichetti, PE
Date: August 1, 2014
Federal Way High School Page 2 Project No. 13003
Springline Design LLC
TABLE OF CONTENTS
Section No. Subject Page No.
SECTION I PROJECT OVERVIEW .....................................................................4
SECTION II CONDITIONS AND REQUIREMENTS SUMMARY...................14
SECTION III OFFSITE ANALYSIS......................................................................16
SECTION IV FLOW CONTROL AND WATER QUALITY
FACILITY ANALYSIS AND DESIGN..........................................23
SECTION V CONVEYANCE SYSTEM ANALYSIS AND DESIGN................30
SECTION VI SPECIAL REPORTS AND STUDIES.............................................30
SECTION VII OTHER PERMITS ...........................................................................34
SECTION VIII EROSION AND SEDIMENT CONTROL ......................................34
SECTION IX BOND QUANTITIES ......................................................................35
SECTION X OPERATIONS AND MAINTENANCE MANUAL.......................35
LIST OF FIGURES
FIGURE 1 VICINITY MAP.................................................................................7
FIGURE 2 TIR WORKSHEET ............................................................................8
FIGURE 3 EXISTING SITE SOIL CONDITIONS ...........................................11
FIGURE 4 EXISTING LAND COVER .............................................................12
FIGURE 5 DEVELOPED LAND COVER ........................................................13
FIGURE 6 DOWNSTREAM STUDY AREA....................................................18
FIGURE 7 OFFSITE ANALYSIS MAP............................................................19
FIGURE 8 FLOW CONTROL TRADE AREAS...............................................26
FIGURE 9 FLOW CONTROL BMP TARGETED AREAS..............................27
FIGURE 10 BIORETENTION CATCHMENT AREAS.....................................29
FIGURE 11 BACKWATER ANALYSIS ............................................................33
Federal Way High School Page 3 Project No. 13003
Springline Design LLC
LIST OF APPENDIXES
APPENDIX A WATER QUALITY AND FLOW CONTROL CALCULATIONS
APPENDIX B OPERATION AND MAINTENANCE MANUAL
APPENDIX C BACKWATER ANALYSIS TABLES
APPENDIX D SEDIMENT POND SIZING
Federal Way High School Page 4 Project No. 13003
Springline Design LLC
SECTION I – PROJECT OVERVIEW
General Description:
This project consists of the demolition and reconstruction of Federal Way High School
(FWHS) on the existing school site. See Figure 1 for a vicinity map of the project area.
The new school construction will be completed in stages by a single contractor such that
the school grounds can remain occupied and operational throughout the redevelopment.
A separate early site work contract is intended to be awarded in early summer of 2014 to
allow for dry weather construction of the project detention pond and portions of the
proposed storm drain system.
ROW improvements for the project include improvements to S 304th Street and S 308th
Street to the north and south of the site. On the south margin of S 304th Street, curb,
gutter, sidewalk and a landscape strip will be constructed. On the north margin of S 308th
Street, from the west property line east to 14th Ave South, curb, gutter, sidewalk and a
landscape strip will be constructed. Storm drainage improvements will be constructed in
both right-of-ways.
This TIR includes details of the stormwater management for the completed project
including flow control and water quality analysis, erosion and sediment control, the TIR
worksheet, and operation and maintenance manual.
Existing Conditions:
ROW:
Existing conditions in the S 304th Street ROW consist of approximately 32 feet of
pavement with no curb or gutter. Runoff sheet flows from the crowned roadway to
unimproved gravel and grass shoulders on each side of the road, following the grade of
the road to the west. At the very west end of the site frontage is located the upstream end
of a 12” ROW storm main which heads west.
Existing conditions in the S 308th Street ROW consist of approximately 36 feet of
pavement. The portion of the ROW from west property line to 14th Ave South sheet flows
to a series of ditch and culverts segments along the north side of the ROW, following the
grade of the road to the west. Culvert sizes increase to the west, with the westernmost
culvert being a 24” pipe. The portion of the ROW from 14th Ave South to Pacific
Highway 99 drains via curb and gutter to an existing 12” storm main on the north side of
S 308th Street. This 12” storm drain line follows the grade of the road to the west and
discharges to the existing ditch system described above.
Federal Way High School Page 5 Project No. 13003
Springline Design LLC
Project Site:
Existing conditions in the 38.46 acre project site consist of the developed high school
campus with existing school district buildings, paved and gravel parking lots, tennis
courts, and sports fields. The site is bounded on the west by single-family residential
lots, on the north by S. 304th Street, on the east by 16th Ave South and Pacific Highway
99, and to the south by S. 308th Street.
The existing school building, including gymnasium, is located in the southeastern
quadrant of the site. In the northeast quadrant of the site is a former King County pool
building.
A school district food services building is located on the southern portion of the site, and
Memorial Stadium is located on west central portion of the property. To the west of
Memorial Stadium is existing lawn/landscaping and sports fields.
The site generally slopes to the south and west from a high point of around 489 feet at the
northeast corner to 436 feet at the southeast corner. Total elevation change across the site
is approximately 53 feet with slopes generally ranging between 2% and 10%.
Existing site drainage is largely collected and conveyed by existing onsite drainage
systems consisting of swales, catch basins, area drains, collection structures and pipes.
The site has five main subbasins which discharge to the ditch system along the north side
of S. 308th Street:
Central Kitchen
Memorial Stadium/Fields
Stadium Parking
Southeast School/Parking
Northeast School/Parking
In addition to the above subbasins, the site has one additional subbasin comprising the
Softball Field, which discharges to the storm drain system located at the west end of S.
304th St:
Both the S. 308th and the S. 304th ROW drainage systems discharge to Cold Creek to the
northwest.
See Table 1 below for a summary of existing land cover. See Figure 4 for a graphic
representation of existing land cover.
Table 1 – Existing Site Land Use
Rooftop
(Acres)
Paving
(Acres)
Underdrained
Fields
(Acres)
Landscape/
Grass
(Acres)
Right-
of-Way
(Acres)
Total
(Acres)
4.65 6.74 3.48 14.62 0.51 30.00
Federal Way High School Page 6 Project No. 13003
Springline Design LLC
Developed Conditions:
The developed project includes construction of a new school building and associated
plaza areas, loading areas and parking lots on the eastern portion of the site. Additionally,
new tennis courts and sports fields will be constructed on the northern portion of the
property, and a detention pond will be constructed along the western margin of the site.
Memorial Stadium, the Stadium Parking lot, and the Central Kitchen improvements will
remain as existing in the developed condition, and their subbasins will continue to
discharge to the downstream storm system independently of the developed project.
Site runoff will be collected via swales, catch basins, and other collection structures, and
will be conveyed via tightline piping to water quality treatment and detention facilities. A
detention pond on the western portion of the site will provide Level 3 flow control for
targeted surfaces. Upstream of the detention facility, bioretention (raingardens) will
provide Enhanced Basic water quality treatment to targeted PGIS surfaces. Flow
discharging from the detention pond will be conveyed to the existing City of Federal Way
storm drainage system within the S. 308th St. ROW.
See Table 2 below for developed site land use summary. See Figure 5 for a graphic
representation of developed land cover.
Table 2 – Developed Site Land Use
Rooftop
(Acres)
PGIS
(Acres)
Non-
PGIS
(Acres)
Overlay
Ex. Pavement
(Acres)
Pond
(Acres)
Underdrained
Fields
(Acres)
Landscape/
Grass
(Acres)
Total
(Acres)
3.05 4.40* 2.89 2.14 1.63 5.64 10.25 30.00
* includes PGIS area (0.51 acres) of ROW improvements
S 304nd Street ROW:
Right-of-way improvements for S 304th St include construction of curb, gutter, sidewalk
and landscape strip on the south side of the ROW for the full site frontage. Associated
storm drainage improvements include installation of catch basins and a storm drain main
along the proposed curb and gutter.
Flow control for S 304th St ROW improvements will be provided in the on site detention
system, via a mitigation trade of other non-targeted areas for targeted ROW surfaces.
Water quality treatment will be provided by a bioretention area (raingarden) which is
located just south of the 304th ROW on the school site.
S 308th Street ROW:
Right-of-way improvements for S 308th St include construction of curb, gutter, sidewalk
and landscape strip on the north side of the ROW from the west property line to14th Ave
Federal Way High School Page 7 Project No. 13003
Springline Design LLC
S. Storm drainage improvements include installation of catch basins and conveyance
along the proposed curb and gutter to replace the existing ditch.
Flow control for S 308th St ROW improvements will be provided in the on site detention
system, via a mitigation trade of other non-targeted areas for targeted ROW surfaces.
Water quality treatment will be provided in the South 304th St raingarden, via a
mitigation trade of non-target areas within the 304th St ROW, for targeted S. 308th St
surfaces.
FIGURE 1 – VICINITY MAP
Project Site
Federal Way High School Page 8 Project No. 13003
Springline Design LLC
FIGURE 2
TECHNICAL INFORMATION REPORT (TIR) WORKSHEET
Part 1 PROJECT OWNER AND
PROJECT ENGINEER
Part 2 PROJECT LOCATION AND
DESCRIPTION
Project Owner : Federal Way Public Schools
School District #210
Address : 31405 18th Ave S
Federal Way, WA 98003
Phone : 253 945 2000
Project Engineer: Marc Errichetti, PE
Company: Springline Design, LLC
Address/Phone: 206 957 8311
Project Name : Federal Way High School
Location : 30611 16th Ave S
Township 21N
Range 4E
Section 8
Part 3 TYPE OF PERMIT
APPLICATION Part 4 OTHER REVIEWS AND PERMITS
Subdivison
Short Subdivision
Grading
Commercial
Other _______________________
_______________________________
DFW HPA Shoreline Management
COE 404 Rockery
DOE Dam Safety Structural Vaults
FEMA Floodplain Other
COE Wetlands
Part 5 SITE COMMUNITY AND DRAINAGE BASIN
Community
City of Federal Way
Drainage Basin
Lower Puget Sound Basin
Part 6 SITE CHARACTERISTICS
River ________________________________
Stream ___________________________
Critical Stream Reach
Depressions/Swales
Lake
Steep Slopes ______________________
Floodplain ______________________
Wetlands
Seeps/Springs
High Groundwater Table
Groundwater Recharge
Other __________________________
Federal Way High School Page 9 Project No. 13003
Springline Design LLC
Part 7 SOILS
Soil Type
Ardents, Alderwood
_________________
_________________
_________________
Slopes
0% to 10%
_________________
_________________
_________________
Erosion Potential
Moderate
_________________
_________________
_________________
Erosive Velocities
_________________
_________________
_________________
_________________
Additional Sheets Attached
Part 8 DEVELOPMENT LIMITATIONS
REFERENCE
______________________________
______________________________
______________________________
______________________________
______________________________
______________________________
Additional Sheets Attached
LIMITATION/SITE CONSTRAINT
_______________________________________
_______________________________________
_______________________________________
_______________________________________
_______________________________________
_______________________________________
Part 9 ESC REQUIREMENTS
MINIMUM ESC REQUIREMENTS
DURING CONSTRUCTION
Sedimentation Facilities
Stabilized Construction Entrance
Perimeter Runoff Control
Clearing and Grading Restrictions
Cover Practices
Construction Sequence
Other
MINIMUM ESC REQUIREMENTS
AFTER CONSTRUCTION
Stabilize Exposed Surface
Remove and Restore Temporary ESC Facilities
Clean and Remove All Silt and Debris
Ensure Operation of Permanent Facilities
Flag Limits of SAO and open space
preservation areas
Other
Federal Way High School Page 11 Project No. 13003
Springline Design LLC
FIGURE 3 – EXISTING SITE SOIL CONDITIONS
Project Site
Till soils
Federal Way High School Page 14 Project No. 13003
Springline Design LLC
SECTION II – CONDITIONS AND REQUIREMENTS SUMMARY
Core and Special Requirements are listed below along with a discussion of their
applicability to this project.
Core Requirements:
Req. #1 Discharge at Natural Location:
Site and ROW: Existing TDA’s will be maintained.
Req. #2 Offsite Analysis:
See Section III.
Req. #3 Flow Control:
Site: Flood Problem Area flow control is required and is being provided
through the use of an onsite detention pond. Onsite flow control BMPs are
provided with the use of bioretention areas.
ROW: Flood Problem Area flow control is required for the S. 304th St and S.
308th St ROW improvements and is being provided by the onsite detention
pond and mitigation area trades.
Req. #4 Conveyance System:
Site and ROW: New conveyance systems will be implemented to meet this
requirement.
Req. #5 Erosion and Sediment Control:
Site and ROW: Construction ESC systems will be implemented to meet this
requirement.
Req. #6 Maintenance and Operations:
Site: FWPS will be responsible for maintenance and operations of site
stormwater systems.
ROW: Public facilities will be owned and maintained by the City. Easements will
be provided for public facilities located onsite, as required.
Req. #7 Financial Guarantees:
Site and ROW: A financial guarantee may be necessary for this project.
Federal Way High School Page 15 Project No. 13003
Springline Design LLC
Req. #8 Water Quality:
Site and ROW: Enhanced Basic water quality treatment is required for the site
and right-of-way and is being provided by bioretention treatment
areas sized per DOE requirements.
In accordance with FWRC Section 19.20.120, “Nonconforming
Water Quality Improvements,” all new and existing pollution
generating surfaces within the site will be treated by a water
quality facility.
Special Requirements:
Req. #1 Area Specific Requirements:
No area specific requirements are applicable to this project.
Req. #2: Floodplain/Floodway Delineation
Project is not adjacent to any floodplains or floodways.
Req. #3 Flood Protection Facilities:
Project is not adjacent to applicable area and will not affect any applicable
facility.
Req. #4 Source Controls:
Project is a school project and will provide appropriate source controls when
required.
Req. #5 Oil Control:
There will be no high use areas and therefore oil control is not required.
Federal Way High School Page 16 Project No. 13003
Springline Design LLC
SECTION III – OFFSITE ANALYSIS
Task 1 – Study Area Definition and Maps
Maps of the project site and surrounding area were obtained from the King County GIS
website. Topographical site information is from the topographical survey for the project
and from the King County iMAP. Storm drainage system maps were compiled from
Federal Way GIS maps and as-built plans. Aerial images were obtained from Google
Maps.
Task 2 – Resource Review
The Federal Way Public Works Department was contacted regarding the resources listed
in section 2.3.1.1 of the 1999 Addendum to KCSWDM. The following is a summary of
the resource review:
Adopted Basin Plans
o Basin Name: Lower Puget Sound Basin (per City of Federal
Federal Way Flow Control Applications Map)
Finalized Drainage Studies
o TIRs from surrounding projects were reviewed.
Basin Reconnaissance Summary Reports
o None completed to our knowledge.
Floodplain/Floodway (FEMA) Maps
o The site is not within a floodplain or floodway per FEMA mapping.
Other Offsite Analysis Reports
o No problems identified.
Environmentally Sensitive Areas Map
o No environmentally sensitive areas identified on or adjacent to site.
Road Drainage Problems
o None to our knowledge.
USDA Soils Survey
o A geotech report has been completed and site soils are primarily glacial
till.
Wetlands Inventory Maps
o No mapped wetlands located on or directly adjacent to site.
o Nearest mapped wetlands located approximately 500 feet southwest of the
site bordering Easter Lake.
Federal Way High School Page 17 Project No. 13003
Springline Design LLC
Task 3 – Field Inspection
A Level 1 downstream analysis was performed in the morning of September 13, 2013.
Weather conditions during the downstream analysis consisted of overcast skies and
temperatures of 64-70 degrees F.
On-site land use and topography was confirmed and downstream land use was identified
as a combination of asphalt streets and forested areas. Refer to Figures 6 and 7 and the
Off-Site Analysis Drainage System Tables following this section for detailed
information.
Runoff from the site discharges into the City of Federal Way conveyance system at
several points along the existing ditch that runs along the north side of S 308th Street, and
at the northwest corner of the site.
All site discharges flow west to 10th Avenue South where the system flows north to
where it is discharged in Cold Creek. The storm drain pipes in the closed system were in
good condition.
Task 4 – Drainage System Description and Problem Description
Based on correspondence with the City of Federal Public Works Department, the only
known problem with the downstream system is several sections of 36” CMP pipe
draining to Cold Creek with the “bottom rusted out of them and are in bad condition”
north of Dash Point Road.
Task 5 – Mitigation of Existing or Potential Problems
Based on the observations made during the field inspection and the requirements for the
design of the proposed drainage systems, no negative impacts to the downstream system
are anticipated, as flows from the site in the redeveloped condition will be greatly
reduced both in duration and peak.
Page 1 of 3
OFF-SITE ANALYSIS DRAINAGE SYSTEM TABLE
SURFACE WATER DESIGN MANUAL, CORE REQUIREMENT #2
Basin:Federal Way High School Subbasin Name:N/A Subbasin Number:N/A
Symbol Drainage
Component Type,
Name, and Size
Drainage
Component
Description
Slope Distance
from site
discharge
Existing
Problems
Potential
Problems
Observations of field
inspector, resource
reviewer, or resident
see map Type: sheet flow, swale,
stream, channel, pipe,
pond; Size: diameter,
surface area
drainage basin, vegetation,
cover, depth, type of sensitive
area, volume
%1/4 ml = 1,320 ft.constrictions, under capacity, ponding,
overtopping, flooding, habitat or organism
destruction, scouring, bank sloughing,
sedimentation, incision, other erosion
tributary area, likelihood of problem,
overflow pathways, potential impacts
#1 SDMH Circular grate
18” CONC (W)
18” CONC (E)
18” CONC (N)
N/A (adjacent to site) CONC (W) good condition
CONC (E) sediment and rock
observed at invert
CONC (N) mineral deposits
observed at invert of pipe
#2 18” Storm Drain 18” Concrete Pipe 6.7%
#3 Catch Basin Type 1 Rectangular grate
18” CONC (W)
18” CONC (E)
18” CONC (S)
N/A 12 ft. 18” CONC (W) good condition
18” CONC (E) good condition
Sump full of non-moving water
#4 18” Storm Drain 18” Concrete Pipe 6.5% Brick headwall in good condition
Pipe clear of debris and in good
condition
#5 24” Storm Drain 24” Concrete Pipe 1.0% Rip rap headwall in good condition
Pipe clear of debris and in good
condition
#6 Catch Basin Type 2 - 72”
with “Snout” Debris
Guard
Rectangular grate
18” CONC (W)
24” CONC (E)
18” CONC (S)
12” IP (NE)
N/A 196 ft. Structure full of non-moving water
to invert of 12” IP (NE)
#6i 12” Storm Drain 12” IP N/A Good condition
Page 2 of 3
Symbol Drainage
Component Type,
Name, and Size
Drainage
Component
Description
Slope Distance
from site
discharge
Existing
Problems
Potential
Problems
Observations of field
inspector, resource
reviewer, or resident
see map Type: sheet flow, swale,
stream, channel, pipe,
pond; Size: diameter,
surface area
drainage basin, vegetation,
cover, depth, type of sensitive
area, volume
%1/4 ml = 1,320 ft.constrictions, under capacity, ponding,
overtopping, flooding, habitat or organism
destruction, scouring, bank sloughing,
sedimentation, incision, other erosion
tributary area, likelihood of problem,
overflow pathways, potential impacts
#7 30” Storm Drain 30” CPP 1.0%
#8 Catch Basin Type 2-84”
With flat top high lake
level and overflow weir
vaned grate.
30” CONC(W)
24” CONC (N)
30” CPP (S)
N/A 242 ft. Structure partially filled with non-
moving water.
#9 30” Storm Drain 30” CONC 0.5%
#10 Manhole Type 2 -54” 30” CONC (W)
30” CONC (E)
N/A 458 ft. Locking lid.
#11 30” Storm Drain 30” CONC 0.5%
#12 Manhole Type 2 – 54” 30” CONC (W)
30” CONC (E)
N/A 674 ft. No sediment observed.
#13 30” Storm Drain 30” CONC 0.5%
#14 Manhole Type 2 – 72” 30” CONC (E)
24” CONC (N)
24” CONC (S)
N/A 744 ft.
#15 24” Storm Drain 24” CONC 1.6%
#16 Manhole Type 1 – 48” 24” CONC (N)
24” CONC (S)
N/A 785 ft. No debris or sediment observed.
Pipes in good condition.
Page 3 of 3
Symbol Drainage
Component Type,
Name, and Size
Drainage
Component
Description
Slope Distance
from site
discharge
Existing
Problems
Potential
Problems
Observations of field
inspector, resource
reviewer, or resident
see map Type: sheet flow, swale,
stream, channel, pipe,
pond; Size: diameter,
surface area
drainage basin, vegetation,
cover, depth, type of sensitive
area, volume
%1/4 ml = 1,320 ft.constrictions, under capacity, ponding,
overtopping, flooding, habitat or organism
destruction, scouring, bank sloughing,
sedimentation, incision, other erosion
tributary area, likelihood of problem,
overflow pathways, potential impacts
#17 24” Storm Drain 24” CONC 1.6%
#18 Manhole Type 1 – 48” 24” CONC (N)
24” CONC (S)
N/A 987 ft. No debris or sediment observed.
Pipes in good condition.
#19 24” Storm 24” CONC 1.6%
#20 Manhole Type 1 – 48” 24” CONC N/A 1162 ft. No debris or sediment observed.
Pipes in good condition.
#21 24” Storm Drain 24” CONC 1.6%
#22 Catch Basin Type 2 – 54”18” CONC (SE)
24” CONC (S)
30” CONC (NW)
8” CONC (SE)
N/A 1337 ft. Locking solid lid.
#23 30” Storm Drain 30” CONC
Federal Way High School Page 23 Project No. 13003
Springline Design LLC
SECTION IV – FLOW CONTROL AND WATER QUALITY FACILITY
ANALYSIS AND DESIGN
Flow Control:
Flow Control BMPs
Per the requirements of Section 5.2 of the 2009 King County Surface Water Design
Manual (KCSWDM), the project is required to implement Flow Control BMP’s.
In the redeveloped condition the site is classified as Large Lot High Impervious,per
Section 5.2.1.2 of the KCSWDM. As such, 100% of targeted surfaces must be served by
a Flow Control BMP.
Per footnote #3 on page 5-7 of the KCSWDM, the targeted surface for projects on large
lots (>22,000 SF) is comprised of all new impervious surfaces. See Figure 9 for a
depiction of targeted surfaces, totaling 3.7 acres.
Bioretention areas (Rain Gardens) have been implemented in several areas of the site to
meet this Flow Control BMP requirement. Surface water runoff which drains to the rain
gardens are subsequently be conveyed to the detention pond. Per the credits listed in
Table 5.2.2.A of the KCSWDM, impervious surfaces which are served by the rain
gardens are modeled as 50% impervious and 50% till grass for design of the formal
downstream flow control facility.
Formal Flow Control Facility
Per the requirements of Section 1.2.3 of the 2009 King County Surface Water Design
Manual (KCSWDM) and the City of Federal Way Flow Control Applications Map, the
project is required to provide formal flow control facilities that meet the requirements of
Flood Problem Flow Control (Level 3 Flow Control). Level 3 flow control is required to
mitigate for all new or replaced impervious surfaces. As the project will not be
converting any native forested areas to pervious surfaces, all developed pervious areas
are non targeted, and these areas will be modeled as pervious in both the predeveloped
and developed condition.
Level 3 Flow Control:Apply the Level 2 flow control standard,AND match the
developed 100-year peak discharge rate to the predeveloped 100-year peak
discharge rate. If the Flood Problem Flow Control Area is located within a
Conservation Flow Control Area and does not drain entirely by non-erodible
manmade conveyance to a major receiving body, then historic site conditions
shall be assumed as the predeveloped condition except for the purposes of
matching 100-year peak discharge rates. For the purposes of matching 100-year
peak discharge rates,existing site conditions may be assumed.
Level 2 Flow Control: Match developed discharge durations to predeveloped
durations for the range of predeveloped discharge rates from 50% of the 2-year
Federal Way High School Page 24 Project No. 13003
Springline Design LLC
peak flow up to the full 50-year peak flow. Also match developed peak discharge
rates to predeveloped peak discharge rates for the 2- and 10- year return periods.
In the developed condition, runoff from flow control targeted surfaces will be collected
and conveyed to a detention facility on the west side of the site.
Due to the topography of the site, flow control targeted surfaces at the southern margin of
the site cannot be reasonably conveyed to the proposed detention facility. In addition, due
to space constraints, provision of separate flow control facilities for the ROW’s is not
reasonably feasible. Accordingly, per section 1.2.3.2.G of the KCSWDM, a mitigation
trade is proposed to provide flow control for these areas, which will bypass the detention
facility.
In trade for these areas, the proposed onsite storm drainage system will include the
collection and conveyance to the detention pond of areas which are not targeted for flow
control. However, due to the configuration of the proposed bypass areas and the
available areas for mitigation trades, implementation of the trade will result in the
provision of mitigation for an additional 0.94 acres of impervious area beyond that which
is “targeted” for required mitigation by the proposed redevelopment. In short, the project
will be “banking” mitigation in the proposed pond for an additional 0.94 acres of
impervious area which may be developed at a later date.
See Table 4 below for a summary of the flow control mitigation trade areas. See Figure
8 for a depiction of the mitigation trade areas.
Table 4 – Flow Control Mitigation Trade Areas
Developed Surface Area
(Acres)
Non-Target Areas to Flow Control (+) 1.86
Target Areas Bypassing Flow Control (-) 0.92
Net “Additional” Mitigation Trade Area To
Flow Control (+) 0.94
Per table 3.2.2.C of the KCSWDM, field areas that include an underdrain collection
system (e.g. grass or synthetic turf sports field) are modeled as 75% grass and 25%
impervious. Per the credits listed in Table 5.2.2.A of the KCSWDM, impervious surfaces
which are served by the rain gardens are modeled as 50% impervious and 50% till grass
for design of the formal downstream flow control facility.
See Table 5 below for a summary of the targeted areas for flow control. This includes the
net “additional” mitigation trade area outlined above. See Figure 5 in Section 1 for a
graphic representation of developed land cover.
Federal Way High School Page 25 Project No. 13003
Springline Design LLC
Table 5 – Targeted Areas Summary
Developed Surface Area
(Acres)
Effective Impervious
(Acres)
Effective Pervious
(Acres)
Building 3.05 3.05 ---
PGIS with Bioretention
(50% Pervious/50% Impervious)4.68 2.34 2.34
Non-PGIS 2.89 2.89 ---
Proposed Underdrained Turf
(75% Pervious/25% Impervious)5.64 1.41 4.23
Pond
(100% Impervious)1.63 1.63 ---
Net “Additional” Flow Control
Mitigation Trade Area 0.94 0.94 ---
Total Target Areas
for Flow Control 12.26 6.57
In addition to the targeted areas summarized in Table 5, the developed condition includes
10.25 acres of non-targeted landscape area; this non targeted area will be modeled as till
grass in both the predeveloped and developed condition. See Table 6 below for the
facility sizing inputs and flow rate comparison based on the above. See Appendix A for
KCRTS routing summaries.
Table 6 – Detention Facility Sizing Data
Impervious
(Acres)
Till
Forest
(Acres)
Till
Grass
(Acres)
Total
Area
(Acres)
2-year Peak
Discharge Rate
(cfs)
10-year
Peak
Discharge
Rate (cfs)
100-year
Peak
Discharge
Rate (cfs)
Predeveloped --- 18.83 10.25 29.08 1.03 1.94 9.24*
Developed
Targeted Areas 12.26 --- 6.57
29.08 0.52 1.28 2.53Developed
Non-Targeted
Areas
--- --- 10.25
* Per KCSWDM,existing site condition used for 100-year pre-developed condition. See Section 1, Table 1.
A flow control system consisting of a 250,000 cubic foot detention pond will be
constructed to provide Level 3 Flow Control onsite before discharging detained
stormwater to the downstream City of Federal Way storm drainage system.
S 304th and 308th Streets ROW
Flow control for right-of-way improvements are implemented as described in mitigation
trade area summarized in Table 4 and facility sizing in Table 6 above.
TTTTT
Federal Way High School Page 28 Project No. 13003
Springline Design LLC
Water Quality
General
Per the City of Federal Way, this project is required to provide Enhanced Basic water
quality treatment for all existing and proposed pollution generation impervious surfaces
(PGIS). This requirement is being met through the use of bioretention areas (rain
gardens) to filter and treat runoff.
Design and sizing of bioretention areas is in accordance with the Department of Ecology
Stormwater Management Manual for Western Washington. Bioretention areas are
designed with 18” of bioretention material and are underdrained, with a maximum
ponding depth of 12” and maximum drawdown time of 24 hours following a storm event.
Sizing of the facilities was done with the Western Washington Hydrology Model
(WWHM) to filter 91% of the runoff volume, per DOE standards.
Site:
The proposed improvements result in approximately 7.62 acres of targeted surfaces,
comprising new and/or replaced pollution generating impervious surface (PGIS), and
landscape areas draining across PGIS.
S 304th and 308th Streets ROW
The proposed improvements to the right-of-ways will add approximately 0.91 acres of
new and replaced PGIS and landscape draining to the ROW.
Due to limited space in the 308th ROW, and in order to limit impacts to existing Stadium
Parking and Central Kitchen facilities adjacent to that ROW, a single ROW water quality
treatment facility is proposed, to be located adjacent to S. 304th St.
A catch basin in the S 304th St ROW will collect runoff from the ROW and convey it to a
bioretention facility adjacent to the ROW. The bioretention facility will treat an area
equivalent to the sum of the target surfaces in the S 304th and S 308th Streets right-of-
ways (0.91 acres). Treated runoff from the bioretention facility will then be discharged to
the downstream S. 304th ROW drainage system.
See Figure 10 for bioretention catchment areas, sizes, and locations. See Appendix A for
bioretention sizing calculations.
Federal Way High School Page 30 Project No. 13003
Springline Design LLC
SECTION V – CONVEYANCE SYSTEM DESIGN AND ANALYSIS
The on-site and ROW drainage will be served by a collection and conveyance system
consisting of pipes and catch basins. Pipes are sloped at a minimum 0.5% with catch
basins at every juncture. For the purposes of design, a backwater analysis was performed
on this system. Flows were derived through the rational method for use in the backwater
analysis. No overtopping of this system occurs during the 25-year event. The spreadsheet
for the pipe flows and layout and 25-year event backwater analysis are included in
Appendix C.
See Figures 11A – 11C following this section for conveyance system and basin area
diagrams.
SOUTH308THSTREETESOUTH
16THAVESOUTHPACIFICHIGHWAY99PACIFICHIGHWAY99PACIFICHIGHWAY99TTT
SOUTH304THSTREETSOUTH304THSTREETSOUTH304THSTREET16THAVESOUTH13THPLSOUTHT
Federal Way High School Page 34 Project No. 13003
Springline Design LLC
SECTION VI – SPECIAL REPORTS AND STUDIES
A geotechnical report for the site was completed.
SECTION VII – OTHER PERMITS
Federal Way Public Schools will be filing a Washington State Department of Ecology
NPDES Notice of Intent.
SECTION VIII – EROSION AND SEDIMENT CONTROL
ESC Measures are being addressed as follows:
Clearing Limits: Clearing limits are being delineated by perimeter silt fencing
and/or chain link fencing.
Cover Measures: Temporary cover shall be installed if an area is to remain
unworked for more than seven days during the dry season (May 1 to September
30) or for more than two consecutive working days during the wet season
(October 1 to April 30). Any area to remain unworked for more than 30 days shall
be seeded or sodded, unless the City determines that winter weather makes
vegetation establishment infeasible.
Perimeter Protection: Perimeter protection will be implemented by silt fencing
around the site perimeter where drainage paths require.
Traffic Area Stabilization: Stabilized areas will be used for construction traffic.
Sediment Retention: The proposed detention pond will be utilized as a sediment
pond during construction. See Appendix D for sediment pond sizing.
Surface Water Control: Surface water will be collected and conveyed via swales
with check dams as necessary.
Dust Control: Dust control, if required, will be provided through the limited use
of water trucks.
Federal Way High School Page 35 Project No. 13003
Springline Design LLC
SECTION IX – BOND QUANTITIES
A bond quantity worksheet for the proposed site improvements will be completed at a
later date.
SECTION X – OPERATIONS AND MAINTENANCE MANUAL
An operation and maintenance manual is provided in Appendix B, outlining the required
regular maintenance necessary for the detention pond and rain gardens to be performed
by Federal Way Public Schools for the site improvements.
APPENDIX A – FLOW CONTROL AND WATER QUALITY
CALCULATIONS
FLOW CONTROL
SUMMARY OF KCRTS INPUTS
EXISTING (HISTORIC) CONDITIONS:
(FOR FLOW CONTROL OTHER THAN 100 YEAR PEAK)
EXISTING
(HISTORIC)
CONDITION
EXISTING (CURRENT) CONDITIONS:
(FOR 100 YEAR PEAK FLOW CONTROL)
EXISTING
(CURRENT)
CONDITION
DEVELOPED CONDITIONS:
DEVELOPED
CONDITION
MITIGATED
CONDITION
(POND
OUTFLOW)
DETENTION POND (STAGE DISCHARGE STORAGE SETUP):
DURATION COMPARISON ANALYSIS
WATER QUALITY
Federal Way High School Page 1 of 8 Project No. 13003
Springline Design LLC
Bioretention/Rain Garden #1
Federal Way High School Page 2 of 8 Project No. 13003
Springline Design LLC
Bioretention/Rain Garden #2
Federal Way High School Page 3 of 8 Project No. 13003
Springline Design LLC
Bioretention/Rain Garden #3
Federal Way High School Page 4 of 8 Project No. 13003
Springline Design LLC
Bioretention/Rain Garden #4
Federal Way High School Page 5 of 8 Project No. 13003
Springline Design LLC
Bioretention/Rain Garden #5
Federal Way High School Page 6 of 8 Project No. 13003
Springline Design LLC
Bioretention/Rain Garden #6
Federal Way High School Page 7 of 8 Project No. 13003
Springline Design LLC
Bioretention/Rain Garden #7
Federal Way High School Page 8 of 8 Project No. 13003
Springline Design LLC
Bioretention/Rain Garden #8
APPENDIX B – OPERATIONS AND MAINTENANCE
MANUAL
APPENDIX C – BACKWATER ANALYSIS
CONVEYANCE INPUTS AND LAYOUT DATA
Project Name:Federal Way High School Event Parameters:Runoff Coefficients:
Job Number:13003 Event PR aR bR Tc iR IR C impervious 0.90
Designed By:MEB in unitless unitless min unitless in/hr C pervious 0.25
25-yr, 24-hr 3.5 2.66 0.65 10 0.60 2.08
100-yr, 24-hr 4.3 2.61 0.63 10 0.61 2.63
CB CB Impervious Pervious Total Total C IR, 25-yr Q25-yr Q25-yr IR,100-yr Q100-yr Q100-yr Length Pipe Size Mannings "n" Mannings "n" Downstream Downstream Upstream Upstream Pipe
Downstream Upstream Area Area Area Area Surface Total Surface Total Uniform Flow Backwater Invert Rim Invert Rim Slope
sf sf sf ac unitless in/hr cfs cfs in/hr cfs cfs ft in unitless unitless %
CB 1.1 CB 1.2 5,000 0 5,000 0.11 0.90 2.08 0.22 2.29 2.63 0.27 6.60 245.0 24 0.014 0.012 429.65 433.35 430.88 439.00 0.50%
CB 1.2 CB 1.3 (FCS) 0 0 0 0.00 0.00 2.08 0.00 2.07 2.63 0.00 6.33 8.0 24 0.014 0.012 430.88 439.00 430.92 441.50 0.50%
CB 1.3 (FCS)INLET #1 0 77,463 77,463 1.78 0.25 2.08 0.93 2.07 2.63 1.17 6.33 34.0 24 0.014 0.012 431.00 439.00 431.00 440.00 0.00%
PIPE OUTLET #2 CB 2.1 0 0 0.00 0.00 2.08 0.00 23.21 2.63 0.00 29.30 53.0 24 0.014 0.012 436.00 439.00 437.90 444.00 3.58%
CB 2.1 CB 2.2 0 0 0.00 0.00 2.08 0.00 23.21 2.63 0.00 29.30 129.0 24 0.014 0.012 437.90 444.00 439.93 444.50 1.57%
CB 2.2 CB 2.3 0 0 0.00 0.00 2.08 0.00 23.21 2.63 0.00 29.30 131.0 24 0.014 0.012 439.93 444.50 441.96 447.50 1.55%
CB 2.3 CB 2.4 0 0 0.00 0.00 2.08 0.00 23.21 2.63 0.00 29.30 63.0 24 0.014 0.012 441.96 447.50 445.23 457.00 5.19%
CB 2.4 CB 2.5 0 0 0.00 0.00 2.08 0.00 23.21 2.63 0.00 29.30 151.0 24 0.014 0.012 445.23 457.00 447.50 459.20 1.50%
CB 2.5 CB 2.6 10,000 9,525 19,525 0.45 0.58 2.08 0.54 22.50 2.63 0.69 28.40 221.0 24 0.014 0.012 447.50 459.20 450.82 464.05 1.50%
CB 2.6 CB 2.7 2,000 17,626 19,626 0.45 0.32 2.08 0.30 6.51 2.63 0.37 8.22 217.0 24 0.014 0.012 450.82 464.05 451.91 461.80 0.50%
CB 2.7 CB 2.8 0 0 0.00 0.00 2.08 0.00 2.89 2.63 0.00 3.65 210.0 18 0.014 0.012 452.41 461.80 453.46 458.50 0.50%
CB 2.8 CB 2.9 20,000 3,254 23,254 0.53 0.81 2.08 0.90 2.37 2.63 1.14 3.00 106.0 12 0.014 0.012 453.96 458.50 456.32 461.30 2.23%
CB 2.9 CB 2.10 7,200 306 7,506 0.17 0.87 2.08 0.31 1.47 2.63 0.40 1.86 125.0 12 0.014 0.012 456.32 461.30 457.74 461.00 1.14%
CB 2.10 CB 2.11 11,100 8,535 19,635 0.45 0.62 2.08 0.58 1.16 2.63 0.73 1.46 73.0 8 0.014 0.012 458.07 461.00 458.57 460.60 0.68%
CB 2.11 CB 2.12 11,300 7,796 19,096 0.44 0.63 2.08 0.58 0.58 2.63 0.73 0.73 218.0 8 0.014 0.012 458.57 460.60 459.67 464.50 0.50%
CB 2.5 CB 22.1 0 5,928 5,928 0.14 0.25 2.08 0.07 0.71 2.63 0.09 0.90 65.0 8 0.014 0.012 448.83 459.20 455.00 458.00 9.49%
PIPE OUTLET #3 CB 22.2 11,675 11,690 23,365 0.54 0.57 2.08 0.64 0.64 2.63 0.81 0.81 49.0 8 0.014 0.012 457.00 457.50 457.25 458.15 0.51%
CB 2.6 CB 4.1 55,000 1,340 56,340 1.29 0.88 2.08 2.38 5.12 2.63 3.01 6.47 90.0 12 0.014 0.012 450.82 464.05 460.00 463.50 10.20%
PIPE OUTLET #4 CB 4.2 19,000 1,590 20,590 0.47 0.85 2.08 0.84 2.29 2.63 1.06 2.89 79.0 12 0.014 0.012 463.00 463.50 465.50 468.20 3.16%
CB 4.2 CB 4.3 23,000 1,211 24,211 0.56 0.87 2.08 1.00 1.45 2.63 1.27 1.83 67.0 8 0.014 0.012 465.50 468.20 468.50 471.80 4.48%
PIPE OUTLET #5 CB 5.1 10,000 1,485 11,485 0.26 0.82 2.08 0.45 0.45 2.63 0.57 0.57 57.0 8 0.014 0.012 463.00 463.50 463.60 466.50 1.05%
CB 2.6 CB 6.1 0 0 0 0.00 0.00 2.08 0.00 10.32 2.63 0.00 13.02 318.0 18 0.014 0.012 450.82 464.05 457.00 465.50 1.94%
CB 6.1 CB 6.2 0 0 0 0.00 0.00 2.08 0.00 1.31 2.63 0.00 1.65 292.0 12 0.014 0.012 457.00 465.50 468.00 478.00 3.77%
CB 6.2 CB 6.3 0 0 0 0.00 0.00 2.08 0.00 1.31 2.63 0.00 1.65 59.0 12 0.014 0.012 468.00 478.00 472.00 482.10 6.78%
CB 6.3 CB 6.4 30,400 0 30,400 0.70 0.90 2.08 1.31 1.31 2.63 1.65 1.65 83.0 8 0.014 0.012 472.00 482.10 480.00 483.00 9.64%
CB 6.1 CB 7.1 9,000 3,087 12,087 0.28 0.73 2.08 0.42 1.21 2.63 0.54 1.53 242.0 12 0.014 0.012 457.50 465.50 460.00 465.00 1.03%
PIPE OUTLET #9 CB 7.2 17,000 4,791 21,791 0.50 0.76 2.08 0.79 0.79 2.63 1.00 1.00 20.0 8 0.014 0.012 464.00 465.00 464.10 465.70 0.50%
CB 6.1 CB 8.1 1,381 0 1,381 0.03 0.90 2.08 0.06 1.52 2.63 0.08 1.92 39.0 8 0.014 0.012 457.00 465.50 462.00 465.50 12.82%
CB 8.1 CB 8.2 4,688 0 4,688 0.11 0.90 2.08 0.20 0.77 2.63 0.25 0.98 63.0 8 0.014 0.012 462.00 465.50 462.66 466.50 1.05%
CB 8.2 CB 8.3 4,868 0 4,868 0.11 0.90 2.08 0.21 0.57 2.63 0.26 0.72 63.0 8 0.014 0.012 462.66 466.50 463.32 466.50 1.05%
CB 8.3 CB 8.4 8,386 0 8,386 0.19 0.90 2.08 0.36 0.36 2.63 0.46 0.46 58.0 8 0.014 0.012 463.32 466.50 463.93 466.80 1.05%
CB 8.1 CB 8.5 7,903 0 7,903 0.18 0.90 2.08 0.34 0.69 2.63 0.43 0.87 39.0 8 0.014 0.012 462.00 465.50 462.82 466.50 2.10%
CB 8.5 CB 8.6 8,168 0 8,168 0.19 0.90 2.08 0.35 0.35 2.63 0.44 0.44 51.0 8 0.014 0.012 462.82 466.50 463.37 466.50 1.08%
CB 6.1 CB 9.1 30,000 24,625 54,625 1.25 0.61 2.08 1.59 6.27 2.63 2.00 7.92 89.0 18 0.014 0.012 457.00 465.50 462.00 465.50 5.62%
CB CB Impervious Pervious Total Total C IR, 25-yr Q25-yr Q25-yr IR,100-yr Q100-yr Q100-yr Length Pipe Size Mannings "n" Mannings "n" Downstream Downstream Upstream Upstream Pipe
Downstream Upstream Area Area Area Area Surface Total Surface Total Uniform Flow Backwater Invert Rim Invert Rim Slope
sf sf sf ac unitless in/hr cfs cfs in/hr cfs cfs ft in unitless unitless %
CB 6.2 CB 10.1 0 0 0 0.00 0.00 2.08 0.00 1.25 2.63 0.00 1.58 60.0 8 0.014 0.012 468.00 478.00 469.00 477.00 1.67%
CB 10.1 CB 10.2 0 7,450 7,450 0.17 0.25 2.08 0.09 1.25 2.63 0.11 1.58 86.0 8 0.014 0.012 469.00 477.00 470.50 473.50 1.74%
CB 10.2 CB 10.3 0 80,000 105,400 2.42 0.19 2.08 0.96 0.96 2.63 1.21 1.21 64.0 8 0.014 0.012 470.50 473.50 471.00 474.00 0.78%
PIPE OUTLET #8 CB 10.4 4,850 0 4,850 0.11 0.90 2.08 0.21 0.21 2.63 0.26 0.26 51.0 8 0.014 0.012 475.80 476.50 480.00 484.00 8.24%
PIPE OUTLET #6 CB 11.1 12,000 2,566 14,566 0.33 0.79 2.08 0.55 2.57 2.63 0.69 3.24 101.0 12 0.014 0.012 464.00 464.50 465.50 468.80 1.49%
CB 11.1 CB 11.2 10,000 2,725 12,725 0.29 0.76 2.08 0.46 2.02 2.63 0.58 2.55 72.0 8 0.014 0.012 465.50 468.80 469.50 472.30 5.56%
CB 11.2 CB 11.3 12,000 6,750 18,750 0.43 0.67 2.08 0.60 1.56 2.63 0.75 1.96 70.0 8 0.014 0.012 469.50 472.30 472.50 475.50 4.29%
CB 11.3 CB 11.4 0 960 960 0.02 0.25 2.08 0.01 0.96 2.63 0.01 1.21 70.0 8 0.014 0.012 472.50 475.50 476.00 480.50 5.00%
CB 11.4 CB 11.5 22,000 0 22,000 0.51 0.90 2.08 0.95 0.95 2.63 1.20 1.20 14.0 8 0.014 0.012 476.00 480.50 476.50 480.00 3.57%
PIPE OUTLET #7 CB 12.1 0 0 0 0.00 0.00 2.08 0.00 2.12 2.63 0.00 2.67 42.0 12 0.014 0.012 464.00 464.50 465.00 467.50 2.38%
CB 12.1 CB 12.2 49,163 0 49,163 1.13 0.90 2.08 2.12 2.12 2.63 2.67 2.67 120.0 8 0.014 0.012 465.00 467.50 473.50 479.00 7.08%
CB 2.7 CB 13.1 2,300 12,700 15,000 0.34 0.35 2.08 0.25 3.32 2.63 0.32 4.19 129.0 12 0.014 0.012 452.91 461.80 456.20 461.20 2.55%
CB 13.1 CB 13.2 29,000 13,755 42,755 0.98 0.69 2.08 1.41 3.07 2.63 1.78 3.88 125.0 12 0.014 0.012 456.20 461.20 459.20 464.20 2.40%
CB 13.2 CB 13.3 34,000 16,155 50,155 1.15 0.69 2.08 1.66 1.66 2.63 2.09 2.09 109.0 12 0.014 0.012 459.20 464.20 460.29 463.50 1.00%
CB 13.3 CB 13.4 45,000 8,302 53,302 1.22 0.80 2.08 2.04 2.04 2.63 2.57 2.57 117.0 12 0.014 0.012 460.29 463.50 462.00 466.00 1.46%
PIPE OUTLET #8 CB 21.1 1,382 0 1,382 0.03 0.90 2.08 0.06 0.06 2.63 0.08 0.08 58.0 8 0.014 0.012 452.50 453.50 453.80 456.80 2.24%
CB 2.8 CB 17.1 11,516 2,000 13,516 0.31 0.80 2.08 0.52 0.52 2.63 0.66 0.66 77.0 8 0.014 0.012 456.23 458.50 457.00 459.00 1.00%
S 308th Street ROW
EX CB #1 CB 14.1 964 0 964 0.02 0.90 2.08 0.04 6.01 2.63 0.05 7.59 26.0 30 0.014 0.012 429.00 433.42 429.65 433.35 2.50%
CB 14.1 CB 14.2 7,040 0 7,040 0.16 0.90 2.08 0.30 5.97 2.63 0.38 7.53 91.0 24 0.014 0.012 429.65 433.35 430.14 432.68 0.54%
CB 14.2 CB 14.3 30,054 0 30,054 0.69 0.90 2.08 1.29 4.02 2.63 1.63 5.07 52.0 18 0.014 0.012 430.14 432.68 430.43 432.47 0.56%
CB 14.3 CB 14.4 4,213 0 4,213 0.10 0.90 2.08 0.18 2.72 2.63 0.23 3.43 8.0 18 0.014 0.012 430.43 432.47 430.50 432.41 0.87%
CB 14.4 CB 14.5 5,929 0 5,929 0.14 0.90 2.08 0.26 2.54 2.63 0.32 3.21 109.0 12 0.014 0.012 430.50 432.41 432.00 434.72 1.38%
CB 14.5 CB 14.6 3,475 0 3,475 0.08 0.90 2.08 0.15 2.28 2.63 0.19 2.88 174.0 12 0.014 0.012 432.00 434.72 441.00 444.72 5.17%
CB 14.6 CB 14.7 22,337 0 22,337 0.51 0.90 2.08 0.96 0.96 2.63 1.21 1.21 100.0 12 0.014 0.012 441.00 444.72 447.00 450.85 6.00%
CB 14.1 CB 15.1 30,000 30,000 60,000 1.38 0.58 2.08 1.65 1.65 2.63 2.08 2.08 58.0 8 0.014 0.012 430.14 432.68 434.50 437.50 7.52%
CB 14.5 CB 16.1 25,100 0 25,100 0.58 0.90 2.08 1.08 1.08 2.63 1.36 1.36 50.0 8 0.014 0.012 441.00 444.72 442.50 445.50 3.00%
CB 14.6 CB 16.2 0 2,700 2,700 0.06 0.25 2.08 0.03 0.09 2.63 0.04 0.12 33.0 8 0.014 0.012 447.33 450.85 450.00 454.00 8.09%
S 304th Street ROW
CB 18.2 CB 18.3 10,667 0 10,667 0.24 0.90 2.08 0.46 1.32 2.63 0.58 1.67 102.0 12 0.014 0.012 444.00 447.39 451.43 456.43 7.28%
CB 18.3 CB 18.4 6,861 0 6,861 0.16 0.90 2.08 0.30 0.87 2.63 0.37 1.09 297.0 12 0.014 0.012 451.43 456.43 467.68 472.68 5.47%
CB 18.4 CB 18.5 6,694 0 6,694 0.15 0.90 2.08 0.29 0.57 2.63 0.36 0.72 197.0 12 0.014 0.012 467.68 472.68 473.53 478.53 2.97%
CB 18.5 CB 18.6 6,537 6,537 0.15 0.90 2.08 0.28 0.28 2.63 0.36 0.36 197.0 12 0.014 0.012 473.53 478.53 478.25 483.26 2.40%
CB 18.6 CB 18.7 1,826 0 1,826 0.04 0.90 2.08 0.08 0.08 2.63 0.10 0.10 196.0 12 0.014 0.012 478.25 483.26 480.25 488.25 1.02%
CB 18.1 CB 19.1 0 2,933 2,933 0.07 0.25 2.08 0.04 1.36 2.63 0.04 1.72 42.0 8 0.014 0.012 439.30 443.94 441.50 444.50 5.24%
PIPE OUTLET #10 CB 18.2 0 0 0 0.00 0.90 2.08 0.00 1.32 2.63 0.00 1.67 27.0 8 0.014 0.012 443.50 444.50 444.00 447.39 1.85%
BACKWATER CALCULATION SPREADSHEET - 25 YEAR
Project Name:FWHS Designed By:MEB
Job Number:13003 Storm Event:25-yr, 24-hr
Conveyance System Information Outlet Control Inlet Control Headwater Summation Overtopping Check
Pipe Segment Surface Total Length Pipe "n" Down- Down- Up- Up- Pipe Barrel Barrel Critical TW TW Barrel Friction Entrance Entrance Entrance Exit Outlet Inlet Inlet Control Approach Bend Bend Q1 Q3 V1 Junction Head HW (HW - Rim) Over-
CB/MH # CB/MH # Flow Flow L Size value Stream Stream Stream Stream Slope Velocity Velocity Depth Elev. Check Hyd. Loss HGL Ke Head Head Control Control Control HW Veloctiy Kb Head Head Loss Elev. Clearance topping
Down Up Q Qtot D Invert Rim Invert Rim Head Rad.Elev.Loss Loss Elev.HW/D Elev.Elev.Head Loss Loss Total Check
CFS CFS FT IN FT FT FT FT % FPS FT FT FT FT FT FT FT FT FT FT FT FT FT FT FT CFS CFS FPS FT FT FT FT
CB 1.1 CB 1.2 0.22 2.29 245.0 24 0.012 429.65 433.35 430.88 439.00 0.50% 0.73 0.01 1.80 432.14 432.14 0.50 0.02 432.88 0.50 0.00 0.01 432.89 0.50 431.88 432.89 0.01 0.64 0.01 2.07 0.73 0.01 432.89 -6.11 Okay
CB 1.2 CB 1.3 (FCS) 0.00 2.07 8.0 24 0.012 430.88 439.00 430.92 441.50 0.50% 0.66 0.01 1.80 432.89 432.89 0.50 0.00 432.92 0.50 0.00 0.01 432.93 0.50 431.92 432.93 0.01 1.32 0.01 2.07 0.66 0.01 432.93 -8.57 Okay
CB 1.3 (FCS) INLET #1 0.93 2.07 34.0 24 0.012 431.00 439.00 431.00 440.00 0.00% 0.66 0.01 1.80 432.93 432.93 0.50 0.00 433.00 0.50 0.00 0.01 433.01 1.10 433.20 433.20 0.00 0.00 23.21 0.66 433.20 -6.80 Okay
PIPE OUTLET #2 CB 2.1 0.00 23.21 53.0 24 0.012 436.00 439.00 437.90 444.00 3.58% 7.39 0.85 1.75 431.00 437.88 0.50 0.47 439.90 0.50 0.42 0.85 441.17 1.80 441.50 441.50 0.85 0.12 0.10 23.21 7.39 0.10 440.75 -3.25 Okay
CB 2.1 CB 2.2 0.00 23.21 129.0 24 0.012 437.90 444.00 439.93 444.50 1.57% 7.39 0.85 1.75 440.75 440.75 0.50 1.15 441.93 0.50 0.42 0.85 443.20 1.80 443.53 443.53 0.85 0.48 0.41 23.21 7.39 0.41 443.09 -1.41 Okay
CB 2.2 CB 2.3 0.00 23.21 131.0 24 0.012 439.93 444.50 441.96 447.50 1.55% 7.39 0.85 1.75 443.09 443.09 0.50 1.17 444.26 0.50 0.42 0.85 445.53 1.80 445.56 445.56 0.85 0.00 23.21 7.39 444.71 -2.79 Okay
CB 2.3 CB 2.4 0.00 23.21 63.0 24 0.012 441.96 447.50 445.23 457.00 5.19% 7.39 0.85 1.75 444.71 444.71 0.50 0.56 447.23 0.50 0.42 0.85 448.50 1.80 448.83 448.83 0.85 0.00 23.21 7.39 447.98 -9.02 Okay
CB 2.4 CB 2.5 0.00 23.21 151.0 24 0.012 445.23 457.00 447.50 459.20 1.50% 7.39 0.85 1.75 447.98 447.98 0.50 1.35 449.50 0.50 0.42 0.85 450.77 1.80 451.10 451.10 0.80 1.32 1.12 22.50 0.71 7.39 0.02 1.14 451.44 -7.76 Okay
CB 2.5 CB 2.6 0.54 22.50 221.0 24 0.012 447.50 459.20 450.82 464.05 1.50% 7.16 0.80 1.75 451.44 451.44 0.50 1.86 453.30 0.50 0.40 0.80 454.50 1.80 454.42 454.50 0.07 0.00 6.51 15.44 7.16 0.71 0.71 455.14 -8.91 Okay
CB 2.6 CB 2.7 0.30 6.51 217.0 24 0.012 450.82 464.05 451.91 461.80 0.50% 2.07 0.07 1.12 455.14 455.14 0.50 0.15 455.29 0.50 0.03 0.07 455.39 0.75 453.41 455.39 0.04 0.00 2.89 3.32 2.07 0.04 0.04 455.39 -6.41 Okay
CB 2.7 CB 2.8 0.00 2.89 210.0 18 0.012 452.41 461.80 453.46 458.50 0.50% 1.64 0.04 0.74 455.39 455.39 0.38 0.14 455.52 0.50 0.02 0.04 455.58 0.60 454.36 455.58 0.14 1.32 0.05 2.37 0.52 1.64 0.01 0.06 455.50 -3.00 Okay
CB 2.8 CB 2.9 0.90 2.37 106.0 12 0.012 453.96 458.50 456.32 461.30 2.23% 3.02 0.14 0.65 455.50 455.50 0.25 0.40 457.32 0.50 0.07 0.14 457.53 0.75 457.07 457.53 0.05 1.32 0.19 1.47 3.02 0.19 457.67 -3.63 Okay
CB 2.9 CB 2.10 0.31 1.47 125.0 12 0.012 456.32 461.30 457.74 461.00 1.14% 1.88 0.05 0.57 457.67 457.67 0.25 0.18 458.74 0.50 0.03 0.05 458.82 0.65 458.39 458.82 0.17 0.48 0.03 1.16 1.88 0.03 458.68 -2.32 Okay
CB 2.10 CB 2.11 0.58 1.16 73.0 8 0.012 458.07 461.00 458.57 460.60 0.68% 3.32 0.17 0.52 458.68 458.68 0.17 0.57 459.25 0.50 0.09 0.17 459.50 0.50 458.90 459.50 0.04 0.48 0.08 0.58 3.32 0.08 459.54 -1.06 Okay
CB 2.11 CB 2.12 0.58 0.58 218.0 8 0.012 458.57 460.60 459.67 464.50 0.50% 1.66 0.04 0.36 459.54 459.54 0.17 0.42 460.34 0.50 0.02 0.04 460.40 0.50 460.00 460.40 0.00 0.00 1.66 460.40 -4.10 Okay
CB 2.5 CB 22.1 0.07 0.71 65.0 8 0.012 448.83 459.20 455.00 458.00 9.49% 2.04 0.06 0.40 451.44 451.44 0.17 0.19 455.67 0.50 0.03 0.06 455.76 0.50 455.33 455.76 0.05 1.32 0.09 0.64 2.04 0.09 455.80 -2.20 Okay
PIPE OUTLET #3 CB 22.2 0.64 0.64 49.0 8 0.012 457.00 457.50 457.25 458.15 0.51% 1.84 0.05 0.38 457.50 457.52 0.17 0.12 457.92 0.50 0.03 0.05 458.00 0.50 457.58 458.00 0.00 0.00 1.84 458.00 -0.15 Caution
CB 2.6 CB 4.1 2.38 5.12 90.0 12 0.012 450.82 464.05 460.00 463.50 10.20% 6.52 0.66 0.66 455.14 455.14 0.25 1.58 461.00 0.50 0.33 0.66 461.99 0.50 460.50 461.99 0.13 1.32 0.87 2.29 6.52 0.87 462.73 -0.77 Okay
PIPE OUTLET #4 CB 4.2 0.84 2.29 79.0 12 0.012 463.00 463.50 465.50 468.20 3.16% 2.92 0.13 0.64 462.73 463.82 0.25 0.28 466.50 0.50 0.07 0.13 466.70 0.50 466.00 466.70 0.27 0.00 1.45 2.92 466.43 -1.77 Okay
CB 4.2 CB 4.3 1.00 1.45 67.0 8 0.012 465.50 468.20 468.50 471.80 4.48% 4.16 0.27 0.56 466.43 466.43 0.17 0.82 469.17 0.50 0.13 0.27 469.57 0.50 468.83 469.57 0.03 0.00 0.45 4.16 469.54 -2.26 Okay
PIPE OUTLET #5 CB 5.1 0.45 0.45 57.0 8 0.012 463.00 463.50 463.60 466.50 1.05% 1.28 0.03 0.31 463.50 463.50 0.17 0.07 464.27 0.50 0.01 0.03 464.31 0.50 463.93 464.31 0.00 0.00 1.28 464.31 -2.19 Okay
CB 2.6 CB 6.1 0.00 10.32 318.0 18 0.012 450.82 464.05 457.00 465.50 1.94% 5.84 0.53 1.23 455.14 455.14 0.38 2.60 458.50 0.50 0.26 0.53 459.29 0.50 457.75 459.29 0.04 1.32 0.70 1.31 9.01 5.84 0.66 1.36 460.61 -4.89 Okay
CB 6.1 CB 6.2 0.00 1.31 292.0 12 0.012 457.00 465.50 468.00 478.00 3.77% 1.67 0.04 0.48 460.61 460.61 0.25 0.33 469.00 0.50 0.02 0.04 469.06 0.50 468.50 469.06 0.04 0.48 0.02 1.31 1.25 1.67 0.02 0.04 469.07 -8.93 Okay
CB 6.2 CB 6.3 0.00 1.31 59.0 12 0.012 468.00 478.00 472.00 482.10 6.78% 1.67 0.04 0.48 469.07 469.07 0.25 0.07 473.00 0.50 0.02 0.04 473.06 0.50 472.50 473.06 0.22 0.00 1.31 1.67 472.85 -9.25 Okay
CB 6.3 CB 6.4 1.31 1.31 83.0 8 0.012 472.00 482.10 480.00 483.00 9.64% 3.75 0.22 0.54 472.85 472.85 0.17 0.82 480.67 0.50 0.11 0.22 480.99 0.50 480.33 480.99 0.00 0.00 3.75 480.99 -2.01 Okay
CB 6.1 CB 7.1 0.42 1.21 242.0 12 0.012 457.50 465.50 460.00 465.00 1.03% 1.55 0.04 0.46 460.61 460.61 0.25 0.24 461.00 0.50 0.02 0.04 461.06 0.50 460.50 461.06 0.08 0.00 0.79 1.55 460.98 -4.02 Okay
PIPE OUTLET #9 CB 7.2 0.79 0.79 20.0 8 0.012 464.00 465.00 464.10 465.70 0.50% 2.26 0.08 0.42 460.98 464.54 0.17 0.07 464.77 0.50 0.04 0.08 464.89 0.50 464.43 464.89 0.00 0.00 2.26 464.89 -0.81 Okay
CB 6.1 CB 8.1 0.06 1.52 39.0 8 0.012 457.00 465.50 462.00 465.50 12.82% 4.37 0.30 0.58 460.61 460.61 0.17 0.53 462.67 0.50 0.15 0.30 463.11 0.50 462.33 463.11 0.08 1.32 0.39 0.77 0.69 4.37 0.15 0.54 463.58 -1.92 Okay
CB 8.1 CB 8.2 0.20 0.77 63.0 8 0.012 462.00 465.50 462.66 466.50 1.05% 2.21 0.08 0.42 463.58 463.58 0.17 0.22 463.80 0.50 0.04 0.08 463.91 0.50 462.99 463.91 0.04 1.32 0.10 0.57 2.21 0.10 463.97 -2.53 Okay
CB 8.2 CB 8.3 0.21 0.57 63.0 8 0.012 462.66 466.50 463.32 466.50 1.05% 1.64 0.04 0.36 463.97 463.97 0.17 0.12 464.09 0.50 0.02 0.04 464.15 0.50 463.65 464.15 0.02 0.00 0.36 1.64 464.13 -2.37 Okay
CB 8.3 CB 8.4 0.36 0.36 58.0 8 0.012 463.32 466.50 463.93 466.80 1.05% 1.03 0.02 0.28 464.13 464.13 0.17 0.04 464.60 0.50 0.01 0.02 464.62 0.50 464.26 464.62 0.06 0.00 0.69 1.03 464.56 -2.24 Okay
CB 8.1 CB 8.5 0.34 0.69 39.0 8 0.012 462.00 465.50 462.82 466.50 2.10% 1.98 0.06 0.39 464.56 464.56 0.17 0.11 464.67 0.50 0.03 0.06 464.76 0.50 463.15 464.76 0.02 0.48 0.03 0.35 1.98 0.03 464.77 -1.73 Okay
CB 8.5 CB 8.6 0.35 0.35 51.0 8 0.012 462.82 466.50 463.37 466.50 1.08% 1.01 0.02 0.27 464.77 464.77 0.17 0.04 464.81 0.50 0.01 0.02 464.83 0.50 463.70 464.83 1.32 0.02 0.00 1.01 0.02 464.85 -1.65 Okay
CB 6.1 CB 9.1 1.59 6.27 89.0 18 0.012 457.00 465.50 462.00 465.50 5.62% 3.55 0.20 0.96 460.61 460.61 0.38 0.27 463.50 0.50 0.10 0.20 463.79 0.50 462.75 463.79 0.00 0.00 3.55 463.79 -1.71 Okay
CB 6.2 CB 10.1 0.00 1.25 60.0 8 0.012 468.00 478.00 469.00 477.00 1.67% 3.60 0.20 0.53 455.14 468.60 0.17 0.55 469.67 0.50 0.10 0.20 469.97 0.50 469.33 469.97 0.20 0.48 0.10 1.25 3.60 0.10 469.86 -7.14 Okay
CB 10.1 CB 10.2 0.09 1.25 86.0 8 0.012 469.00 477.00 470.50 473.50 1.74% 3.60 0.20 0.53 469.86 469.86 0.17 0.78 471.17 0.50 0.10 0.20 471.47 0.50 470.83 471.47 0.12 0.48 0.10 0.96 3.60 0.10 471.45 -2.05 Okay
CB 10.2 CB 10.3 0.96 0.96 64.0 8 0.012 470.50 473.50 471.00 474.00 0.78% 2.74 0.12 0.46 471.45 471.45 0.17 0.34 471.79 0.50 0.06 0.12 471.96 0.50 471.33 471.96 0.01 0.00 0.21 2.74 471.96 -2.04 Okay
PIPE OUTLET #8 CB 10.4 0.21 0.21 51.0 8 0.012 475.80 476.50 480.00 484.00 8.24% 0.60 0.01 0.21 471.96 476.24 0.17 0.01 480.67 0.50 0.00 0.01 480.68 0.50 480.33 480.68 0.00 0.00 0.60 480.68 -3.32 Okay
PIPE OUTLET #6 CB 11.1 0.55 2.57 101.0 12 0.012 464.00 464.50 465.50 468.80 1.49% 3.27 0.17 0.68 464.50 464.84 0.25 0.44 466.50 0.50 0.08 0.17 466.75 0.50 466.00 466.75 0.52 0.48 0.08 2.02 3.27 0.08 466.31 -2.49 Okay
CB 11.1 CB 11.2 0.46 2.02 72.0 8 0.012 465.50 468.80 469.50 472.30 5.56% 5.79 0.52 0.63 466.31 466.31 0.17 1.70 470.17 0.50 0.26 0.52 470.95 0.50 469.83 470.95 0.31 0.00 1.56 5.79 470.64 -1.66 Okay
CB 11.2 CB 11.3 0.60 1.56 70.0 8 0.012 469.50 472.30 472.50 475.50 4.29% 4.46 0.31 0.56 470.64 470.64 0.17 0.98 473.17 0.50 0.15 0.31 473.63 0.50 472.83 473.63 0.12 0.00 0.96 4.46 473.51 -1.99 Okay
CB 11.3 CB 11.4 0.01 0.96 70.0 8 0.012 472.50 475.50 476.00 480.50 5.00% 2.75 0.12 0.41 473.51 473.51 0.17 0.37 476.67 0.50 0.06 0.12 476.84 0.50 476.33 476.84 0.11 0.00 0.95 2.75 476.73 -3.77 Okay
CB 11.4 CB 11.5 0.95 0.95 14.0 8 0.012 476.00 480.50 476.50 480.00 3.57% 2.71 0.11 0.40 476.73 476.73 0.17 0.07 477.17 0.50 0.06 0.11 477.34 0.50 476.83 477.34 1.32 0.15 0.00 2.71 0.15 477.49 -2.51 Okay
PIPE OUTLET #7 CB 12.1 0.00 2.12 42.0 12 0.012 464.00 464.50 465.00 467.50 2.38% 2.70 0.11 0.33 464.50 464.67 0.25 0.13 466.00 0.50 0.06 0.11 466.17 0.50 465.50 466.17 0.57 0.48 0.05 2.12 2.70 0.05 465.65 -1.85 Okay
FWHS - Backwater Conveyance Calculation-Ph2 Permit.xls 7/30/2014
Conveyance System Information Outlet Control Inlet Control Headwater Summation Overtopping Check
Pipe Segment Surface Total Length Pipe "n" Down- Down- Up- Up- Pipe Barrel Barrel Critical TW TW Barrel Friction Entrance Entrance Entrance Exit Outlet Inlet Inlet Control Approach Bend Bend Q1 Q3 V1 Junction Head HW (HW - Rim) Over-
CB/MH # CB/MH # Flow Flow L Size value Stream Stream Stream Stream Slope Velocity Velocity Depth Elev. Check Hyd. Loss HGL Ke Head Head Control Control Control HW Veloctiy Kb Head Head Loss Elev. Clearance topping
Down Up Q Qtot D Invert Rim Invert Rim Head Rad.Elev.Loss Loss Elev.HW/D Elev.Elev.Head Loss Loss Total Check
CFS CFS FT IN FT FT FT FT % FPS FT FT FT FT FT FT FT FT FT FT FT FT FT FT FT CFS CFS FPS FT FT FT FT
CB 12.1 CB 12.2 2.12 2.12 120.0 8 0.012 465.00 467.50 473.50 479.00 7.08% 6.07 0.57 0.33 465.65 465.65 0.17 3.12 474.17 0.50 0.29 0.57 475.02 0.50 473.83 475.02 1.32 0.75 0.00 6.07 0.75 475.78 -3.22 Okay
CB 2.7 CB 13.1 0.25 3.32 129.0 12 0.012 452.91 461.80 456.20 461.20 2.55% 4.23 0.28 0.33 455.39 455.39 0.25 0.95 457.20 0.50 0.14 0.28 457.62 0.50 456.70 457.62 0.24 1.32 0.37 3.07 4.23 0.37 457.75 -3.45 Okay
CB 13.1 CB 13.2 1.41 3.07 125.0 12 0.012 456.20 461.20 459.20 464.20 2.40% 3.91 0.24 0.33 457.75 457.75 0.25 0.79 460.20 0.50 0.12 0.24 460.56 0.50 459.70 460.56 0.07 0.00 1.66 3.91 460.49 -3.71 Okay
CB 13.2 CB 13.3 1.66 1.66 109.0 12 0.012 459.20 464.20 460.29 463.50 1.00% 2.11 0.07 0.33 460.49 460.49 0.25 0.20 461.29 0.50 0.03 0.07 461.39 0.50 460.79 461.39 0.00 0.00 2.11 461.39 -2.11 Okay
CB 13.3 CB 13.4 2.04 2.04 117.0 12 0.012 460.29 463.50 462.00 466.00 1.46% 2.59 0.10 0.33 461.39 461.39 0.25 0.32 463.00 0.50 0.05 0.10 463.16 0.50 462.50 463.16 0.00 0.00 0.06 2.59 463.16 -2.84 Okay
PIPE OUTLET #8 CB 21.1 0.06 0.06 58.0 8 0.012 452.50 453.50 453.80 456.80 2.24% 0.17 0.00 0.33 452.50 453.00 0.17 0.00 454.47 0.50 0.00 0.00 454.47 0.50 454.13 454.47 0.00 0.00 0.17 454.47 -2.33 Okay
CB 2.8 CB 17.1 0.52 0.52 77.0 8 0.012 456.23 458.50 457.00 459.00 1.00% 1.49 0.03 0.33 455.50 456.73 0.17 0.12 457.67 0.50 0.02 0.03 457.72 0.50 457.33 457.72 1.32 0.05 0.00 1.49 0.05 457.76 -1.24 Okay
S 308th Street ROW
EX CB #1 CB 14.1 0.04 6.01 26.0 30 0.012 429.00 433.42 429.65 433.35 2.50% 1.22 0.02 0.94 429.50 430.72 0.63 0.00 432.15 0.50 0.01 0.02 432.18 0.50 430.90 432.18 0.06 0.00 5.97 2.29 1.22 0.01 0.01 432.14 -1.21 Okay
CB 14.1 CB 14.2 0.30 5.97 91.0 24 0.012 429.65 433.35 430.14 432.68 0.54% 1.90 0.06 0.94 432.14 432.14 0.50 0.05 432.19 0.50 0.03 0.06 432.27 0.50 431.14 432.27 0.08 0.00 4.02 1.65 1.90 0.02 0.02 432.21 -0.47 Caution
CB 14.2 CB 14.3 1.29 4.02 52.0 18 0.012 430.14 432.68 430.43 432.47 0.56% 2.27 0.08 0.86 432.21 432.21 0.38 0.06 432.27 0.50 0.04 0.08 432.39 0.50 431.18 432.39 0.04 0.00 2.72 2.27 432.36 -0.11 Caution
CB 14.3 CB 14.4 0.18 2.72 8.0 18 0.012 430.43 432.47 430.50 432.41 0.87% 1.54 0.04 0.75 432.36 432.36 0.38 0.00 432.36 0.50 0.02 0.04 432.42 0.50 431.25 432.42 0.16 0.00 2.54 1.54 432.25 -0.16 Caution
CB 14.4 CB 14.5 0.26 2.54 109.0 12 0.012 430.50 432.41 432.00 434.72 1.38% 3.23 0.16 0.82 432.25 432.25 0.25 0.47 433.00 0.50 0.08 0.16 433.24 0.50 432.50 433.24 0.13 0.00 2.28 3.23 433.11 -1.61 Okay
CB 14.5 CB 14.6 0.15 2.28 174.0 12 0.012 432.00 434.72 441.00 444.72 5.17% 2.91 0.13 0.79 433.11 433.11 0.25 0.61 442.00 0.50 0.07 0.13 442.20 0.50 441.50 442.20 0.02 0.00 0.96 1.17 2.91 0.08 0.08 442.26 -2.46 Okay
CB 14.6 CB 14.7 0.96 0.96 100.0 12 0.012 441.00 444.72 447.00 450.85 6.00% 1.22 0.02 0.41 442.26 442.26 0.25 0.06 448.00 0.50 0.01 0.02 448.03 0.50 447.50 448.03 0.00 0.96 1.22 448.03 -2.82 Okay
CB 14.1 CB 15.1 1.65 1.65 58.0 8 0.012 430.14 432.68 434.50 437.50 7.52% 4.73 0.35 0.62 432.21 432.21 0.17 0.92 435.17 0.50 0.17 0.35 435.69 0.50 434.83 435.69 1.32 0.46 0.00 4.73 0.46 436.15 -1.35 Okay
CB 14.5 CB 16.1 1.08 1.08 50.0 8 0.012 441.00 444.72 442.50 445.50 3.00% 3.10 0.15 0.49 442.26 442.26 0.17 0.34 443.17 0.50 0.07 0.15 443.39 0.50 442.83 443.39 0.00 1.32 0.20 0.00 3.10 0.20 443.59 -1.91 Okay
CB 14.6 CB 16.2 0.03 0.09 33.0 8 0.012 447.33 450.85 450.00 454.00 8.09% 0.26 0.00 0.52 442.26 447.92 0.17 0.00 450.67 0.50 0.00 0.00 450.67 0.50 450.33 450.67 1.32 0.00 0.00 0.26 0.00 450.67 -3.33 Okay
S 304th Street ROW
CB 18.2 CB 18.3 0.46 1.32 102.0 12 0.012 444.00 447.39 451.43 456.43 7.28% 1.69 0.04 0.33 445.00 445.00 0.25 0.12 452.43 0.50 0.02 0.04 452.50 0.50 451.93 452.50 0.01 0.00 0.87 1.69 452.49 -3.94 Okay
CB 18.3 CB 18.4 0.30 0.87 297.0 12 0.012 451.43 456.43 467.68 472.68 5.47% 1.10 0.02 0.33 452.49 452.49 0.25 0.15 468.68 0.50 0.01 0.02 468.71 0.50 468.18 468.71 0.00 0.00 0.57 1.10 468.71 -3.97 Okay
CB 18.4 CB 18.5 0.29 0.57 197.0 12 0.012 467.68 472.68 473.53 478.53 2.97% 0.73 0.01 0.33 468.71 468.71 0.25 0.04 474.53 0.50 0.00 0.01 474.54 0.50 474.03 474.54 0.00 0.00 0.28 0.73 474.54 -3.99 Okay
CB 18.5 CB 18.6 0.28 0.28 197.0 12 0.012 473.53 478.53 478.25 483.26 2.40% 0.36 0.00 0.33 474.54 474.54 0.25 0.01 479.25 0.50 0.00 0.00 479.25 0.50 478.75 479.25 0.00 0.08 0.36 479.25 -4.01 Okay
CB 18.6 CB 18.7 0.08 0.08 196.0 12 0.012 478.25 483.26 480.25 488.25 1.02% 0.10 0.00 0.33 479.25 479.25 0.25 0.00 481.25 0.50 0.00 0.00 481.25 0.50 480.75 481.25 0.00 0.00 0.10 481.25 -7.00 Okay
CB 18.1 CB 19.1 0.04 1.36 42.0 8 0.012 439.30 443.94 441.50 444.50 5.24% 3.90 0.24 0.33 439.30 439.80 0.17 0.45 442.17 0.50 0.12 0.24 442.52 0.50 441.83 442.52 0.00 0.00 3.90 442.52 -1.98 Okay
PIPE OUTLET #10 CB 18.2 0.00 1.32 27.0 8 0.012 443.50 444.50 444.00 447.39 1.85% 3.79 0.22 0.33 444.00 444.00 0.17 0.27 444.67 0.50 0.11 0.22 445.00 0.50 444.33 445.00 0.00 0.00 3.79 445.00 -2.39 Okay
FWHS - Backwater Conveyance Calculation-Ph2 Permit.xls 7/30/2014
BACKWATER CALCULATION SPREADSHEET - 100 YEAR
Project Name:FWHS Designed By:MEB
Job Number:13003 Storm Event:100-yr, 24-hr
Conveyance System Information Outlet Control Inlet Control Headwater Summation Overtopping Check
Pipe Segment Surface Total Length Pipe "n" Down- Down- Up- Up- Pipe Barrel Barrel Critical TW TW Barrel Friction Entrance Entrance Entrance Exit Outlet Inlet Inlet Control Approach Bend Bend Q1 Q3 V1 Junction Head HW (HW - Rim) Over-
CB/MH # CB/MH # Flow Flow L Size value Stream Stream Stream Stream Slope Velocity Velocity Depth Elev. Check Hyd. Loss HGL Ke Head Head Control Control Control HW Veloctiy Kb Head Head Loss Elev. Clearance topping
Down Up Q Qtot D Invert Rim Invert Rim Head Rad.Elev.Loss Loss Elev.HW/D Elev.Elev.Head Loss Loss Total Check
CFS CFS FT IN FT FT FT FT % FPS FT FT FT FT FT FT FT FT FT FT FT FT FT FT FT CFS CFS FPS FT FT FT FT
CB 1.1 CB 1.2 0.27 6.60 245.0 24 0.012 429.65 433.35 430.88 439.00 0.50% 2.10 0.07 1.80 432.14 432.14 0.50 0.18 432.88 0.50 0.03 0.07 432.98 0.50 431.88 432.98 0.06 0.64 0.04 6.33 2.10 0.04 432.96 -6.04 Okay
CB 1.2 CB 1.3 (FCS) 0.00 6.33 8.0 24 0.012 430.88 439.00 430.92 441.50 0.50% 2.01 0.06 1.80 432.96 432.96 0.50 0.01 432.97 0.50 0.03 0.06 433.06 0.50 431.92 433.06 0.06 1.32 0.08 6.33 2.01 0.08 433.08 -8.42 Okay
CB 1.3 (FCS) INLET #1 1.17 6.33 34.0 24 0.012 431.00 439.00 431.00 440.00 0.00% 2.01 0.06 1.80 433.08 433.08 0.50 0.02 433.11 0.50 0.03 0.06 433.20 1.10 433.20 433.20 0.00 0.00 29.30 2.01 433.20 -6.80 Okay
PIPE OUTLET #2 CB 2.1 0.00 29.30 53.0 24 0.012 436.00 439.00 437.90 444.00 3.58% 9.33 1.35 1.75 431.00 437.88 0.50 0.76 439.90 0.50 0.68 1.35 441.93 1.80 441.50 441.93 1.35 0.12 0.16 29.30 9.33 0.16 440.74 -3.26 Okay
CB 2.1 CB 2.2 0.00 29.30 129.0 24 0.012 437.90 444.00 439.93 444.50 1.57% 9.33 1.35 1.75 440.74 440.74 0.50 1.84 442.58 0.50 0.68 1.35 444.60 1.80 443.53 444.60 1.35 0.48 0.65 29.30 9.33 0.65 443.90 -0.60 Okay
CB 2.2 CB 2.3 0.00 29.30 131.0 24 0.012 439.93 444.50 441.96 447.50 1.55% 9.33 1.35 1.75 443.90 443.90 0.50 1.87 445.77 0.50 0.68 1.35 447.79 1.80 445.56 447.79 1.35 0.00 29.30 9.33 446.44 -1.06 Okay
CB 2.3 CB 2.4 0.00 29.30 63.0 24 0.012 441.96 447.50 445.23 457.00 5.19% 9.33 1.35 1.75 446.44 446.44 0.50 0.90 447.34 0.50 0.68 1.35 449.36 1.80 448.83 449.36 1.35 0.00 29.30 9.33 448.01 -8.99 Okay
CB 2.4 CB 2.5 0.00 29.30 151.0 24 0.012 445.23 457.00 447.50 459.20 1.50% 9.33 1.35 1.75 448.01 448.01 0.50 2.15 450.17 0.50 0.68 1.35 452.19 1.80 451.10 452.19 1.27 1.32 1.78 28.40 0.90 9.33 0.04 1.82 452.74 -6.46 Okay
CB 2.5 CB 2.6 0.69 28.40 221.0 24 0.012 447.50 459.20 450.82 464.05 1.50% 9.04 1.27 1.75 452.74 452.74 0.50 2.96 455.70 0.50 0.63 1.27 457.60 1.80 454.42 457.60 0.11 0.00 8.22 19.49 9.04 1.13 1.13 458.62 -5.43 Okay
CB 2.6 CB 2.7 0.37 8.22 217.0 24 0.012 450.82 464.05 451.91 461.80 0.50% 2.62 0.11 1.12 458.62 458.62 0.50 0.24 458.87 0.50 0.05 0.11 459.02 0.75 453.41 459.02 0.07 0.00 3.65 4.19 2.62 0.06 0.06 459.02 -2.78 Okay
CB 2.7 CB 2.8 0.00 3.65 210.0 18 0.012 452.41 461.80 453.46 458.50 0.50% 2.07 0.07 0.74 459.02 459.02 0.38 0.22 459.24 0.50 0.03 0.07 459.34 0.60 454.36 459.34 0.23 1.32 0.09 3.00 0.66 2.07 0.01 0.10 459.21 0.71 Overtopping!!
CB 2.8 CB 2.9 1.14 3.00 106.0 12 0.012 453.96 458.50 456.32 461.30 2.23% 3.82 0.23 0.65 459.21 459.21 0.25 0.64 459.85 0.50 0.11 0.23 460.18 0.75 457.07 460.18 0.09 1.32 0.30 1.86 3.82 0.30 460.40 -0.90 Okay
CB 2.9 CB 2.10 0.40 1.86 125.0 12 0.012 456.32 461.30 457.74 461.00 1.14% 2.37 0.09 0.57 460.40 460.40 0.25 0.29 460.68 0.50 0.04 0.09 460.82 0.65 458.39 460.82 0.27 0.48 0.04 1.46 2.37 0.04 460.58 -0.42 Caution
CB 2.10 CB 2.11 0.73 1.46 73.0 8 0.012 458.07 461.00 458.57 460.60 0.68% 4.19 0.27 0.52 460.58 460.58 0.17 0.91 461.49 0.50 0.14 0.27 461.90 0.50 458.90 461.90 0.07 0.48 0.13 0.73 4.19 0.13 461.96 1.36 Overtopping!!
CB 2.11 CB 2.12 0.73 0.73 218.0 8 0.012 458.57 460.60 459.67 464.50 0.50% 2.10 0.07 0.36 461.96 461.96 0.17 0.68 462.64 0.50 0.03 0.07 462.74 0.50 460.00 462.74 0.00 0.00 2.10 462.74 -1.76 Okay
CB 2.5 CB 22.1 0.09 0.90 65.0 8 0.012 448.83 459.20 455.00 458.00 9.49% 2.58 0.10 0.40 452.74 452.74 0.17 0.31 455.67 0.50 0.05 0.10 455.82 0.50 455.33 455.82 0.08 1.32 0.14 0.81 2.58 0.14 455.87 -2.13 Okay
PIPE OUTLET #3 CB 22.2 0.81 0.81 49.0 8 0.012 457.00 457.50 457.25 458.15 0.51% 2.32 0.08 0.38 457.50 457.52 0.17 0.19 457.92 0.50 0.04 0.08 458.04 0.50 457.58 458.04 0.00 0.00 2.32 458.04 -0.11 Caution
CB 2.6 CB 4.1 3.01 6.47 90.0 12 0.012 450.82 464.05 460.00 463.50 10.20% 8.23 1.05 0.66 458.62 458.62 0.25 2.51 461.13 0.50 0.53 1.05 462.71 0.50 460.50 462.71 0.21 1.32 1.39 2.89 8.23 1.39 463.89 0.39 Overtopping!!
PIPE OUTLET #4 CB 4.2 1.06 2.89 79.0 12 0.012 463.00 463.50 465.50 468.20 3.16% 3.68 0.21 0.64 463.89 463.89 0.25 0.44 466.50 0.50 0.11 0.21 466.82 0.50 466.00 466.82 0.43 0.00 1.83 3.68 466.39 -1.81 Okay
CB 4.2 CB 4.3 1.27 1.83 67.0 8 0.012 465.50 468.20 468.50 471.80 4.48% 5.26 0.43 0.56 466.39 466.39 0.17 1.31 469.17 0.50 0.21 0.43 469.81 0.50 468.83 469.81 0.04 0.00 0.57 5.26 469.77 -2.03 Okay
PIPE OUTLET #5 CB 5.1 0.57 0.57 57.0 8 0.012 463.00 463.50 463.60 466.50 1.05% 1.62 0.04 0.31 463.50 463.50 0.17 0.11 464.27 0.50 0.02 0.04 464.33 0.50 463.93 464.33 0.00 0.00 1.62 464.33 -2.17 Okay
CB 2.6 CB 6.1 0.00 13.02 318.0 18 0.012 450.82 464.05 457.00 465.50 1.94% 7.37 0.84 1.23 458.62 458.62 0.38 4.15 462.77 0.50 0.42 0.84 464.04 0.50 457.75 464.04 0.07 1.32 1.11 1.65 11.37 7.37 1.05 2.17 466.13 0.63 Overtopping!!
CB 6.1 CB 6.2 0.00 1.65 292.0 12 0.012 457.00 465.50 468.00 478.00 3.77% 2.10 0.07 0.48 466.13 466.13 0.25 0.53 469.00 0.50 0.03 0.07 469.10 0.50 468.50 469.10 0.07 0.48 0.03 1.65 1.58 2.10 0.04 0.07 469.10 -8.90 Okay
CB 6.2 CB 6.3 0.00 1.65 59.0 12 0.012 468.00 478.00 472.00 482.10 6.78% 2.10 0.07 0.48 469.10 469.10 0.25 0.11 473.00 0.50 0.03 0.07 473.10 0.50 472.50 473.10 0.35 0.00 1.65 2.10 472.76 -9.34 Okay
CB 6.3 CB 6.4 1.65 1.65 83.0 8 0.012 472.00 482.10 480.00 483.00 9.64% 4.73 0.35 0.54 472.76 472.76 0.17 1.31 480.67 0.50 0.17 0.35 481.19 0.50 480.33 481.19 0.00 0.00 4.73 481.19 -1.81 Okay
CB 6.1 CB 7.1 0.54 1.53 242.0 12 0.012 457.50 465.50 460.00 465.00 1.03% 1.95 0.06 0.46 466.13 466.13 0.25 0.38 466.51 0.50 0.03 0.06 466.60 0.50 460.50 466.60 0.13 0.00 1.00 1.95 466.47 1.47 Overtopping!!
PIPE OUTLET #9 CB 7.2 1.00 1.00 20.0 8 0.012 464.00 465.00 464.10 465.70 0.50% 2.85 0.13 0.42 466.47 466.47 0.17 0.12 466.59 0.50 0.06 0.13 466.78 0.50 464.43 466.78 0.00 0.00 2.85 466.78 1.08 Overtopping!!
CB 6.1 CB 8.1 0.08 1.92 39.0 8 0.012 457.00 465.50 462.00 465.50 12.82% 5.51 0.47 0.58 466.13 466.13 0.17 0.84 466.97 0.50 0.24 0.47 467.68 0.50 462.33 467.68 0.12 1.32 0.62 0.98 0.87 5.51 0.24 0.86 468.42 2.92 Overtopping!!
CB 8.1 CB 8.2 0.25 0.98 63.0 8 0.012 462.00 465.50 462.66 466.50 1.05% 2.79 0.12 0.42 468.42 468.42 0.17 0.35 468.77 0.50 0.06 0.12 468.95 0.50 462.99 468.95 0.07 1.32 0.16 0.72 2.79 0.16 469.04 2.54 Overtopping!!
CB 8.2 CB 8.3 0.26 0.72 63.0 8 0.012 462.66 466.50 463.32 466.50 1.05% 2.06 0.07 0.36 469.04 469.04 0.17 0.19 469.23 0.50 0.03 0.07 469.33 0.50 463.65 469.33 0.03 0.00 0.46 2.06 469.31 2.81 Overtopping!!
CB 8.3 CB 8.4 0.46 0.46 58.0 8 0.012 463.32 466.50 463.93 466.80 1.05% 1.31 0.03 0.28 469.31 469.31 0.17 0.07 469.38 0.50 0.01 0.03 469.42 0.50 464.26 469.42 0.10 0.00 0.87 1.31 469.32 2.52 Overtopping!!
CB 8.1 CB 8.5 0.43 0.87 39.0 8 0.012 462.00 465.50 462.82 466.50 2.10% 2.50 0.10 0.39 469.32 469.32 0.17 0.17 469.49 0.50 0.05 0.10 469.64 0.50 463.15 469.64 0.03 0.48 0.05 0.44 2.50 0.05 469.66 3.16 Overtopping!!
CB 8.5 CB 8.6 0.44 0.44 51.0 8 0.012 462.82 466.50 463.37 466.50 1.08% 1.27 0.03 0.27 469.66 469.66 0.17 0.06 469.72 0.50 0.01 0.03 469.75 0.50 463.70 469.75 1.32 0.03 0.00 1.27 0.03 469.79 3.29 Overtopping!!
CB 6.1 CB 9.1 2.00 7.92 89.0 18 0.012 457.00 465.50 462.00 465.50 5.62% 4.48 0.31 0.96 466.13 466.13 0.38 0.43 466.56 0.50 0.16 0.31 467.03 0.50 462.75 467.03 0.00 0.00 4.48 467.03 1.53 Overtopping!!
CB 6.2 CB 10.1 0.00 1.58 60.0 8 0.012 468.00 478.00 469.00 477.00 1.67% 4.54 0.32 0.53 458.62 468.60 0.17 0.87 469.67 0.50 0.16 0.32 470.15 0.50 469.33 470.15 0.32 0.48 0.15 1.58 4.54 0.15 469.98 -7.02 Okay
CB 10.1 CB 10.2 0.11 1.58 86.0 8 0.012 469.00 477.00 470.50 473.50 1.74% 4.54 0.32 0.53 469.98 469.98 0.17 1.25 471.23 0.50 0.16 0.32 471.71 0.50 470.83 471.71 0.19 0.48 0.15 1.21 4.54 0.15 471.68 -1.82 Okay
CB 10.2 CB 10.3 1.21 1.21 64.0 8 0.012 470.50 473.50 471.00 474.00 0.78% 3.46 0.19 0.46 471.68 471.68 0.17 0.54 472.22 0.50 0.09 0.19 472.50 0.50 471.33 472.50 0.01 0.00 0.26 3.46 472.49 -1.51 Okay
PIPE OUTLET #8 CB 10.4 0.26 0.26 51.0 8 0.012 475.80 476.50 480.00 484.00 8.24% 0.76 0.01 0.21 472.49 476.24 0.17 0.02 480.67 0.50 0.00 0.01 480.68 0.50 480.33 480.68 0.00 0.00 0.76 480.68 -3.32 Okay
PIPE OUTLET #6 CB 11.1 0.69 3.24 101.0 12 0.012 464.00 464.50 465.50 468.80 1.49% 4.13 0.26 0.68 464.50 464.84 0.25 0.71 466.50 0.50 0.13 0.26 466.90 0.50 466.00 466.90 0.83 0.48 0.13 2.55 4.13 0.13 466.20 -2.60 Okay
CB 11.1 CB 11.2 0.58 2.55 72.0 8 0.012 465.50 468.80 469.50 472.30 5.56% 7.30 0.83 0.63 466.20 466.20 0.17 2.71 470.17 0.50 0.41 0.83 471.41 0.50 469.83 471.41 0.49 0.00 1.96 7.30 470.92 -1.38 Okay
CB 11.2 CB 11.3 0.75 1.96 70.0 8 0.012 469.50 472.30 472.50 475.50 4.29% 5.63 0.49 0.56 470.92 470.92 0.17 1.57 473.17 0.50 0.25 0.49 473.90 0.50 472.83 473.90 0.19 0.00 1.21 5.63 473.72 -1.78 Okay
CB 11.3 CB 11.4 0.01 1.21 70.0 8 0.012 472.50 475.50 476.00 480.50 5.00% 3.47 0.19 0.41 473.72 473.72 0.17 0.59 476.67 0.50 0.09 0.19 476.95 0.50 476.33 476.95 0.18 0.00 1.20 3.47 476.76 -3.74 Okay
CB 11.4 CB 11.5 1.20 1.20 14.0 8 0.012 476.00 480.50 476.50 480.00 3.57% 3.43 0.18 0.40 476.76 476.76 0.17 0.12 477.17 0.50 0.09 0.18 477.44 0.50 476.83 477.44 1.32 0.24 0.00 3.43 0.24 477.68 -2.32 Okay
PIPE OUTLET #7 CB 12.1 0.00 2.67 42.0 12 0.012 464.00 464.50 465.00 467.50 2.38% 3.40 0.18 0.33 464.50 464.67 0.25 0.20 466.00 0.50 0.09 0.18 466.27 0.50 465.50 466.27 0.91 0.48 0.09 2.67 3.40 0.09 465.45 -2.05 Okay
CB 12.1 CB 12.2 2.67 2.67 120.0 8 0.012 465.00 467.50 473.50 479.00 7.08% 7.66 0.91 0.33 465.45 465.50 0.17 4.97 474.17 0.50 0.46 0.91 475.53 0.50 473.83 475.53 1.32 1.20 0.00 7.66 1.20 476.73 -2.27 Okay
CB 2.7 CB 13.1 0.32 4.19 129.0 12 0.012 452.91 461.80 456.20 461.20 2.55% 5.34 0.44 0.33 459.02 459.02 0.25 1.51 460.54 0.50 0.22 0.44 461.20 0.50 456.70 461.20 0.38 1.32 0.58 3.88 5.34 0.58 461.41 0.21 Overtopping!!
CB 13.1 CB 13.2 1.78 3.88 125.0 12 0.012 456.20 461.20 459.20 464.20 2.40% 4.94 0.38 0.33 461.41 461.41 0.25 1.25 462.66 0.50 0.19 0.38 463.23 0.50 459.70 463.23 0.11 0.00 2.09 4.94 463.12 -1.08 Okay
CB 13.2 CB 13.3 2.09 2.09 109.0 12 0.012 459.20 464.20 460.29 463.50 1.00% 2.66 0.11 0.33 463.12 463.12 0.25 0.32 463.44 0.50 0.06 0.11 463.60 0.50 460.79 463.60 0.00 0.00 2.66 463.60 0.10 Overtopping!!
CB 13.3 CB 13.4 2.57 2.57 117.0 12 0.012 460.29 463.50 462.00 466.00 1.46% 3.27 0.17 0.33 463.60 463.60 0.25 0.52 464.12 0.50 0.08 0.17 464.37 0.50 462.50 464.37 0.00 0.00 0.08 3.27 464.37 -1.63 Okay
PIPE OUTLET #8 CB 21.1 0.08 0.08 58.0 8 0.012 452.50 453.50 453.80 456.80 2.24% 0.22 0.00 0.33 451.00 453.00 0.17 0.00 454.47 0.50 0.00 0.00 454.47 0.50 454.13 454.47 0.00 0.22 454.47 -2.33 Okay
FWHS - Backwater Conveyance Calculation-Ph2 Permit.xls 7/30/2014
Conveyance System Information Outlet Control Inlet Control Headwater Summation Overtopping Check
Pipe Segment Surface Total Length Pipe "n" Down- Down- Up- Up- Pipe Barrel Barrel Critical TW TW Barrel Friction Entrance Entrance Entrance Exit Outlet Inlet Inlet Control Approach Bend Bend Q1 Q3 V1 Junction Head HW (HW - Rim) Over-
CB/MH # CB/MH # Flow Flow L Size value Stream Stream Stream Stream Slope Velocity Velocity Depth Elev. Check Hyd. Loss HGL Ke Head Head Control Control Control HW Veloctiy Kb Head Head Loss Elev. Clearance topping
Down Up Q Qtot D Invert Rim Invert Rim Head Rad.Elev.Loss Loss Elev.HW/D Elev.Elev.Head Loss Loss Total Check
CFS CFS FT IN FT FT FT FT % FPS FT FT FT FT FT FT FT FT FT FT FT FT FT FT FT CFS CFS FPS FT FT FT FT
CB 2.8 CB 17.1 0.66 0.66 77.0 8 0.012 456.23 458.50 457.00 459.00 1.00% 1.88 0.05 0.33 459.21 459.21 0.17 0.19 459.40 0.50 0.03 0.05 459.48 0.50 457.33 459.48 1.32 0.07 1.88 0.07 459.56 0.56 Overtopping!!
S 308th Street ROW
EX CB #1 CB 14.1 0.05 7.59 26.0 30 0.012 429.00 433.42 429.65 433.35 2.50% 1.55 0.04 0.94 429.65 430.72 0.63 0.01 432.15 0.50 0.02 0.04 432.21 0.50 430.90 432.21 0.09 0.00 7.53 6.60 1.55 0.02 0.02 432.14 -1.21 Okay
CB 14.1 CB 14.2 0.38 7.53 91.0 24 0.012 429.65 433.35 430.14 432.68 0.54% 2.40 0.09 0.94 432.14 432.14 0.50 0.09 432.22 0.50 0.04 0.09 432.35 0.50 431.14 432.35 0.13 0.00 5.07 2.08 2.40 0.03 0.03 432.25 -0.43 Caution
CB 14.2 CB 14.3 1.63 5.07 52.0 18 0.012 430.14 432.68 430.43 432.47 0.56% 2.87 0.13 0.86 432.25 432.25 0.38 0.10 432.36 0.50 0.06 0.13 432.55 0.50 431.18 432.55 0.06 0.00 3.43 2.87 432.49 0.02 Overtopping!!
CB 14.3 CB 14.4 0.23 3.43 8.0 18 0.012 430.43 432.47 430.50 432.41 0.87% 1.94 0.06 0.75 432.49 432.49 0.38 0.01 432.50 0.50 0.03 0.06 432.58 0.50 431.25 432.58 0.26 0.00 3.21 1.94 432.32 -0.09 Caution
CB 14.4 CB 14.5 0.32 3.21 109.0 12 0.012 430.50 432.41 432.00 434.72 1.38% 4.08 0.26 0.82 432.32 432.32 0.25 0.75 433.07 0.50 0.13 0.26 433.46 0.50 432.50 433.46 0.21 0.00 2.88 4.08 433.25 -1.47 Okay
CB 14.5 CB 14.6 0.19 2.88 174.0 12 0.012 432.00 434.72 441.00 444.72 5.17% 3.67 0.21 0.79 433.25 433.25 0.25 0.97 442.00 0.50 0.10 0.21 442.31 0.50 441.50 442.31 0.04 0.00 1.21 1.48 3.67 0.13 0.13 442.41 -2.31 Okay
CB 14.6 CB 14.7 1.21 1.21 100.0 12 0.012 441.00 444.72 447.00 450.85 6.00% 1.55 0.04 0.41 442.41 442.41 0.25 0.10 448.00 0.50 0.02 0.04 448.06 0.50 447.50 448.06 0.00 1.21 1.55 448.06 -2.79 Okay
CB 14.1 CB 15.1 2.08 2.08 58.0 8 0.012 430.14 432.68 434.50 437.50 7.52% 5.97 0.55 0.62 432.25 432.25 0.17 1.46 435.17 0.50 0.28 0.55 436.00 0.50 434.83 436.00 1.32 0.73 0.00 5.97 0.73 436.73 -0.77 Okay
CB 14.5 CB 16.1 1.36 1.36 50.0 8 0.012 441.00 444.72 442.50 445.50 3.00% 3.91 0.24 0.49 442.41 442.41 0.17 0.54 443.17 0.50 0.12 0.24 443.52 0.50 442.83 443.52 0.00 1.32 0.31 0.00 3.91 0.31 443.83 -1.67 Okay
CB 14.6 CB 16.2 0.04 0.12 33.0 8 0.012 447.33 450.85 450.00 454.00 8.09% 0.33 0.00 0.52 442.41 447.92 0.17 0.00 450.67 0.50 0.00 0.00 450.67 0.50 450.33 450.67 1.32 0.00 0.00 0.33 0.00 450.67 -3.33 Okay
S 304th Street ROW
CB 18.2 CB 18.3 0.58 1.67 102.0 12 0.012 444.00 447.39 451.43 456.43 7.28% 2.13 0.07 0.33 445.20 445.20 0.25 0.19 452.43 0.50 0.04 0.07 452.54 0.50 451.93 452.54 0.01 0.00 1.09 2.13 452.52 -3.91 Okay
CB 18.3 CB 18.4 0.37 1.09 297.0 12 0.012 451.43 456.43 467.68 472.68 5.47% 1.39 0.03 0.33 452.52 452.52 0.25 0.24 468.68 0.50 0.02 0.03 468.73 0.50 468.18 468.73 0.00 0.00 0.72 1.39 468.72 -3.96 Okay
CB 18.4 CB 18.5 0.36 0.72 197.0 12 0.012 467.68 472.68 473.53 478.53 2.97% 0.92 0.01 0.33 468.72 468.72 0.25 0.07 474.53 0.50 0.01 0.01 474.55 0.50 474.03 474.55 0.00 0.00 0.36 0.92 474.55 -3.98 Okay
CB 18.5 CB 18.6 0.36 0.36 197.0 12 0.012 473.53 478.53 478.25 483.26 2.40% 0.45 0.00 0.33 474.55 474.55 0.25 0.02 479.25 0.50 0.00 0.00 479.25 0.50 478.75 479.25 0.00 0.10 0.45 479.25 -4.01 Okay
CB 18.6 CB 18.7 0.10 0.10 196.0 12 0.012 478.25 483.26 480.25 488.25 1.02% 0.13 0.00 0.33 479.25 479.25 0.25 0.00 481.25 0.50 0.00 0.00 481.25 0.50 480.75 481.25 0.00 0.00 0.13 481.25 -7.00 Okay
CB 18.1 CB 19.1 0.04 1.72 42.0 8 0.012 439.30 443.94 441.50 444.50 5.24% 4.92 0.38 0.33 443.30 443.30 0.17 0.72 444.02 0.50 0.19 0.38 444.58 0.50 441.83 444.58 0.00 0.00 4.92 444.58 0.08 Overtopping!!
PIPE OUTLET #10 CB 18.2 0.00 1.67 27.0 8 0.012 443.50 444.50 444.00 447.39 1.85% 4.79 0.36 0.33 444.00 444.00 0.17 0.44 444.67 0.50 0.18 0.36 445.20 0.50 444.33 445.20 0.00 0.00 4.79 445.20 -2.19 Okay
FWHS - Backwater Conveyance Calculation-Ph2 Permit.xls 7/30/2014
APPENDIX D – SEDIMENT POND SIZING
Developed (15-min time series) 2 Year Flow for Sediment Pond Sizing
Kirkland | Tacoma | Mount Vernon
425-827-7701 | www.aesgeo.com
February 8, 2021
Project No. 20200453E001
Federal Way Public Schools
33330 8th Avenue South
Federal Way, Washington 98003
Attention: Mr. Delin Huang
Subject: Preliminary Geotechnical Engineering Recommendations
Federal Way High School Memorial Field Improvements
1344 South 308th Street
Federal Way, Washington
Dear Mr. Huang:
This letter-report summarizes Associated Earth Sciences, Inc.’s (AESI’s) preliminary geotechnical
engineering recommendations for the proposed improvements to the Federal Way High School
Memorial Field located at 1344 South 308th Street in Federal Way, Washington. Our
recommendations are based on review of our previous work completed on the Federal Way High
School site, which has included subsurface explorations, geotechnical engineering studies, and
construction monitoring. Our work was completed in accordance with our proposal, dated
December 21, 2020.
SITE AND PROJECT DESCRIPTION
The project site is the Memorial Field athletics field and parking lot at the southwest corner of
the existing Federal Way High School property, located at 1344 South 308th Street in Federal Way,
Washington (King County Parcel No. 0821049001). The site is shown on the “Vicinity Map,”
Figure 1. The parking lot and stadium are roughly rectangular-shaped portions of the high school
parcel and are bound to the north by the high school baseball field, to the east by a parking lot
and the school building, to the south by South 308th Street, and to the west by existing
stormwater ponds and residential development. The football field is surrounded by an athletic
track and oriented with its long axis north-south. Grandstands overlook the field from the east
and west sides. The existing parking lot is gravel-surfaced, with ingress and egress at the east and
west ends of the parking lot. The ground surface is basically flat over most of the parking lot and
Federal Way High School
Memorial Field Improvements Preliminary
Federal Way, Washington Geotechnical Engineering Recommendations
February 8, 2021 ASSOCIATED EARTH SCIENCES, INC.
NS/ld - 20200453E001-3 Page 2
field and then slopes upward to the east at an inclination of about 2 Horizontal:1 Vertical (2H:1V)
on the east side of the field. Overall vertical relief across the site is on the order of 25 feet.
Details of the proposed improvements are limited at this time, but the improvements are
planned to occur in two phases. The first phase would consist of improvements to the parking
area and the second phase would consist of improvements to the stadium and field. Specifically,
the proposed improvements include the following:
• replacement of several stadium structures, including grandstands, bathrooms, and other
accessory structures;
• new asphalt pavement in the stadium parking lot;
• new pavement of pathways throughout the site;
• replacement of track surfaces and artificial turfs;
• improvements to infrastructure for site lighting, security, and other systems; and
• possibly frontage improvements.
The purpose of our work was to use existing subsurface information to develop preliminary
geotechnical engineering design recommendations for pavement, foundations, structural fills,
and seismic site class per current code requirements. The recommendations contained in the
letter-report are considered preliminary. The subsurface conditions that are the basis for the
recommendations in the letter-report were extrapolated from site explorations advanced for the
neighboring high school project. The assumed subsurface conditions should be verified by
site-specific explorations or by observation of exposed subgrades at the time of construction.
If differing subsurface conditions are encountered, the conclusions and recommendations
contained in this letter-report should be confirmed or changed to reflect the actual conditions
encountered.
PREVIOUS SUBSURFACE EXPLORATION
In order to collect subsurface information at the areas of the proposed improvements, we
reviewed our previous study at the site, which included drilling 10 exploration borings on
January 2 and 3, 2014 using a hollow-stem auger drilling rig. Our findings and analyses were
reported in our geotechnical engineering report titled, “Subsurface Exploration, Geologic
Hazards, and Geotechnical Engineering Report, Federal Way High School Replacement,” dated as
revised October 31, 2014. Eight of the 2014 exploration borings were drilled at the southeast
corner of the parcel near the high school building and two were drilled west of the Memorial
Field and parking lot area. The locations of the four nearest exploration borings, EB-4, EB-5, EB-9,
and EB-10, are shown on the “Existing Site and Exploration Plan,” Figure 2, and logs of these
Federal Way High School
Memorial Field Improvements Preliminary
Federal Way, Washington Geotechnical Engineering Recommendations
February 8, 2021 ASSOCIATED EARTH SCIENCES, INC.
NS/ld - 20200453E001-3 Page 3
explorations are included in the Appendix. Additional subsurface explorations were not included
in this scope of work.
The conclusions and recommendations presented in this letter-report are based on review of our
previous exploration borings at the site. The number, locations, and depths of the explorations
were completed within site and budgetary constraints. Because of the nature of exploratory work
below ground, interpolation of subsurface conditions between field explorations is necessary. It
should be noted that differing subsurface conditions may sometimes be present due to the
random nature of deposition and the alteration of topography by past grading and/or filling. The
nature and extent of any variations between the field explorations may not become fully evident
until construction. If variations are observed at that time, it may be necessary to re-evaluate
specific recommendations in this letter-report and make appropriate changes. Ground surface
elevations and subsurface conditions observed at the exploration boring locations may have been
altered by the construction and grading activities that occurred after the exploration during
construction of the existing school, and the conditions observed at the time of drilling may no
longer be representative of existing conditions.
The various types of soil and groundwater elevations, as well as the depths where soil and
groundwater characteristics changed, are indicated on the exploration boring logs presented in
the Appendix. The depths indicated on the logs where conditions changed may represent
gradational variations between sediment types in the field. If changes occurred between sample
intervals in our borings, they were interpreted.
SUBSURFACE CONDITIONS
Subsurface conditions at the project site were inferred from the field explorations accomplished
for our 2014 study and review of selected applicable geologic literature. The general distribution
of geologic units is shown on the exploration logs. The explorations generally encountered native
pre-Fraser sediments overlain in some areas by existing fill.
Stratigraphy
The following sections present more detailed subsurface information organized from the
youngest (shallowest) to the oldest (deepest) sediment types.
Federal Way High School
Memorial Field Improvements Preliminary
Federal Way, Washington Geotechnical Engineering Recommendations
February 8, 2021 ASSOCIATED EARTH SCIENCES, INC.
NS/ld - 20200453E001-3 Page 4
Existing Fill
Fill soils (soils not naturally placed) were encountered at the locations of exploration borings EB-9
and EB-10 to depths of 11 and 7 feet below the ground surface, respectively. The fill generally
consisted of loose, silty sand with gravel. Portions of the fill contained organic material. We
interpret the encountered fill as likely resulting from past grading activities, including the filling
of low areas west of the stadium and field. Fill thickness can vary over short distances and may
be deeper than observed in our explorations. Due to the variable density and content, the
existing fill soils are not suitable for foundation support.
Pre-Fraser Deposits
In exploration borings EB-4 and EB-5 and underlying the fill in exploration borings EB-9 and EB-10,
sediments consisted of medium dense to very dense, silty, fine to medium sand with gravel, siltier
areas, silt beds, and trace organics, interpreted as pre-Fraser deposits. The pre-Fraser deposits
were placed prior to the Fraser Glaciation and subsequently compacted by the weight of the
overlying glacial ice. The upper 3 to 5 feet of the pre-Fraser deposits were of lower density,
interpreted as being due to weathering. The pre-Fraser deposits extended to the full depths
explored of approximately 15.9 to 21.5 feet, as shown on the exploration logs in the Appendix.
The medium dense to very dense material is generally considered suitable for support of light- to
heavily-loaded foundations when in an intact, undisturbed condition. This material is moisture-
sensitive and susceptible to disturbance when wet.
Groundwater
We encountered groundwater seepage in exploration borings EB-9 and EB-10 at depths of 10 and
14 feet, respectively. We anticipate that the encountered groundwater likely represents a local
groundwater table within the underlying pre-Fraser deposits. We expect that shallow
groundwater seepage would likely represent interflow within the existing fill. Interflow occurs
when surface water percolates down through the surficial weathered or higher-permeability
sediments and becomes perched atop underlying, lower-permeability sediments. It should be
noted that the occurrence and level of groundwater seepage at the site may vary in response to
such factors as changes in season, precipitation, and site use. The explorations reviewed for this
study were completed on January 2 and 3, 2014.
PRELIMINARY GEOTECHNICAL DESIGN RECOMMENDATIONS
From a geotechnical engineering standpoint, it is our opinion that the site is suitable for the
proposed improvements provided the recommendations contained in this letter-report are
Federal Way High School
Memorial Field Improvements Preliminary
Federal Way, Washington Geotechnical Engineering Recommendations
February 8, 2021 ASSOCIATED EARTH SCIENCES, INC.
NS/ld - 20200453E001-3 Page 5
incorporated into the design and construction of the project. In general, foundations can be
supported by medium dense or denser native soils or structural fill, where dense, non-organic
existing fill is present under proposed lightly-loaded structures, such as pavement; it may be
suitable for structural support provided the subgrade can be compacted to a firm and unyielding
condition and with the approval of the geotechnical engineer. The following sections provide
preliminary recommendations for seismic site class, site preparation, structural fill, foundations,
pavement, and drainage.
Seismic Site Class
Seismic design shall be in accordance with the 2015 International Building Code (IBC). The native
soils at the site are consistent with seismic Site Class “D” as defined in ASCE 7 - Minimum Design
Loads for Buildings and Other Structures (2010) as referenced by the 2015 IBC and Site Class “D”
seismic design parameters should be used for design.
Site Preparation
Existing buried utilities, vegetation, topsoil, demolition debris, and any other deleterious
materials should be removed where they are located below planned construction areas. All
disturbed soils should be removed to expose underlying, undisturbed, native sediments and
replaced with structural fill, as needed. All excavations below final grade made for demolition or
clearing and grubbing activities should be backfilled, as needed, with structural fill. Erosion and
surface water control should be established around the clearing limits to satisfy local
requirements.
Once clearing and grubbing activities have been completed, existing fill, where encountered,
should be addressed. We recommend that existing fill be removed from below areas of planned
foundations to expose underlying, undisturbed native sediments, followed by restoration of the
planned foundation grade with compacted structural fill. Removal of existing fill should extend
laterally beyond the new foundation footprint a minimum of 2 feet. Care should be taken not to
disturb support soils of existing foundations, if any will remain. Support soils should be
considered those soils within a prism projected downward and outward from existing footings at
inclinations of 1H:1V. Where existing fill is removed and replaced with structural fill, conventional
shallow foundations may be used for building support. The required depth of removal should be
determined in the field based on actual conditions encountered during excavation.
Site Disturbance
The site soils contained a high percentage of fine-grained material, which makes them moisture-
sensitive and subject to disturbance when wet. The contractor must use care during site
Federal Way High School
Memorial Field Improvements Preliminary
Federal Way, Washington Geotechnical Engineering Recommendations
February 8, 2021 ASSOCIATED EARTH SCIENCES, INC.
NS/ld - 20200453E001-3 Page 6
preparation and excavation operations so that the underlying soils are not softened. If
disturbance occurs to soils in structural areas, the softened soils should be removed and the area
brought to grade with structural fill.
Proof-Rolling
Following the recommended clearing, stripping, and any planned excavation, the stripped
subgrade within large paving areas should be proof-rolled with heavy, rubber-tired construction
equipment, such as a fully-loaded, tandem-axle dump truck. Proof-rolling should be performed
prior to structural fill placement or foundation excavation. The proof-roll should be monitored
by the geotechnical engineer so that any soft or yielding subgrade soils can be identified. Any
soft/loose, yielding soils should be removed to expose firm and unyielding subgrade. The
subgrade should then be scarified, adjusted in moisture content, and recompacted to the
required density. Proof-rolling should only be attempted if soil moisture contents are at or near
optimum moisture content. Proof-rolling of wet subgrades could result in further degradation.
Low areas and excavations may then be raised to the planned finished grade with compacted
structural fill. Subgrade preparation and selection, placement, and compaction of structural fill
should be performed under engineering-controlled conditions in accordance with the project
specifications.
Structural Fill
Placement of structural fill may be necessary to establish desired grades at the site or to backfill
utility trenches or around foundations. All references to structural fill in this letter-report refer
to subgrade preparation, fill type, and placement and compaction of materials as discussed in
this section. If a percentage of compaction is specified under another section of this letter-report
the value given in that section should be used.
After overexcavation/stripping has been performed to the satisfaction of the geotechnical
engineer/engineering geologist, the exposed ground surface should be recompacted to a firm
and unyielding condition. If the subgrade contains too much moisture, suitable recompaction
may be difficult or impossible to attain and should probably not be attempted. In lieu of
recompaction, the area to receive fill should be blanketed with washed rock or quarry spalls to
act as a capillary break between the new fill and the wet subgrade. Where the exposed ground
remains soft and further overexcavation is impractical, placement of an engineered stabilization
fabric may be necessary to prevent contamination of the free-draining layer by silt migration
from below. After recompaction of the exposed ground is approved by the geotechnical engineer,
or a free-draining rock course is laid, structural fill may be placed to attain desired grades.
Federal Way High School
Memorial Field Improvements Preliminary
Federal Way, Washington Geotechnical Engineering Recommendations
February 8, 2021 ASSOCIATED EARTH SCIENCES, INC.
NS/ld - 20200453E001-3 Page 7
Structural fill is defined as non-organic soil, acceptable to the geotechnical engineer, placed in
maximum 8-inch loose lifts, with each lift being compacted to at least 95 percent of the modified
Proctor maximum dry density using ASTM International (ASTM) D-1557 as the standard. Utility
trench backfill should be placed and compacted in accordance with applicable municipal codes
and standards. The top of the compacted fill should extend horizontally a minimum distance of
3 feet beyond footings or pavement edges before sloping down at an angle no steeper than
2H:1V. Fill slopes should either be overbuilt and trimmed back to final grade or
surface-compacted to the specified density.
We recommend that a clean, free-draining gravel and/or sand be used in structural areas.
Free-draining fill consists of non-organic soil with the amount of fine-grained material limited to
5 percent by weight when measured on the minus No. 4 sieve fraction. Soils in which the amount
of fine-grained material (smaller than No. 200 sieve) is greater than approximately 5 percent
(measured on the minus No. 4 sieve size) should be considered moisture-sensitive. Portions of
the site soils contained significant fine-grained fractions and are considered moisture-sensitive.
The use of moisture-sensitive soil in structural fills should be limited to favorable dry weather
conditions and non-structural areas such as under landscaping.
The contractor should note that any proposed fill soils must be evaluated by AESI prior to their
use in fills. This would require that we have a sample of the material at least 3 business days in
advance to perform a Proctor test and determine its field compaction standard.
A representative from our firm should observe the stripped subgrade and be present during
placement of structural fill to monitor the work and perform a representative number of in-place
density tests. In this way, the adequacy of the earthwork may be evaluated as filling progresses
and any problem areas may be corrected at that time. It is important to understand that taking
random compaction tests on a part-time basis will not assure uniformity or acceptable
performance of a fill. As such, we are available to aid the owner in developing a suitable
monitoring and testing frequency.
Foundations
In the exploration borings located near the site, suitable bearing soils were observed at depths
of about 5 feet in EB-4 and EB-5 east of the site and 8 to 12 feet in EB-9 and EB-10 west of the
site. Based on our current understanding of the project, significant foundations are not planned
near the western part of the site, where the bearing stratum was encountered relatively deep
within the existing detention pond areas. Therefore, we anticipate that any proposed structures
can be supported on conventional shallow spread footings. If changes to the proposed
improvements include new foundations near the west end of the site, additional field studies
Federal Way High School
Memorial Field Improvements Preliminary
Federal Way, Washington Geotechnical Engineering Recommendations
February 8, 2021 ASSOCIATED EARTH SCIENCES, INC.
NS/ld - 20200453E001-3 Page 8
may be needed to verify subsurface conditions and depth to bearing soils in the proposed
foundation areas.
For footings bearing directly on medium dense to dense natural sediments, or on structural fill
placed over these materials as described above, we recommend that an allowable foundation
soil bearing pressure of 2,500 pounds per square foot (psf) be used for design purposes, including
both dead and live loads. An increase of one-third may be used for short-term wind or seismic
loading.
Perimeter footings should be buried at least 18 inches into the surrounding soil for frost
protection. However, all footings must penetrate to the prescribed bearing stratum, and no
footing should be founded in or above organic or loose soils. All footings should have a minimum
width of 18 inches. It should be noted that the area bound by lines extending downward at 1H:1V
from any footing must not intersect another footing or intersect a filled area that has not been
compacted to at least 95 percent of ASTM D-1557. In addition, a 1.5H:1V line extending down
from any footing must not daylight because sloughing or raveling may eventually undermine the
footing. Thus, footings should not be placed near the edge of steps or cuts in the bearing soils.
Anticipated settlement of footings founded as described above should be on the order of 1 inch
or less. However, disturbed soil not removed from footing excavations prior to footing placement
could result in increased settlements. All footing areas should be inspected by AESI prior to
placing concrete to verify that the design bearing capacity of the soils has been attained and that
construction conforms to the recommendations contained in this letter-report. Such inspections
may be required by the City of Federal Way.
Perimeter footing drains should be provided, as discussed under the “Drainage Considerations”
section of this letter-report.
Floor Support
Slab-on-grade floors may be used over medium dense or denser native soils, inorganic existing
fills soils re-compacted to 95 percent relative compaction, or over structural fill placed as
recommended in the “Site Preparation” and “Structural Fill” sections of this letter-report. Slab
design can assume a soil subgrade modulus of 200 pounds per cubic inch (pci) for slabs cast over
the medium dense, natural sediments, re-compacted existing fill or properly compacted
structural fill placed over these materials. Slab-on-grade floors should be cast atop a minimum of
4 inches of washed pea gravel or washed crushed “chip” rock with less than 3 percent passing
the U.S. No. 200 sieve to act as a capillary break. The floors should also be protected from
dampness by covering the capillary break layer with an impervious moisture barrier at least 10
mils in thickness.
Federal Way High School
Memorial Field Improvements Preliminary
Federal Way, Washington Geotechnical Engineering Recommendations
February 8, 2021 ASSOCIATED EARTH SCIENCES, INC.
NS/ld - 20200453E001-3 Page 9
Passive Resistance and Friction Factors
All backfill around foundation units should be placed per our recommendations for structural fill
and as described in the “Structural Fill” section of this letter-report. Lateral loads can be resisted
by friction between the foundation and the natural glacial soils or supporting structural fill soils,
and by passive earth pressure acting on the buried portions of the foundations. The foundations
must be backfilled with structural fill and compacted to at least 95 percent of the maximum dry
density to achieve the passive resistance provided below. We recommend the following
allowable design parameters:
Passive equivalent fluid = 350 pounds per cubic foot
Coefficient of friction = 0.35
Drainage Considerations
Foundations should be provided with foundation drains placed at the bottom of footing or slab
elevation. Drains should consist of rigid, perforated, polyvinyl chloride (PVC) pipe surrounded by
washed pea gravel. The drains should be constructed with sufficient gradient to allow gravity
discharge away from any proposed buildings. Roof and surface runoff should not discharge into
the footing drain system, but should be handled by a separate, rigid, tightline drain. In planning,
exterior grades adjacent to walls should be sloped downward away from the proposed structures
to achieve surface drainage.
Pavement
Pavement areas should be prepared in accordance with the “Site Preparation” section of this
letter-report. If the stripped native soil or existing fill pavement subgrade can be compacted to
95 percent of ASTM D-1557 and is firm and unyielding, no additional overexcavation is required.
Soft or yielding areas should be overexcavated to provide a suitable subgrade and backfilled with
structural fill. The pavement sections included in this letter-report section are for driveway and
parking areas onsite, and are not applicable to right-of-way improvements. At this time we are
not aware of any planned right-of-way improvements; however, if any new paving of public
streets is required, we should be allowed to offer situation-specific recommendations.
The exposed ground should be recompacted to 95 percent of ASTM D-1557 and proof-rolled in
accordance with the “Proof-Rolling” section of this letter-report. If required, structural fill may
then be placed to achieve desired subbase grades. After the prepared subgrade is approved by
the geotechnical engineer, the overlying pavement in areas of planned passenger car driving and
parking can consist of a minimum of 2 inches of asphaltic concrete pavement (ACP) underlain by
4 inches of 1¼-inch crushed surfacing base course. In driveway areas subjected to heavier loads,
Federal Way High School
Memorial Field Improvements Preliminary
Federal Way, Washington Geotechnical Engineering Recommendations
February 8, 2021 ASSOCIATED EARTH SCIENCES, INC.
NS/ld - 20200453E001-3 Page 10
such as that from delivery trucks or school buses, a minimum pavement section consisting of
3 inches of ACP underlain by 2 inches of 5/8-inch crushed surfacing top course and 4 inches of
1¼-inch crushed surfacing base course is recommended. The crushed rock courses must be
compacted to 95 percent of the maximum density, as determined by ASTM D-1557. All paving
materials should meet gradation criteria contained in the current Washington State Department
of Transportation (WSDOT) Standard Specifications.
Depending on construction staging and desired performance, the crushed base course material
may be substituted with asphalt treated base (ATB) beneath the final asphalt surfacing. The
substitution of ATB should be as follows: 4 inches of crushed rock can be substituted with
3 inches of ATB, and 6 inches of crushed rock may be substituted with 4 inches of ATB. ATB should
be placed over a native or structural fill subgrade compacted to a minimum of 95 percent relative
density, and a 1½- to 2-inch thickness of crushed rock to act as a working surface. If ATB is used
for construction access and staging areas, some rutting and disturbance of the ATB surface should
be expected. The general contractor should remove affected areas and replace them with
properly compacted ATB prior to final surfacing.
LIMITATIONS
This letter-report has been prepared for the exclusive use of Federal Way Public Schools and their
agents for specific application to this project. Within the limitations of scope, schedule, and
budget, our services have been performed in accordance with generally accepted geotechnical
engineering practices in effect in this area at the time our letter-report was prepared. No other
warranty, express or implied, is made.
CLOSURE
Our recommendations should be considered preliminary in that project plans and construction
details have not been finalized at the time of this letter-report. We are available to provide
additional geotechnical consultation as the project design develops and possibly changes from
that upon which this letter-report is based. We recommend that AESI perform a final
geotechnical review of the plans prior to final design completion. In this way, our earthwork and
foundation recommendations may be properly interpreted and implemented in the design.
We are also available to provide geotechnical engineering and monitoring services during
construction. The integrity of the foundations and pavement depends on proper site preparation
and construction procedures. In addition, engineering decisions may have to be made in the field
in the event that variations in subsurface conditions become apparent. Construction monitoring
Federal Way High School
Memorial Field Improvements Preliminary
Federal Way, Washington Geotechnical Engineering Recommendations
February 8, 2021 ASSOCIATED EARTH SCIENCES, INC.
NS/ld - 20200453E001-3 Page 11
services are not part of this current scope of work. If these services are desired, please let us
know, and we will prepare a proposal.
We have enjoyed working with you on this study and are confident these recommendations will
aid in the successful completion of your project. If you should have any questions or require
further assistance, please do not hesitate to call.
Sincerely,
ASSOCIATED EARTH SCIENCES, INC.
Kirkland, Washington
______________________________
Nicki Shobert, E.I.T. Kurt D. Merriman, P.E.
Project Engineer Senior Principal Engineer
Attachments: Figure 1. Vicinity Map
Figure 2. Existing Site and Exploration Plan
Appendix. Exploration Logs
APPENDIX
Exploration Logs
Technical Information Report
Federal Way High School Pre-Apprenticeship Space
2210134.10
Section 7
Other Permits
Technical Information Report
Federal Way High School Pre-Apprenticeship Space 7-1
2210134.10
7.0 Other Permits
Required permits for this project include City of Federal Way Use Process I approval, a City of
Federal Way Engineering Permit, and a City of Federal Way Building Permit. No other permits
are anticipated requirements.
Technical Information Report
Federal Way High School Pre-Apprenticeship Space
2210134.10
Section 8
CSWPPP Analysis and Design
Technical Information Report
Federal Way High School Pre-Apprenticeship Space 8-1
2210134.10
8.0 CSWPPP Analysis and Design
The proposed development will comply with guidelines set forth in the KCSWDM. The plan
includes erosion/sedimentation control measures designed to prevent sediment -laden runoff from
leaving the site or from adversely affecting critical water resources during construction.
ESC Plan Analysis and Design (Part A)
The erosion potential of the site is influenced by four major factors: soil characteristics, vegetative
cover, topography, and climate. Erosion/sedimentation control is achieved by a combination of
structural measures, cover measures, and construction practices that are tailored to fit the
specific site.
The following measures will be used to control erosion/sedimentation processes. These
measures comply with the Erosion and Sediment Control Standards in the KCSWDM.
• Clearing Limits: Prior to beginning land-disturbing activities, clearing limits will be marked
with high-visibility plastic fence or temporary construction fencing. Significant vegetation to
remain will be marked and protected by fencing.
• Cover Measures: Disturbed areas shall be permanently or temporarily covered, as
required in Section D.4.2 of the KCSWDM. Temporary measures include plastic sheeting
and mulch. Permanent measures include gravel surfacing and vegetation.
• Perimeter Protection: Silt fence will be installed at the perimeter of the disturbed areas to
protect them. The silt fence will help to remove sediment from surface water and will
provide some flow control.
• Traffic Area Stabilization: Existing paved surfaces will be used for a construction
entrance; a stabilized construction entrance may be used, if found necessary. Wheel
washing and/or street sweeping will be provided, as necessary, to prevent tracking of
sediment onto adjacent surfaces.
• Sediment Retention: Inlet protection devices will be installed in all existing and new catch
basins. Additionally, silt fence will be installed at the perimeter of the disturb ed areas.
These measures will assist with sediment retention during construction.
• Surface Water Collection: Surface water from the threshold discharge area will sheet
flow toward the project boundary or to a catch basin. Inlet protection devices will be
installed in all new and existing catch basins and silt fence will be installed at the project
boundary. These measures will assist with removing sediment from surface water. The
disturbed area within the threshold discharge area is small and does not require large
collection devices, such as sediment traps or ponds.
• Dewatering Control: Water may be encountered during ground disturbing activities. If
water is encountered, the contractor shall remove it and dispose of it in a manner that does
not pollute surface water or cause downstream erosion or flooding. Examples of disposal
options include use of a sedimentation bag with outfall to a swale for small volumes of
localized dewatering or transporting it in a vehicle for legal offsite disposal.
• Dust Control: If necessary, the contractor shall spray exposed soils with water to prevent
wind transport of soil.
Technical Information Report
Federal Way High School Pre-Apprenticeship Space 8-2
2210134.10
• Flow Control: The disturbed area within the threshold discharge area is very small ,
approximately 0.2 acre in size or less. Because of the small nature of the site, the need for
formal flow control facilities is not anticipated during construction. The silt fence installed at
the perimeter of the site will provide some level of flow control for surface water.
No known hazard areas are located on or near the project site.
8.1.1 ESC Maintenance
All ESC measures shall be maintained and reviewed on a regular basis, as prescribed in the
maintenance requirements of each BMP (see Figure 8-3).
8.1.2 ESC Supervisor
The contractor shall designate an Erosion and Sedimentation Control (ESC) supervisor who shall
be responsible for maintenance and review of ESC and for compliance w ith all permit conditions
relating to ESC. The ESC supervisor must be available for rapid response to ESC problems.
The ESC supervisor is required to be a Certified Erosion and Sedimentation Control Lead
(CESCL), with demonstrated expertise in ESC to perform these reviews and to be responsible for
ESC implementation.
8.1.3 Documentation
The ESC supervisor shall review the site at least once a month during the dry season, weekly
during the wet season, and within 24 hours of significant storms. Written records o f these
reviews shall be kept onsite, with copies submitted to City of Federal Way within 48 hours.
If the Department of Development and Environmental Services (DDES) requires that a written
record be maintained, a standard ESC Maintenance Report, included here as Figure 8-1, may be
used. A copy of all required maintenance reports shall be kept onsite throughout the duration of
construction.
8.1.4 Review Timing
During the wet season, weekly reviews shall be carried out every six to eight calendar days.
During the dry season, monthly reviews shall be carried out within three days of the calendar day
for the last inspection (e.g., if an inspection occurred on June 6, then the next inspection must
occur between July 3 and July 9). Reviews shall also take place within 24 hours of significant
storms. In general, a significant storm is one with more than 0.5 inch of rain in 24 hours or less.
Another indication that a storm is "significant" is if gullies form as a result of the runoff.
Stormwater Pollution Prevention and Spill (SWPPS) Plan Design (Part B)
The below SWPPS Plan shall be completed by the contractor for use during construction of the
project. Blanks are intentional as they are part of the contractor’s means and methods.
The Stormwater Pollution Prevention and Spill (SWPPS) Plan includes three elements: a site
plan, a pollution prevention report, and a spill prevention and cleanup report. This report includes
identifying the expected sources of potential pollution and spills that may occur during
construction, and works to develop a plan to prevent pollution and spills. It also develops a plan
to mitigate spills that may occur. The SWPPS Plan will be kept on-site at all times during
construction. The general contractor will be responsible to ensure that subcontractors are aware
of the SWPPS Plan and a form or record will be provided stating that all subcontractors have read
and agree to the SWPPS Plan. An employee training worksheet is provided for the contractor’s
use (see Figure 8-2).
Technical Information Report
Federal Way High School Pre-Apprenticeship Space 8-3
2210134.10
A SWPPS Site Plan will be developed by the contractor. The SWPPS Site Plan, Pollution
Prevention Report, and Spill Prevention and Cleanup Report were preliminarily developed and
BMPs were selected based on Section 2.3.1.4 of the KCSWDM and the KCSPPM.
8.2.1 Pollution and Spill Prevention Source Controls and BMPs
The sources of pollution and spills are identified below, and the BMPs to be used for each source
for prevention of both pollution and spills are listed below:
Liquids that will be handled or stored on-site are the following: _________. Containers will be
stored as shown on the SWPPS Site Plan and include the following types and sizes:
___________. Tight-fitting lids shall be placed on all containers containing liquids. Containers
shall be covered with plastic sheeting during rain events. Drip pans or absorbent materials shall
be placed beneath all mounted container taps and at all potential drip and spill locations during
filling and unloading of containers. Containers shall be stored such that if a container leaks or
spills, the contents will not be discharged, flow, or be washed into the storm drainage system,
surface water, or groundwater. Appropriate spill cleanup materials shall be stored and
maintained near the container storage area. Storage area shall be swept and cleaned as
needed. Area shall not be hosed down such that water drains to the storm drainage system or
neighboring areas. Containers shall be checked daily for leaks and spills and replaced, as
necessary. All spilled liquids will be collected and disposed of properly. Spill control devices
shall be routinely inspected on a weekly basis.
Dry pesticides and fertilizers shall be covered with plastic sheeting or stored in a sealed
container. Materials shall be stored on pallets or another raised method to prevent contact with
stormwater runoff. Alternatively, the materials shall be contained in a manner such that if the
container leaks or spills, the contents will not discharge, flow, or be washed into the storm
drainage system, surface waters, or groundwater. Maintenance requirements are the same as
liquid materials described above.
Chemicals that will be handled or stored on-site are the following: _________. Containers will be
stored as shown on the SWPPS Site Plan and include the following types and sizes:
___________. BMPs and maintenance requirements are the same as liquids with the addition of
the following ______.
Soil, sand, and other erodible materials shall be stored on-site in a contractor-designated
location. Materials shall be covered with plastic sheeting per standard detail. Perimeter controls
shall be constructed as shown on the TESC plan to prevent eroded materials from leaving the
project site.
Fueling shall not occur on-site. If fueling does occur on-site, the contractor shall develop a
containment plan for spills and provide lighting and signage if fueling occurs at night in
conformance with the KCSPPM.
Maintenance and repair of vehicles shall not occur on-site. If maintenance or repair of vehicles
does occur on-site, the contractor shall develop a spill prevention plan in conformance with the
KCSPPM.
Truck wheel washing shall occur in a controlled manner, such that runoff is collected and
disposed of in a legal manner.
Rinsing of hand tools shall occur in a designated location, and water for washing shall be
collected and disposed of in a legal manner.
Technical Information Report
Federal Way High School Pre-Apprenticeship Space 8-4
2210134.10
Contaminated soils shall be covered with plastic sheeting or contained to prevent stormwater
from carrying pollutants away to surface or ground waters. Appropriate spill cleanup materials,
such as brooms, dustpans, vacuum sweepers, etc., shall be stored and maintained near the
storage area. Storage area shall be swept and cleaned as needed. Area shall not be hose d
down such that water drains to the storm drainage system, groundwater, surface water, or
neighboring areas.
During concrete and asphalt construction, the contractor shall provide the following BMPs or
equivalent measures, methods or practices as requir ed:
1. Drip pans, ground cloths, heavy cardboard, or plywood wherever concrete, asphalt, and
asphalt emulsion chunks and drips are likely to fall unintentionally, such as beneath
extraction points from mixing equipment.
2. Storm drains shall be covered to prevent concrete and asphalt from entering the storm
system.
3. Concrete, concrete slurry, and rinse water shall be contained and collected, and shall not
be washed or allowed to discharge into storm drain, ditch, or neighboring parcels. All
collected runoff shall be properly disposed of.
4. Contractor shall designate an area where application and mixing equipment cleaning will
be conducted. Rinse water and slurry shall be collected, contained, and disposed of in a
legal manner.
5. Routine maintenance: the pouring area shall be swept at the end of each day or more
frequently if needed. Loose aggregate chunks and dust shall be collected. Areas shall not
be hosed down.
The contractor may provide the following optional BMPs if the above do not provide adequate
source controls:
6. Cover portable mixing equipment with an awning or plastic sheeting to prevent contact with
rainfall.
7. Provide catch basin inserts configured for pollutant removal.
pH elevated water shall not be discharged from the site. Contractor shall monitor stormwater for
pH prior to discharging from the site. Contractor shall implement a pH treatment plan if pH is not
within the natural range.
8.2.2 Responsible Personnel and Contact Information
The contractor shall designate an ESC Supervisor and post their contact name, company, and
phone number and/or email in a readily visible location onsite.
[name] with [company] shall be responsible for pollution and spill prevention and
cleanup and can be contacted at [phone] or [email] .
Contractor shall fill out the attached Pollution Prevention Team Worksheet (see Figure 8-2).
Technical Information Report
Federal Way High School Pre-Apprenticeship Space 8-5
2210134.10
8.2.3 Pollution and Spill Prevention Worksheets
Pollution prevention, BMP implementation reports, material inventory worksheets, pollutant
source identification worksheet, and spill/leak report may be found attached as Figure 8-2.
8.2.4 Disposal Methods
Contractor shall dispose of contaminated soils and water in a legal manner. Options include the
following: _______________.
Technical Information Report
Federal Way High School Pre-Apprenticeship Space
2210134.10
Section 8.0 Figures
Figure 8-1 ......... ESC Maintenance Report
Figure 8-2 ......... CSWPP Forms
Figure 8-3 ......... Pollution Prevention Inspection Reports, Spill Prevention Monitoring, and
Spill Incident Reports
KING COUNTY, WASHINGTON, SURFACE WATER DESIGN MANUAL
E S C M A I N T E N A N C E R E P O R T
Performed By:___________________________
Date:___________________________
Project Name:___________________________
DPER Permit #:___________________________
Clearing Limits
Damage OK Problem
Visible OK Problem
Intrusions OK Problem
Other OK Problem
Mulch
Rills/Gullies OK Problem
Thickness OK Problem
Other OK Problem
Nets/Blankets
Rills/Gullies OK Problem
Ground Contact OK Problem
Other OK Problem
Plastic
Tears/Gaps OK Problem
Other OK Problem
Seeding
Percent Cover OK Problem
Rills/Gullies OK Problem
Mulch OK Problem
Other OK Problem
Sodding
Grass Health OK Problem
Rills/Gullies OK Problem
Other OK Problem
Perimeter Protection including Silt Fence
Damage OK Problem
Sediment Build-up OK Problem
Concentrated Flow OK Problem
Other OK Problem
Flow Control BMP protection
Damage OK Problem
Sedimentation OK Problem
Concentrated Flow OK Problem
Rills/Gullies OK Problem
Intrusions OK Problem
Other OK Problem
Brush Barrier
Damage OK Problem
Sediment Build-up OK Problem
Concentrated Flow OK Problem
Other OK Problem
Vegetated Strip
Damage OK Problem
Sediment Build-up OK Problem
Concentrated Flow OK Problem
Other OK Problem
Construction Entrance
Dimensions OK Problem
Sediment Tracking OK Problem
Vehicle Avoidance OK Problem
Other OK Problem
2016 Surface Water Design Manual – Appendix D CSWPP Forms 4/24/2016
KING COUNTY, WASHINGTON, SURFACE WATER DESIGN MANUAL
Wheel Wash
Dimensions OK Problem
Sed build up or tracking OK……. Problem
Other OK Problem
Construction Road
Stable Driving Surf. OK Problem
Vehicle Avoidance OK Problem
Other OK Problem
Sediment Trap/Pond
Sed. Accumulation OK Problem
Overtopping OK Problem
Inlet/Outlet Erosion OK Problem
Other OK Problem
Catch Basin/Inlet Protection
Sed. Accumulation OK Problem
Damage OK Problem
Clogged Filter OK Problem
Other OK Problem
Interceptor Dike/Swale
Damage OK Problem
Sed. Accumulation OK Problem
Overtopping OK Problem
Other OK Problem
Pipe Slope Drain
Damage OK Problem
Inlet/Outlet OK Problem
Secure Fittings OK Problem
Other OK Problem
Ditches
Damage OK Problem
Sed. Accumulation OK Problem
Overtopping OK Problem
Other OK Problem
Outlet Protection
Scour OK Problem
Other OK Problem
Level Spreader
Damage OK Problem
Concentrated Flow OK Problem
Rills/Gullies OK Problem
Sed. Accumulation OK Problem
Other OK Problem
Dewatering Controls
Sediment OK.. Problem
Dust Control
Palliative applied OK Problem
Miscellaneous
Wet Season Stockpile OK Problem
Other OK Problem
Comments:
Actions Taken:
Problems Unresolved:
2016 Surface Water Design Manual – Appendix D CSWPP Forms 4/24/2016
KING COUNTY, WASHINGTON, SURFACE WATER DESIGN MANUAL
BMP Implementation
Completed by:
Title:
Date:
Develop a plan for implementing each BMP. Describe the steps necessary to implement the BMP (i.e., any
construction or design), the schedule for completing those steps (list dates), and the person(s) responsible for
implementation.
BMPs
Description of Action(s) Required for
Implementation
Scheduled Milestone and
Completion Date(s)
Person
Responsible for
Action
Good
Housekeeping
1.
2.
3
Preventive
Maintenance
1.
2.
3.
4.
Spill
Prevention
and
Emergency
Cleanup
1.
2.
3.
Inspections 1.
2.
3.
2016 Surface Water Design Manual – Appendix D CSWPP Forms 4/24/2016
KING COUNTY, WASHINGTON, SURFACE WATER DESIGN MANUAL
BMPs
Description of Action(s) Required for Implementation
Schedule Milestone and
Completion Date(s)
Person
Responsible for
Action
Source Control
BMPs
1.
2.
3
4.
5.
6.
7.
8.
Treatment BMPs 1.
2.
3.
4.
Emerging
technologies
1.
2.
Flow Control
BMPs
3.
4.
2016 Surface Water Design Manual – Appendix D CSWPP Forms 4/24/2016
KING COUNTY, WASHINGTON, SURFACE WATER DESIGN MANUAL
Pollution Prevention Team
Completed by: ______________________
Title: ______________________________
Date: ______________________________
Responsible Official: Title:
Team Leader: Office Phone:
Cell Phone #:
Pager #:
Responsibilities:
(1) Title:
Office Phone:
Pager #:
Cell Phone:
Responsibilities:
(2) Title:
Office Phone:
Pager #:
Cell Phone #:
Responsibilities:
2016 Surface Water Design Manual – Appendix D CSWPP Forms 4/24/2016
KING COUNTY, WASHINGTON, SURFACE WATER DESIGN MANUAL
Employee Training
Completed by:
Title:
Date:
Describe the annual training of employees on the SWPPP, addressing spill response, good housekeeping, and material management practices.
Training Topics
1.) LINE WORKERS
Brief Description of Training Program/Materials
(e.g., film, newsletter course)
Schedule for Training
(list dates)
Attendees
Spill Prevention and
Response
Good Housekeeping
Material Management
Practices
2.) P2 TEAM:
SWPPP Implementation
Monitoring Procedures
2016 Surface Water Design Manual – Appendix D CSWPP Forms 4/24/2016
KING COUNTY, WASHINGTON, SURFACE WATER DESIGN MANUAL
List of Significant Spills and Leaks
Completed by:
Title:
Date:
List all spills and leaks of toxic or hazardous pollutants that were significant but are not limited to, release of oil or hazardous substances in excess of reportable
quantities. Although not required, we suggest you list spills and leaks of non-hazardous materials.
Description Response Procedure
Date
(month/day/ye
ar)
Location
(as
indicated
on site
map)
Type of
Material
Quantit
y
Sourc
e, If
Known
Reason for
Spill/Leak
Amount of
Material
Recovered
Material No
longer
exposed to
Stormwater
(Yes/No)
Preventive Measure Taken
2016 Surface Water Design Manual – Appendix D CSWPP Forms 4/24/2016
KING COUNTY, WASHINGTON, SURFACE WATER DESIGN MANUAL
Potential Pollutant Source Identification
Completed by:
Title:
Date:
List all potential stormwater pollutants from materials handled, treated, or stored on-site.
Potential Stormwater Pollutant
Stormwater Pollutant Source
Likelihood of pollutant being present in your
stormwater discharge. If yes, explain
2016 Surface Water Design Manual – Appendix D CSWPP Forms 4/24/2016
KING COUNTY, WASHINGTON, SURFACE WATER DESIGN MANUAL
Material Inventory
Completed by:
Title:
Date:
List materials handled, treated, stored, or disposed of at the project site that may potentially be exposed to precipitation or runoff.
Quantity (Units) Likelihood of contact with stormwater Past Spill or
Used Produced Stored If Yes, describe reason Leak
Material Purpose/Location (indicate per/wk. or yr.) Yes No
2016 Surface Water Design Manual – Appendix D CSWPP Forms 4/24/2016
Technical Information Report
Federal Way High School Pre-Apprenticeship Space
2210134.10
Section 9
Bond Quantities, Facilities Summaries, and
Declarations of Covenant
Technical Information Report
Federal Way High School Pre-Apprenticeship Space 9-1
2210134.10
9.0 Bond Quantities, Facilities Summaries, and Declarations of Covenant
A Stormwater Facility Summary Sheet is provided as Figure 9-1. In addition, Stormwater Facility
Sketches are provided as Figure 9-2.
Federal Way Public Schools is exempt from typical bonding requirements because it is a public
agency. Because of this, a Bond Quantity Worksheet is not required and has not been prepared.
Because the drainage facilities are to be privately owned and maintained, a Declaration of
Covenant for Inspection and Maintenance of Stormwater Facilities and BMPs is provided as
Figure 9-3.
Technical Information Report
Federal Way High School Pre-Apprenticeship Space
2210134.10
Section 9.0 Figures
Figure 9-1 ......... Stormwater Facility Summary Sheet
Figure 9-2 ......... Stormwater Facility Sketches
Figure 9-3 ......... Declaration of Covenant for Inspection and Maintenance of Stormwater
Facilities and BMPs
2016 KING COUNTY SURFACE WATER DESIGN MANUAL, REFERENCE D
4/24/2016
Page 1
STORMWATER FACILITY SUMMARY SHEET DPER Permit No.___________________
(provide one Stormwater Facility Summary Sheet per Natural Discharge Location)Date ___________________
OVERVIEW:NPDES Permit No.___________________
Project Name
Parcel No.____________________________
Project Location Retired Parcel No.____________________________
Downstream Drainage Basins:Project includes Landscape Management Plan?yes
Major Basin Name ______________________________________________(include copy with TIR as Appendix)no
Immediate Basin Name ______________________________________________
GENERAL FACILITY INFORMATION: Leachable Metals
Infiltration Impervious Surface Limit
Type # of Type # of Type # of facilities Flow Control BMPs
Ponds ______ Ponds ______ Ponds ______ Basic Clearing Limit
Vaults ______ Tanks ______ Vaults ______ Conservation Drainage Facility
Tanks ______ Trenches _____ Tanks ______ Flood Problem Landscape Management Plan
If no flow control facility, check one:
Project qualifies for KCSWDM Exemption (KCSWDM 1.2.3):
Basic Exemption (Applies to Commercial parcels only)Area % of Total
Redevelopment projects
Cost Exemption for Parcel Redevelopment projects
Direct Discharge Exemption
Other _____________________ Total impervious surface served by
Project qualifies for 0.1 cfs Exception per KCSWDM 1.2.3 flow control facility(ies) (sq ft)
Impervious surface served by flow
KCSWDM Adjustment No. ___________________control facility(ies) designed
1990 or later (sq ft)
approved KCSWDM Adjustment No. __________________ Impervious surface served by
Shared Facility Name/Location: _________________________ pervious surface absorption (sq ft)
No flow control required (other, provide justification): Impervious surface served by approved
____________________________________________________ water quality facility(ies) (sq ft)
Flow Control
Performance Std
Declarations of Covenant Recording No.
Water QualityDetention
TREATMENT SUMMARY FOR TOTAL IMPERVIOUS SURFACES
-----
Total Impervious Acreage (ac)
No flow control required per approved
Flow control provided in regional/shared facility per approved
PROVIDE FACILITY DETAILS AND FACILITY SKETCH FOR EACH FACILITY ON REVERSE. USE ADDITIONAL SHEETS AS NEEDED FOR ADDITIONAL FACILITIES
Impervious Surface Exemption for Transportation Total Acreage (ac)
Federal Way High School Pre-Apprenticeship Space
30611 16th Avenue South, Federal Way, WA 98003
2723059014
XLower Puget Sound
X
1 acre of impervious surface capacity in existing pond
Cold Creek
NA
0
0
0
0
0
0
0
0
0 X
TBD
0.17
0.17 100
7405 100
7405 100
0 0
0 0
2016 KING COUNTY SURFACE WATER DESIGN MANUAL, REFERENCE D
4/24/2016
Page 2
STORMWATER FACILITY SUMMARY SHEET DPER Permit No.___________________
(provide one Stormwater Facility Summary Sheet per Natural Discharge Location)
Project Name Downstream Drainage Basins:
Major Basin Name _______________________________
Project Location Immediate Basin Name ___________________________
FLOW CONTROL FACILITY:Basin:
Facility Name/Number _______________________________________ New Facility Project Impervious
Facility Location ____________________________________________ Existing Facility Acres Served ________
UIC? □ yes □ no UIC Site ID:% of Total Project Impervious
cu.ft.Volume Factor Acres Served ________
_____________ ac.ft.____________of Safety _______No. of Lots Served ________
Control Structure location: _______________________________________________
Type of Control Structure:No. of Orifices/Restrictions __________
Riser in vault Size of Orifice/Restriction (in.) No.1 ______ cu.ft.
Riser in Type II CB (numbered starting with lowest No.2 ______ ac.ft.
Weir in Type II CB orifice): No.3 ______
(inches in decimal format)No.4 ______
WATER QUALITY FACILITIES Design Information
Indicate no. of water quality facilities/BMPs for each type:Water Quality design flow (cfs)
_______Flow dispersion Water Quality treated volume (sandfilter) (cu.ft.)
_______Filter strip Water Quality storage volume (wetpool) (cu.ft.)
_______Biofiltration swale regular, wet or Landscape management plan Farm management plan
continuous inflow
_______Wetvault combined w/detention ______High flow bypass structure (e.g., flow-splitter catch basin)
_______Wetpond basic large combined w/detention ______Oil/water separator baffle coalescing plate
_______Pre-settling pond ______Storm filter
_______Stormwater wetland ______Pre-settling structure (Manufacturer:______________________)
_______Sand filter basic large Sand bed depth ______Catch basin inserts (Manufacturer:________________________)
regular linear vault (inches)______________Source controls _________________________________________
● Is facility lined? yes no If so, what marker is used above liner?_____________________________________________________
Facility Summary Sheet Sketch: All detention, infiltration and water quality facilities must include a detailed sketch (11"x17" reduced size plan sheets preferred).
Dam Safety Regulations (WA State Dept of
Ecology):
Reservoir Volume
above natural grade
Depth of Reservoir
above natural grade (ft)
Live Storage
Volume
Live Storage
Depth (ft)
XBIORETENTION (rain garden)
West end of site
X
1
0
0
N/A
N/A
N/A
0.17
100%
Lower Puget Sound
60
X
0.5
Federal Way High School Pre-Apprenticeship Space
30611 16th Avenue South, Federal Way, WA 98003
Cold Creek
NA
0
0
0
0
0
0
0
0
0
0
0
0
0
0
EXISTING FEDERAL
WAY HIGH SCHOOL
EXISTING FEDERAL
WAY HIGH SCHOOL
PROPOSED POLE BARN
FFE = 462.67
EXISTING 12" PVC
STORM PIPE
CONNECT STORM PIPE TO EXISTING WITH INSERTA-TEE.
CONTRACTOR SHALL POTHOLE AND FIELD VERIFY EXISTING
PIPE LOCATION AND INVERT ELEVATION PRIOR TO CONSTRUCTION.
IE: 453.90±
7 LF 6" PVC SDR35 @ 61.0%
CB 01
TYPE 1 WITH LOCKING
HERRINGBONE GRATE
N: 122838.87
E: 1272744.54
RIM: 461.17
IE: 458.17 6" NE
IE: 458.17 6" SW
6.50'
13.50'
RAIN GARDEN WITH
MINIMUM LIVE STORAGE
VOLUME OF 50 CF
CONNECT BUILDING
DOWNSPOUTS
TO RAIN GARDEN WITH
4" PVC SDR35 PIPE
SLOPED AT 0.5% MIN
(TYP)46546446
3
462
462461462462
4614
C4.1
ROOF DRAIN CONNECTION
6" IE: 460.67
ROOF DRAIN CONNECTION
6" IE: 460.67
Sheet No.
Designed by:Drawn by:Checked by:
Sheet Title:
Revisions:
Project Title:
Issue Set & Date:
Client:
Project No.
2215 North 30th Street, Suite 300 Tacoma, WA 98403
T A C O M A SEATTLE SPOKANE TRI-CITIES
253.383.2422 TEL 253.383.2572 FAX www.ahbl.com WEB
FEDERAL WAY HIGH SCHOOL PRE-APPRENTICESHIP SPACE
A PORTION OF THE NE 1/4 OF THE NE 1/4 OF SEC. 08, TWN. 21 N., RGE. 04 E. W.M.
CITY OF FEDERAL WAY, KING COUNTY, WASHINGTON.
FEDERAL WAY HIGH
SCHOOL
PRE-APPRENTICESHIP
SPACE
FEDERAL WAY PUBLIC
SCHOOLS
33330 8TH AVENUE SOUTH
FEDERAL WAY, WA 98003
STEPHEN NUTT
2210134
PERMIT SET
07.12.2021
JAD LDJJAD
9Know what's below.
before you dig.Call
R
CITY ENGINEER
DATE
CITY OF FEDERAL WAY
PERMIT NO.:16-105024-00-CO
8
C4.0
GRAPHIC SCALE
0 10 20
1" = 10 FEET
5
N
STORM DRAINAGE
AND UTILITY PLAN
1.PROOF OF LIABILITY INSURANCE SHALL BE SUBMITTED TO THE CITY PRIOR TO THE
PRECONSTRUCTION MEETING.
2.ALL PIPE AND APPURTENANCES SHALL BE LAID ON A PROPERLY PREPARED FOUNDATION IN
ACCORDANCE WITH WSDOT 7-02.3(1). THIS SHALL INCLUDE LEVELING AND COMPACTING THE
TRENCH BOTTOM, THE TOP OF FOUNDATION MATERIAL, AND REQUIRED PIPE BEDDING, TO A
UNIFORM GRADE SO THAT THE ENTIRE PIPE IS SUPPORTED BY A UNIFORMLY DENSE UNYIELDING
BASE.
3.STEEL PIPE SHALL BE GALVANIZED AND HAVE ASPHALT TREATMENT #1 OR BETTER INSIDE AND
OUTSIDE.
4.ALL DRAINAGE STRUCTURES, SUCH AS CATCH BASINS AND MANHOLES, NOT LOCATED WITHIN A
TRAVELED ROADWAY OR SIDEWALK SHALL HAVE SOLID LOCKING LIDS. ALL DRAINAGE
STRUCTURES ASSOCIATED WITH A PERMANENT RETENTION/DETENTION FACILITY SHALL HAVE
SOLID LOCKING LIDS.
5.ALL CATCH BASIN GRATES SHALL CONFORM TO CFW DRAWING NUMBERS 4-1, 4-2, 4-3, 4-4 OR 4-5.
6.ALL DRIVEWAY CULVERTS LOCATED WITHIN THE RIGHT-OF-WAY SHALL BE OF SUFFICIENT
LENGTH TO PROVIDE A MINIMUM 3:1 SLOPE FROM THE EDGE OF THE DRIVEWAY TO THE BOTTOM
OF THE DITCH. CULVERTS SHALL HAVE BEVELED END SECTIONS TO MATCH THE SIDE SLOPES.
7.ROCK FOR EROSION PROTECTION OF DITCHES, CHANNELS AND SWALES, WHERE REQUIRED,
MUST BE OF SOUND QUARRY ROCK, PLACED TO A DEPTH OF ONE FOOT AND MUST MEET THE
FOLLOWING SPECIFICATIONS: 4"-8" ROCK/40%-70% PASSING; 2"-4" ROCK/30%-40% PASSING; AND
-2" ROCK/10%-20% PASSING. INSTALLATION SHALL BE IN ACCORDANCE WITH KCRS DRAWING
NUMBER 51 OR AS AMENDED BY THE APPROVED PLANS. RECYCLED ASPHALT OR CONCRETE
RUBBLE SHALL NOT BE USED.
8.LOTS NOT APPROVED FOR INFILTRATION SHALL BE PROVIDED WITH DRAINAGE OUTLETS
(STUB-OUTS). STUB-OUTS SHALL CONFORM TO THE FOLLOWING:
A.EACH OUTLET SHALL BE SUITABLY LOCATED AT THE LOWEST ELEVATION ON THE LOT, SO
AS TO SERVICE ALL FUTURE ROOF DOWNSPOUTS AND FOOTING DRAINS, DRIVEWAYS, YARD
DRAINS, AND ANY OTHER SURFACE OR SUBSURFACE DRAINS NECESSARY TO RENDER THE
LOTS SUITABLE FOR THEIR INTENDED USE. EACH OUTLET SHALL HAVE FREE-FLOWING,
POSITIVE DRAINAGE TO AN APPROVED STORMWATER CONVEYANCE SYSTEM OR TO AN
APPROVED OUTFALL LOCATION.
B.OUTLETS ON EACH LOT SHALL BE LOCATED WITH A FIVE-FOOT HIGH, 2 X 4 STAKE MARKED
"STORM". THE STUBOUT SHALL EXTEND ABOVE SURFACE LEVEL, BE VISIBLE AND BE
SECURED TO THE STAKE.
C.PIPE MATERIAL SHALL CONFORM TO UNDERDRAIN SPECIFICATIONS DESCRIBED IN KCRS
7.04 AND, IF NONMETALLIC, THE PIPE SHALL CONTAIN WIRE OR OTHER ACCEPTABLE
DETECTION.
D.DRAINAGE EASEMENTS ARE REQUIRED FOR DRAINAGE SYSTEMS DESIGNED TO CONVEY
FLOWS THROUGH INDIVIDUAL LOTS.
E.THE APPLICANT/CONTRACTOR IS RESPONSIBLE FOR COORDINATING THE LOCATIONS OF
ALL STUB-OUT CONVEYANCE LINES WITH RESPECT TO THE UTILITIES (I.E. POWER, GAS,
TELEPHONE, TELEVISION).
F.ALL INDIVIDUAL STUB-OUTS SHALL BE PRIVATELY OWNED AND MAINTAINED BY THE LOT
HOMEOWNER.
CITY OF FEDERAL WAY DRAINAGE NOTES:
LEGEND
BUILDING OUTLINE
EXISTING MINOR CONTOURS
EXISTING MAJOR CONTOURS
PROPOSED MINOR CONTOUR
PROPOSED MAJOR CONTOUR
CATCH BASIN TYPE 1
DOWNSPOUT CONNECTION
STORM DRAINAGE PIPING
BIORETENTION FACILITY
PERFORATED UNDERDRAIN
ROCK OUTFALL PROTECTION
101
100
1
C4.1
2
C4.1
4
C4.1
3
C4.1
5
C4.1
Sheet No.
Designed by:Drawn by:Checked by:
Sheet Title:
Revisions:
Project Title:
Issue Set & Date:
Client:
Project No.
2215 North 30th Street, Suite 300 Tacoma, WA 98403
T A C O M A SEATTLE SPOKANE TRI-CITIES
253.383.2422 TEL 253.383.2572 FAX www.ahbl.com WEB
FEDERAL WAY HIGH SCHOOL PRE-APPRENTICESHIP SPACE
A PORTION OF THE NE 1/4 OF THE NE 1/4 OF SEC. 08, TWN. 21 N., RGE. 04 E. W.M.
CITY OF FEDERAL WAY, KING COUNTY, WASHINGTON.
FEDERAL WAY HIGH
SCHOOL
PRE-APPRENTICESHIP
SPACE
FEDERAL WAY PUBLIC
SCHOOLS
33330 8TH AVENUE SOUTH
FEDERAL WAY, WA 98003
STEPHEN NUTT
2210134
PERMIT SET
07.12.2021
JAD LDJJAD
9Know what's below.
before you dig.Call
R
CITY ENGINEER
DATE
CITY OF FEDERAL WAY
PERMIT NO.:16-105024-00-CO
9
C4.1
STORM DRAINAGE
DETAILS
POLE BARN STRUCTURE
0.5%
(MIN)
DOWNSPOUT OR RAIN LEADER.
REFER TO ARCHITECTURAL
DRAWINGS.
PROVIDE FITTINGS
AS REQUIRED
PVC CAP. CUT HOLE IN CAP
TO ALLOW DOWNSPOUT / RAIN LEADER
TO PENETRATE WITH 18" CLEARANCE
FINISHED GRADE 2" (MIN)4"±BIORETENTION FACILITY NOTES
1.CONTRACTOR SHALL EXCAVATE TO SUBGRADE OF BIORETENTION FACILITY.
2.PROVIDE BIORETENTION SOIL MIX (BSM) PER REFERENCE 11-C OF THE KING COUNTY SURFACE WATER DESIGN MANUAL.
3.BIORETENTION SOIL MIX (BSM) SHALL NOT BE PLACED UNTIL AFTER SITE PAVING.
4.DO NOT PLACE WHEN SOIL IS SATURATED OR SUBJECT TO WATER WITHIN 48 HRS. COVER ON SITE SOILS TO PREVENT WETTING OR
SATURATION. TEST SOIL FERTILITY AND MICRONUTRIENTS AND, IF NECESSARY, AMEND MIXTURE TO CREATE OPTIMUM CONDITIONS FOR
PLANT ESTABLISHMENT AND EARLY GROWTH AT RATES RECOMMENDED BY AN INDEPENDENT LAB SOIL TEST.
5.SUBGRADE PREPARATION: SCARIFY SUB-SOILS IN TWO DIRECTIONS TO A DEPTH OF 6". THE ENTIRE AREA SHOULD BE DISTURBED BY
SCARIFICATION AND BSM APPLIED TO SCARIFIED SURFACE. NO CONSTRUCTION VEHICLES SHALL DRIVE ON NATIVE SOILS AT INFILTRATION
ELEVATION OR ON BIORETENTION SOILS.
6.DO NOT COMPACT SUBGRADE
7.NO CONSTRUCTION TRAFFIC SHALL BE ALLOWED TO DRIVE WITHIN BIORETENTION FACILITY
8.QUARRY SPALLS ARE TO BE PER WSDOT SPEC. 9-13.1(5). THICKNESS SHALL BE 8" MINIMUM AND AREA SHALL BE APPROXIMATELY 10 SF AT
EACH INLET.
9.THE BIORETENTION FACILITY HAS BEEN SIZED TO TREAT 1,152 SF (REFER TO CALCULATIONS INCLUDED IN SECTION 2 OF THE TIR).
10.SEE LANDSCAPING PLAN FOR PLANTING DETAILS
3:1 M
A
X
BIORETENTION SOIL MIX
PER REFERENCE 11-C
OF THE KCSWDM 18" MINTOP WIDTH: 14.5
461.17
UNDISTURBED
NATIVE SOIIL
SEE
GRADING
SHEET
SEE
GRADING
SHEET
BOTTOM WIDTH: 8.5'
6" FREEBOARD
FRAME AND VANED GRATE
RECTANGULAR ADJUSTMENT SECTION
3"4" MI
N. (
T
Y
P.)
34"
5"
#3 BAR EACH WAY
SEE NOTE 1
#3 BAR EACH
CORNER
#3 BAR EACH
CORNER
18" MIN.
26"(SEE
N
O
T
E
6)
22
"
(S
E
E
N
O
T
E
6
)4"44"21" MIN.24"
30
"
20"
5"
6" OR 12"
ONE #3 BAR HOOP
FOR 6" HEIGHT
TWO #3 BAR HOOPS
FOR 12" HEIGHT
ALTERNATIVE PRECAST BASE SECTION
#3 BAR EACH SIDE
SECTION B-B
#3 BAR
HOOP
*CORRUGATED POLYETHYLENE STORM SEWER PIPE
NOTE:
1.AS ACCEPTABLE ALTERNATIVES TO THE REBAR SHOWN IN THE PRECAST BASE SECTION,
FIBERS (PLACED ACCORDING TO THE STANDARD SPECIFICATIONS), OR WIRE MESH HAVING A
MINIMUM AREA OF 0.12 SQUARE INCHES PER FOOT SHALL BE USED WITH THE MINIMUM
REQUIRED REBAR SHOWN IN THE ALTERNATIVE PRECAST BASE SECTION. WIRE MESH SHALL
NOT BE PLACED IN THE KNOCKOUTS.
2.THE KNOCKOUT DIAMETER SHALL NOT BE GREATER THAN 20". KNOCKOUTS SHALL HAVE A
WALL THICKNESS OF 2" MINIMUM TO 2.5" MAXIMUM. PROVIDE A 1.5" MINIMUM GAP BETWEEN
THE KNOCKOUT WALL AND THE OUTSIDE OF THE PIPE. AFTER THE PIPE IS INSTALLED, FILL
THE GAP WITH JOINT MORTAR IN ACCORDANCE WITH STANDARD SPECIFICATION 9-04.3.
3.THE MAXIMUM DEPTH FROM THE FINISHED GRADE TO THE LOWEST PIPE INVERT SHALL BE 5'.
4.THE FRAME AND GRATE MAY BE INSTALLED WITH THE FLANGE UP OR DOWN. THE FRAME MAY
BE CAST INTO THE ADJUSTMENT SECTION.
5.THE PRECAST BASE SECTION MAY HAVE A ROUNDED FLOOR, AND THE WALLS MAY BE SLOPED
AT A RATE OF 1:24 OR STEEPER.
6.THE OPENING SHALL BE MEASURED AT THE TOP OF THE PRECAST BASE SECTION.
7.ALL PICKUP HOLES SHALL BE GROUTED FULL AFTER THE BASIN HAS BEEN PLACED.
PIPE ALLOWANCES
PIPE MATERIAL
MAXIMUM
INSIDE
DIAMETER
REINFORCED OR PLAIN CONCRETE 12"
ALL METAL PIPE 15"
*CPSSP (STD. SPEC. 9-05.20)12"
SOLID WALL PVC (STD. SPEC. 9-05.12(1))15"
PROFILE WALL PVC (STD. SPEC. 9-05.12(2))15"
NOTES:
1.BACKFILL MATERIAL SHALL NOT HAVE ROCKS OR PARTICLES LARGER THAN 1" WITHIN 12" OF
THE PIPE. BACKFILL MATERIAL SHALL BE PLACED IN 8" MAXIMUM LOOSE LIFTS AND
COMPACTED TO 95% MAXIMUM DRY DENSITY PER MODIFIED PROCTOR TEST (ASTM D-1557).
2.CONSTRUCT ALL STORM AND ROOF DRAINS IN CONFORMANCE WITH THIS DETAIL UNLESS
NOTED OTHERWISE ON THE PLANS.
3.ALL TRENCH EXCAVATIONS SHALL BE SLOPED, SHORED, SHEETED, BRACED, OR OTHERWISE
SUPPORTED IN COMPLIANCE WITH OSHA REGULATIONS AND LOCAL ORDINANCES.
4.IF ORGANIC MATERIAL IS ENCOUNTERED DURING UTILITY EXCAVATION, OVEREXCAVATE
TRENCH TO INCREASE PIPE BEDDING DEPTH TO 18" OR MORE AS REQUIRED TO COMPACT
BEDDING TO FIRM AND UNYIELDING CONDITION.
BACKFILL WITH BANK RUN
GRAVEL FOR TRENCH BACKFILL
PER WSDOT 9-03.19 OR
SUITABLE NATIVE MATERIAL
0.15 x DIA OR 4" MIN
PAVEMENT, BASE COURSE AND
SUBBASE PER PAVING SHEETS
8" TYP
RIGID
(DI, CONC)
FLEXIBLE
(CPEP, CMP, PVC)
PIPE AS SPECIFIED
ON PLAN OR SPECS
1.5 x I.D. + 18"
24" MIN
PIPE BEDDING PER
WSDOT 9-03.12, (3)6"DIA6" MIN
1 NOT TO SCALE
CATCH BASIN TYPE 1
2 NOT TO SCALE
TRENCH SECTION
4 NOT TO SCALE
BIORETENTION FACILITY
3 NOT TO SCALE
DOWNSPOUT CONNECTION
BOTTOM ELEV: 460.67
6" PONDING DEPTH
TOP OF POND ELEV: 461.67
OVERFLOW RIM ELEV: 461.17
OUTLET PROTECTION PER PLAN
INLET PIPE
PER PLAN
6"Ø PERFORATED PVC
SDR35 SLOPED AT 0.5% MIN.
18" MIN.
6" MIN
UNDERDRAIN BEDDING PER WSDOT 9-03.12(4),
GRAVEL BACKFILL FOR DRAINS.
INLET P
I
P
E
INLET/OUTFALL PIPE
OUTFALL
P
I
P
E
*8'
2'DIA. + 4'PLAN
SECTION
* UNLESS OTHERWISE
NOTED ON PLANS
EXISTING AND/OR
FINISHED GROUND
4" MIN. FACE
QUARRY ROCK
12" MIN. DEPTH (12"Ø PIPE)
18" MIN. DEPTH (15"-18"Ø PIPE)
24" MIN. ( 24"-30"Ø PIPE)
5 NOT TO SCALE
ROCK OUTFALL PROTECTION
RECORDING REQUESTED BY AND
WHEN RECORDED MAIL TO:
DECLARATION OF COVENANT
FOR MAINTENANCE AND INSPECTION OF FLOW CONTROL BMPS
Grantor:
Grantee: King County
Legal Description:
Additional Legal(s) on:
Assessor's Tax Parcel ID#:
IN CONSIDERATION of the approved King County (check one of the following) residential
building permit, commercial building permit, clearing and grading permit, subdivision permit, or
short subdivision permit for Application No. ____________________ relating to the real property
("Property") described above, the Grantor(s), the owner(s) in fee of that Property, hereby
covenants(covenant) with King County, a political subdivision of the state of Washington, and its
municipal successors in interest and assigns ("King County" and "the County", or "its municipal
successor"), that he/she(they) will observe, consent to, and abide by the conditions and obligations set
forth and described in Paragraphs 1 through 8 below with regard to the Property. Grantor(s) hereby
grants(grant), covenants(covenant), and agrees(agree) as follows:
1
Federal Way High School Pre-Apprenticeship Space
NE 1/4 OF NE 1/4 OF SEC 8-21-4 LESS CO RDS TGW POR OF NW 1/4 OF NW 1/4
.
N/A
0821049001
x
NW 1/4 OF SEC 9-21-4 LY WLY OF 16TH AVE S & OF PACIFIC HWY S TGW POR OF VAC 16TH AVE S
LESS RD (ROW DEDICATION PER CITY OF FEDERAL WAY REC #20190329000115 & #20190329000116)
.
1. Grantor(s) or his/her(their) successors in interest and assigns ("Owners") shall retain, uphold,
and protect the stormwater management devices, features, pathways, limits, and restrictions, known as
flow control best management practices ("BMPs"), shown on the approved Flow Control BMP Site Plan
for the Property attached hereto and incorporated herein as Exhibit A.
2. The Owners shall at their own cost, operate, maintain, and keep in good repair, the Property's
BMPs as described in the approved Design and Maintenance Details for each BMP attached hereto and
incorporated herein as Exhibit B.
3. King County shall provide at least 30 days written notice to the Owners that entry on the
Property is planned for the inspection of the BMPs. After the 30 days, the Owners shall allow King
County to enter for the sole purpose of inspecting the BMPs. In lieu of inspection by the County, the
Owners may elect to engage a licensed civil engineer registered in the state of Washington who has
expertise in drainage to inspect the BMPs and provide a written report describing their condition. If the
engineer option is chosen, the Owners shall provide written notice to the Director of the Water and Land
Resources Division or its municipal successor in interest ("WLR") within fifteen days of receiving the
County's notice of inspection. Within 30 days of giving this notice, the Owners, or the engineer on
behalf of the Owners, shall provide the engineer's report to WLR. If the report is not provided in a timely
manner as specified above, the County may inspect the BMPs without further notice.
4. If King County determines from its inspection, or from an engineer's report provided in
accordance with Paragraph 3, that maintenance, repair, restoration, and/or mitigation work is required for
the BMPs, WLR shall notify the Owners of the specific maintenance, repair, restoration, and/or
mitigation work (Work) required under Title 9 of the King County Code ("KCC"). WLR shall also set a
reasonable deadline for completing the Work or providing an engineer's report that verifies completion of
the Work. After the deadline has passed, the Owners shall allow the County access to re-inspect the
BMPs unless an engineer's report has been provided verifying completion of the Work. If the work is not
2
completed properly within the time frame set by WLR, King County may initiate an enforcement action.
Failure to properly maintain the BMPs is a violation of KCC Chapter 9.04 and may subject the Owners to
enforcement under the KCC, including fines and penalties.
5. Apart from performing routine landscape maintenance, the Owners are hereby required to
obtain written approval from WLR before performing any alterations or modifications to the BMPs.
6. Any notice or approval required to be given by one party to the other under the provisions of
this Declaration of Covenant shall be effective upon personal delivery to the other party, or after three (3)
days from the date that the notice or approval is mailed with delivery confirmation to the current address
on record with each Party. The parties shall notify each other of any change to their addresses.
7. This Declaration of Covenant is intended to promote the efficient and effective management
of surface water drainage on the Property, and it shall inure to the benefit of all the citizens of King
County and its municipal successors and assigns. This Declaration of Covenant shall run with the land
and be binding upon Grantor(s), and Grantor's(s') successors in interest and assigns.
8. This Declaration of Covenant may be terminated by execution of a written agreement by the
Owners and King County that is recorded by King County in its real property records.
3
IN WITNESS WHEREOF, this Declaration of Covenant for the Maintenance and Inspection of
Flow Control BMPs is executed this _____ day of ____________________, 20_____.
GRANTOR, owner of the Property
GRANTOR, owner of the Property
STATE OF WASHINGTON ) COUNTY OF KING )ss.
On this day personally appeared before me:
, to me known to be the individual(s) described in
and who executed the within and foregoing instrument and acknowledged that they signed the same as
their free and voluntary act and deed, for the uses and purposes therein stated.
Given under my hand and official seal this _____ day of ____________________, 20_____.
Printed name
Notary Public in and for the State of Washington,
residing at
My appointment expires
4
Technical Information Report
Federal Way High School Pre-Apprenticeship Space
2210134.10
Section 10
Operations and Maintenance Plan
Technical Information Report
Federal Way High School Pre-Apprenticeship Space 10-1
2210134.10
10.0 Operations and Maintenance Plan
The drainage facilities detailed in this report will be privately owned and maintained.
Facility Descriptions
10.1.1 Bioretention BMP
This project proposes a bioretention facility, which will provide flow control for stormwater, if
maintained properly. To function as intended, the bioretention facility must be clear of trash and
debris and contain healthy, water tolerant plants. The facility should be inspected annually and
after large storms to ensure that it is functioning properly.
10.1.2 Conveyance Pipes and Ditches
Pipes transport stormwater runoff from the roof to the proposed bioretention facility. To work
properly, pipes must be kept free of silt and other debris. If pipes become blocked, surface
flooding could occur.
Maintenance Requirements
Refer to Figure 10-1 for a copy of the Maintenance Requirements for Flow Control, Conveyance,
and Water Quality Facilities.
Technical Information Report
Federal Way High School Pre-Apprenticeship Space
2210134.10
Section 10.0 Figures
Figure 10-1 ....... Maintenance Requirements for Flow Control, Conveyance, and Water
Quality Facilities
APPENDIX A MAINTENANCE REQUIREMENTS FOR FLOW CONTROL, CONVEYANCE, AND WQ FACILITIES
NO. 6 – CONVEYANCE PIPES AND DITCHES
Maintenance
Component
Defect or Problem Conditions When Maintenance is Needed Results Expected When
Maintenance is Performed
Pipes Sediment & debris
accumulation
Accumulated sediment or debris that exceeds
20% of the diameter of the pipe.
Water flows freely through pipes.
Vegetation/roots Vegetation/roots that reduce free movement of
water through pipes.
Water flows freely through pipes.
Contaminants and
pollution
Any evidence of contaminants or pollution such
as oil, gasoline, concrete slurries or paint.
Materials removed and disposed of
according to applicable regulations.
Source control BMPs implemented if
appropriate. No contaminants
present other than a surface oil film.
Damage to protective
coating or corrosion
Protective coating is damaged; rust or corrosion
is weakening the structural integrity of any part of
pipe.
Pipe repaired or replaced.
Damaged Any dent that decreases the cross section area
of pipe by more than 20% or is determined to
have weakened structural integrity of the pipe.
Pipe repaired or replaced.
Ditches Trash and debris Trash and debris exceeds 1 cubic foot per 1,000
square feet of ditch and slopes.
Trash and debris cleared from
ditches.
Sediment
accumulation
Accumulated sediment that exceeds 20% of the
design depth.
Ditch cleaned/flushed of all
sediment and debris so that it
matches design.
Noxious weeds Any noxious or nuisance vegetation which may
constitute a hazard to County personnel or the
public.
Noxious and nuisance vegetation
removed according to applicable
regulations. No danger of noxious
vegetation where County personnel
or the public might normally be.
Contaminants and
pollution
Any evidence of contaminants or pollution such
as oil, gasoline, concrete slurries or paint.
Materials removed and disposed of
according to applicable regulations.
Source control BMPs implemented if
appropriate. No contaminants
present other than a surface oil film.
Vegetation Vegetation that reduces free movement of water
through ditches.
Water flows freely through ditches.
Erosion damage to
slopes
Any erosion observed on a ditch slope. Slopes are not eroding.
Rock lining out of
place or missing (If
Applicable)
One layer or less of rock exists above native soil
area 5 square feet or more, any exposed native
soil.
Replace rocks to design standards.
2016 Surface Water Design Manual – Appendix A 4/24/2016
A-11
APPENDIX A MAINTENANCE REQUIREMENTS FLOW CONTROL, CONVEYANCE, AND WQ FACILITIES
NO. 11 – GROUNDS (LANDSCAPING)
Maintenance
Component
Defect or Problem Conditions When Maintenance is Needed Results Expected When
Maintenance is Performed
Site Trash or litter Any trash and debris which exceed 1 cubic foot
per 1,000 square feet (this is about equal to the
amount of trash it would take to fill up one
standard size office garbage can). In general,
there should be no visual evidence of dumping.
Trash and debris cleared from site.
Noxious weeds Any noxious or nuisance vegetation which may
constitute a hazard to County personnel or the
public.
Noxious and nuisance vegetation
removed according to applicable
regulations. No danger of noxious
vegetation where County personnel
or the public might normally be.
Contaminants and
pollution
Any evidence of contaminants or pollution such
as oil, gasoline, concrete slurries or paint.
Materials removed and disposed of
according to applicable regulations.
Source control BMPs implemented if
appropriate. No contaminants
present other than a surface oil film.
Grass/groundcover Grass or groundcover exceeds 18 inches in
height.
Grass or groundcover mowed to a
height no greater than 6 inches.
Trees and Shrubs Hazard Any tree or limb of a tree identified as having a
potential to fall and cause property damage or
threaten human life. A hazard tree identified by
a qualified arborist must be removed as soon
as possible.
No hazard trees in facility.
Damaged Limbs or parts of trees or shrubs that are split or
broken which affect more than 25% of the total
foliage of the tree or shrub.
Trees and shrubs with less than 5%
of total foliage with split or broken
limbs.
Trees or shrubs that have been blown down or
knocked over.
No blown down vegetation or
knocked over vegetation. Trees or
shrubs free of injury.
Trees or shrubs which are not adequately
supported or are leaning over, causing exposure
of the roots.
Tree or shrub in place and
adequately supported; dead or
diseased trees removed.
4/24/2016 2016 Surface Water Design Manual – Appendix A
A-16
Technical Information Report
Federal Way High School Pre-Apprenticeship Space
2210134.10
Section 11
Conclusion
Technical Information Report
Federal Way High School Pre-Apprenticeship Space 11-1
2210134.10
11.0 Conclusion
The Federal Way High School Pre-Apprenticeship Space site was designed to meet the 2016
King County Surface Water Design Manual (KCSWDM), as adopted by the City Federal Way per
the Addendum to the King County Surface Water Manual (Addendum), January 8, 2017. The site
incorporates conveyance and bioretention facilities to manage stormwater generated from the
site. Stormwater calculations and modeling conform to King County standards.
It was determined using these criteria that:
• The bioretention facility was sized properly.
• Pipe networks are designed to be of adequate size to effectively convey the 25-year storm
event and to contain the 100-year storm event.
This analysis is based on data and records either supplied to or obtained by AHBL. These documents
are referenced within the text of the analysis. The analysis was prepared using procedures and practices
within the standard accepted practices of the industry. We conclude that this project, as schematically
represented, will not create any new problems within the downstream drainage system. This project will
not noticeably aggravate any existing downstream problems due to either water quality or quantity.
AHBL, Inc.
James A. Daley, EIT
Project Engineer
JAD/lsk
July 2021
Q:\2021\2210134\WORDPROC\Reports\20210708 Rpt (TIR) 2210134.10.docx