_Twin Trails HX Preliminary Plat 5-3-2023 DEPARTMENT OF COMMUNITY DEVELOPMENT STAFF REPORT TO THE FEDERAL WAY HEARING EXAMINER Twin Trails Preliminary Plat File 21-104105-00-SU (Related File 21-104106 00-SE) PUBLIC HEARING May 3, 2023 2:00 p.m. Federal Way City Hall City Council Chambers 33325 8th Avenue South Report prepared by: Natalie Kamieniecki, Associate Planner TABLE OF CONTENTS I. GENERAL INFORMATION ................................................................................1 II. CONSULTED DEPARTMENTS AND AGENCIES ....................................................2 III. STATE ENVIRONMENTAL POLICY ACT..............................................................2 IV. NATURAL CHARACTERISTICS ..........................................................................3 V. GENERAL DESIGN .........................................................................................3 VI. TRANSPORTATION .........................................................................................4 VII. PUBLIC SERVICES .........................................................................................5 VIII. UTILITIES ......................................................................................................5 IX. ANALYSIS OF DECISIONAL CRITERIA ...............................................................6 X. FINDINGS OF FACT AND CONCLUSIONS ...........................................................8 XI. RECOMMENDATIONS ................................................................................... 10 LIST OF EXHIBITS ........................................................................................ 11 Twin Trails Preliminary Plat 21-104105-00-SU Hearing Examiner Staff Report Page 1 of 11 I. GENERAL INFORMATION Applicant: Prospect Development – Justin Holland 2913 5th Avenue NE, Ste 201 Puyallup, WA 98372 Agent: ESM Consulting Engineers, LLC 33400 8th Ave S, Suite 201 Federal Way, WA 98003 John.Everett@esmcivil.com Action Requested: The applicant is requesting preliminary plat approval of a 38-lot subdivision of two parcels totaling 9.28-acres, pursuant to Federal Way Revised Code (FWRC) Title 18, “Subdivisions” (FWRC Chapter 18.35, “Preliminary Plat”). Staff Representative: Natalie Kamieniecki, Associate Planner Natalie.kamieniecki@cityoffederalway.com 253-835-2638 A. Description of Proposal Subdivide King County Parcel No’s 242103-9051 and 242103-9008, totaling 9.28- acres into 38 single-family residential lots. Minimum lot size of 7,200 square feet. The project includes landscape, open space, street improvements, storm drainage facilities, and utility improvements. Property is zoned RS-7.2 B. Legal Description Parcel # 242103-9008: LOT “2” OF FEDERAL WAY BLA#21-104109-su REC #20220914900001 SD BLA LOC IN SE ¼ OF NE ¼ STR 24-21-03 Parcel # 244103-9051: S 412 1/3 FT OF N 824 1/3 FT OF SE ¼ OF NE ¼ C. Zoning and Comprehensive Plan Designations, and Existing Uses Zoning/Comprehensive Plan Designation and Density – The subject property is zoned Single Family Residential (RS 7.2) and has a comprehensive plan designation of Single-Family Residential High Density. Lots in the RS 7.2 zone must meet the minimum lot size of 7,200 square feet. As shown on the preliminary site plan, (Exhibit A), all lots in the plat meet or exceed the underlying code-required minimum lot size of 15,000 square feet. Twin Trails Preliminary Plat 21-104105-00-SU Hearing Examiner Staff Report Page 2 of 11 Direction Zoning Comprehensive Plan Existing Land Use Site Single Family Residential (RS 7.2) Single Family, High Density Parcel # 242103- 9008: Vacant Parcel # 244103- 9051: Single-Family Dwelling North Single Family Residential (RS 7.2) Single Family, High Density Single Family Dwellings and vacant Single- Family Residential lots South Single Family Residential (RS15.0) Single Family, Medium Density Single Family Dwellings and vacant Single- Family Residential lot East Single Family Residential (RS15.0) Single Family, Medium Density Vacant Land West Single Family Residential (RS 7.2) Single Family, Medium Density King County Transit Park and Ride Lot II. CONSULTED DEPARTMENTS AND AGENCIES The following departments, agencies, and individuals were advised of this application: A. The Community Development Review Committee (CDRC) consisting of the City of Federal Way Department of Community Development Planning and Building Divisions; Public Works, Parks, and Police Departments; South King Fire & Rescue; Lakehaven Water & Sewer District; and Federal Way School District. CDRC comments have been incorporated into this report where applicable. B. All owners of real property located within 300 feet of site boundaries were mailed notices of application and public hearing. The site was posted and notice was published in the Federal Way Mirror and on the city’s website. C. In accordance with the State Environmental Policy Act (SEPA) and the FWRC Title 14, “Environmental Protection,” all property owners within 300 feet of all site boundaries, and all affected agencies, were notified of the proposed action and the city’s environmental decision. In addition, the site was posted and notice was published in the Federal Way Mirror and on the city’s website. III. STATE ENVIRONMENTAL POLICY ACT (SEPA) The City of Federal Way issued an Environmental Determination of Nonsignificance (DNS) for the proposed action on March 3, 2023. This determination was based on review of information in the project file, including the environmental checklist (Exhibit C). resulting in the conclusion that the proposal would not result in probable significant Twin Trails Preliminary Plat 21-104105-00-SU Hearing Examiner Staff Report Page 3 of 11 adverse impacts on the environment. The DNS was published in Federal Way Mirror on March 3, 2023. The comment period for the DNS concluded on March 17, 2023. No public or agency comment was received. The SEPA appeal period ended on March 24, 2023, with no appeals to the city’s environmental decision. IV. NATURAL ENVIRONMENT Environmentally Critical Areas A. Geotechnical: Preliminary Geotechnical Engineering Study for Twin Trails Preliminary Plat, prepared by Earth Solutions NW, LLC, dated August 23, 2021; updated September 13, 2021 (Exhibit E) provides a site analysis of the soils, topography and construction recommendations. The report conforms the absence of landslide and erosion geologic hazards. B. Wetland / Fish and Wildlife: A Wetland and Fish and Wildlife Assessment Report, prepared by Sound View Consultants, LLC, dated September 28, 2021 and revised April 14, 2023. (Exhibit F). The report identifies three (3) off site wetlands. Wetland 1 is located approximately 150 feet offsite to the east of the subject property at its closest point and is approximately 1.56 acres in size. Per FWRC 19.145.420(1), Wetland 1 is a Category III depressional wetland. Wetland 2 is located approximately 210 feet offsite to the east of the subject property at its closest point and is approximately 0.26 acres in size. Per FWRC 19.145.420(1), Wetland 2 is a Category III depressional wetland. Wetland 3 is located approximately 280 feet offsite to the east of the subject property at its closest point and is approximately 880 square feet (0.02 acre) in size. Per FWRC 19.145.420(1), Wetland 3 is a Category IV depressional wetland. No other wetlands, waterbodies, or priority habitats and species were identified on or within 225 feet of the subject property. Wetlands 1 and 2 are classified as Category III wetlands. Per FWRC 19.145.420(2), Category III wetlands require a standard 80-foot buffer width. Wetland 3 is classified as a Category IV wetland. Per FWRC 19.145.420(2), Category IV wetlands typically require a standard 50-foot buffer width; however, due to the small size of Wetland 3 (less than 1,000 square feet) and the units’ isolated nature, no buffer is required per FWRC 19.145.420(3). V. GENERAL DESIGN A. Subdivision Design - The Twin Trails proposed preliminary plat is a single-family residential subdivision with public right-of-way dedications and improvements, landscaping, and associated infrastructure. The proposed all meet the minimum lot size of 7,200 square feet and are rectangular-shaped. Per FWRC 19.200.010, each lot must provide a minimum front yard structural setback of 20 feet, a side and rear yard structural setback of five feet. Side yard setbacks for corner lots are increased to 10 feet for those yards adjacent to rights-of-way that are not considered the property’s primary vehicular access. Setbacks for flag lots are depicted under the Twin Trails Preliminary Plat 21-104105-00-SU Hearing Examiner Staff Report Page 4 of 11 definition of “property line,” FWRC 19.05.160, P definitions. For the purposes of preliminary plat review, the building setback lines (BSBL) are depicted on the preliminary plat map, and each lot contains an adequate building area as required under the FWRC to accommodate setbacks. B. Landscaping / Tree Retention - The applicant has proposed to clear and grade the entire site at the time of construction of the plat infrastructure. The proposed grading plan would include clearing areas for roadways, a storm drainage facility, utilities and the individual lots. Replacement trees to be planted on the individual lots at time of single-family building permit application. A plat note will be affixed to the final plat regarding planting of replacement trees on the individual lots at time of single-family building permit. Pursuant to FWRC 18.60.030 (1), land divisions should provide a 10-foot-wide type III landscape strip along all arterial street. The site fronts SW 341st ST along the northern property line and is considered a local access road, and to the south SW 344th ST which is a principal collector. Type III land scape buffer is not required. C. Parks & Open Space –The proposed plat will provide fee-in-lieu of open space and meets the open space minimum requirements in FWRC 18.55.060, for the purposes of preliminary plat review. VI. TRANSPORTATION A. Concurrency (FWRC 19.90) – The applicant is required to undergo traffic concurrency analysis pursuant to the state Growth Management Act; goals and policies of the Federal Way Comprehensive Plan; and FWRC Chapter 19.90, “Transportation Concurrency Management.” The proposed development will result in 36 new peak hour trips. The city’s Traffic Division has reviewed the concurrency application and has issued an approved Capacity Reserve Certificate dated December 7, 2022 (Exhibit I). B. Impact Fee (FWRC 19.91) – The applicant will be subject to the city’s transportation impact fee. The fee will be calculated based on the fee rate in effect at the time a complete building permit application is submitted and must be paid prior to building permit issuance. C. Public Improvements – The plat infrastructure improvements include new public internal roadways, existing public right-of-way improvements, associated utilities, and landscaping. The new internal roadways will be constructed to a Type W standard section. The new 19th Ave SW extension to SW 344th Street will be construction to a Type ‘S’ standard section. Additionally, half street improvements will be provided along the adjacent existing rights-of way. This includes the south half of SW 341st Pl to complete a Type ‘S’ road section, the east half of 19th Ave SW along to complete a Type ‘S’ road section, and the north half of SW 344th St to a Type ‘K’ road section. In addition, internal circulation provides four (4) private access tracts to accommodate a limited number of lots. Twin Trails Preliminary Plat 21-104105-00-SU Hearing Examiner Staff Report Page 5 of 11 VII. PUBLIC SERVICES A. Police and Fire Services - Police services are provided by and will continue to be provided by the City of Federal Way Police Department. Fire, emergency and medical response is provided by South King Fire and Rescue. B. Schools – The proposed subdivision is located within two Federal Way School District’s School Boundary Maps. The applicant provided a school access analysis with the preliminary plat application (Exhibit J). High school students from this development will receive bus transportation to and from either Decatur or Todd Beamer High School, as these schools are over one mile from the subject site. Students attending Illahee Middle School would be bussed to school. Students attending TAF at Saghalie will be able to walk or bike to school. Students attending Olympic View Elementary would be bussed to school and students attending Sherwood Forest Elementary would be able to walk or bike to school. The proposed development will provide for additional safe waking conditions including sidewalks and lighting required through half street improvements and new internal public roadways. School impact fees, as authorized by city ordinance, provide mitigation for the students of this development. School impact fees are determined on the basis of the district’s Capital Facilities Plan and are subject to annual adjustment and update and are due at the time of the building permit issuance for the new dwelling units. C. Fire Protection - Existing fire hydrants are located in close proximity to the subject property; specifically, at about 120 feet north of the intersection of SW 341 ST and 19th Ave SW and near the southwest corner of the property close to the terminus of SW 344th ST. Additional fire hydrants and the specific locations of new hydrants will be determined during engineering review. Fire sprinklers are required for Lots 25, 26, and 27 due to limited access and no turnaround. The remainder of the lots will be determined for fire sprinklers upon building plans submittal. VIII. UTILITIES A. Sewage Disposal – The applicant proposes to serve the proposed plat by a public sewer system managed by the Lakehaven Water & Sewer District. A September 13, 2021, Certificate of Sewer Availability (Exhibit H) indicates the district’s capacity to serve the proposed development through a Developer Extension Agreement (DEA). B. Water Supply – The applicant proposes to serve the subdivision with a public water supply and distribution system managed by the Lakehaven Water & Sewer District. The September 13, 2021, Water Availability Letter (Exhibit G) indicates Lakehaven’s capacity to serve the proposed development through a Developer Extension Agreement (DEA). Twin Trails Preliminary Plat 21-104105-00-SU Hearing Examiner Staff Report Page 6 of 11 C. Drainage Facilities - Development of the site will create additional runoff from new impervious surfaces such as streets, driveways, sidewalks and rooftops. Storm drainage facilities are being designed in accordance with the 2021 KCSWDM and the city’s amendments to the manual. The applicant’s preliminary Technical Information Report (Exhibit D), provides analysis of proposed stormwater facilities for the subject property. Conservation Flow Control Area and Enhanced Basic Water Quality Area designations. Final approval of the storm drainage that are shown on the conceptual clearing and grading and utility plan and detailed in the TIR, will require Public Works Department engineering review. Stormwater design and plat drainage elements must conform to the standards, policies, and practices of the City of Federal Way’s Surface Water Management Division as outlined in the 2021 KCSWDM and city amendments, the Comprehensive Surface Water Management Plan, and the Stormwater System Operation and Maintenance Manual. The approved storm drainage facilities must be constructed per city code requirements, prior to final plat approval and recording of the subdivision. A Surface and Stormwater Utility System Development Charge is required. System development Charges (SDCs) are one-time fees that will be paid at the time of development and are intended to recover a share of the cost of the system capacity needed to serve growth. IX. ANALYSIS OF DECISIONAL CRITERIA The FWRC establishes review procedures and decisional criteria for deciding upon various types of land use applications. Pursuant to FWRC Chapter 18.35, preliminary plat applications are submitted to the Hearing Examiner for public hearing and final decision on the preliminary plat. Hearing Examiner Preliminary Plat Decisional Criteria – Pursuant to FWRC 18.35.170, the Hearing Examiner may recommend approval of the proposed preliminary plat only if the following decisional criteria are met. Decisional criteria and staff responses are provided below. A. The project is consistent with the Federal Way Comprehensive Plan. Staff Comment: The application is subject to the adopted Federal Way Comprehensive Plan (FWCP), which designates the property as Single-Family, High Density. The proposed land use, Single-Family Residential, with 7,200 square-foot minimum lot size is consistent with density allowances and policies applicable to this land use as established in the FWCP. As proposed, the project is consistent with FWCP Chapter 2 – Land Use; LUG 3 – Preserve and protect Federal Way’s single- family neighborhoods and LUP 13 – Maintain and protect the character of existing single-family neighborhoods through strict enforcements of the City’s land use regulations. Twin Trails Preliminary Plat 21-104105-00-SU Hearing Examiner Staff Report Page 7 of 11 B. The project is consistent with all applicable provisions of the Federal Way Revised Code, including those adopted by reference. Staff Comment: The preliminary plat application is required to comply with the applicable provisions of FWRC Title 14, “Environmental Policy”; Title 16 “Surface and Stormwater Management”; Title 18, “Subdivisions”; Title 19, “Zoning”; and all other applicable codes and regulations. Future development of the residential subdivision will be required to comply with all applicable development codes and regulations. As proposed, and with conditions as recommended by staff, the preliminary plat will comply with all provisions of the chapter. C. The project is consistent with the public health, safety, and welfare. Staff Comment: The proposed preliminary plat will permit development of the site consistent with the current single-family land use classification of the FWCP and map. New roadways and sidewalks will increase pedestrian safety and promote multimodal transportation. Proposed access and fire hydrant locations must meet all requirements of South King Fire & Rescue. Future development of the plat in accordance with applicable codes and regulations will ensure protection of the public health, safety, and welfare. D. It is consistent with the design criteria listed in FWRC 18.05.020; and. Staff Comment: The proposed preliminary plat will promote the purposes identified in FWRC 18.05.020, and the standards and regulations therein, as identified in the staff report, including effective use of land; promotion of safe and convenient travel on streets; provision for the housing needs of the community; protection of environmentally sensitive areas; fee in lieu option for open space and replacement trees planted on individual lots satisfying tree unit density requirement. As proposed, and with conditions as recommended by city staff, the preliminary plat application complies with all provisions of the chapter. E. It is consistent with the development standards listed in Chapter 18.55 FWRC, and FWRC 18.60.030 through 18.60.120. Staff Comment: Staff reviewed the preliminary plat and associated plans and it is consistent with the above listed codes. The proposed preliminary plat is consistent with density of the RS 7.2 zone and can accommodate bulk regulations and setbacks contained in FWRC 19.200.010. Impacts to the road network are adequately mitigated as described in Section IV of this report. Lakehaven Water and Sewer District has capacity to service the site utilities. Stormwater facilities are proposed in accordance with the 2021 KCSFM as described in section VIII of this report. In addition, development of this site is required to comply with the provisions of FWRC Title 18, “Subdivisions”; Title 14, “Environmental Policy”; Title 19, “Zoning and Development Code”; and all other applicable local and state development codes and regulations. As proposed, and as recommended by city staff, the preliminary plat application complies with all applicable statutes, codes, and regulations. Twin Trails Preliminary Plat 21-104105-00-SU Hearing Examiner Staff Report Page 8 of 11 X. FINDINGS OF FACT AND CONCLUSIONS Based on an analysis of the proposed action, the environmental record, and related decisional criteria, the Department of Community Development finds that: 1. The proposal is to subdivide a vacant 9.28-acre parcel into 38 single-family residential lots, with associated roadway, stormwater, landscaping and utility improvements. The subject property is zoned RS7.2, and the preliminary plat application was deemed complete on November 24, 2021. 2. The proposed single-family residential plat is permissible in the RS zoning districts under FWRC 19.200.010. Subdivisions of 10 lots or more are subject to review under FWRC Chapter 18.35 “Preliminary Plat.” The 38 proposed lots meet or exceed the underlying required minimum lot size of 7,200 square feet. 3. Notice of application was published in accordance with FWRC 18.35.090 on December 3, 2023. No comments were received. 4. An Environmental Determination of Nonsignificance (DNS) was issued for this proposed action on March 3, 2023, with a comment period ending March 17, 2023 and appeal period expiring March 24, 2023. No comments or appeals of the environmental determination were filed with the city. 5. Notice of Hearing was published in accordance with FWRC19.35.100 on April 14, 2023. 6. The applicant has proposed to clear and grade the entire site at the time of construction of the infrastructure. The proposed grading plan would include clearing areas for roadways, a storm drainage facility, utilities and the individual lots. Replacement trees to be planted on the individual lots at time of single-family building permit application. 7. Open space requirement to be provided through the fee-in-lieu option (Exhibit K). The fee-in-lieu of onsite open space will be 15 percent of the most recent assessed value of the property, minus any onsite open space areas, and due at final plat approval. The applicant must provide a voluntary agreement letter authorizing the city to use the open space fee-in-lieu in any of the Parks Planning Areas the city per FWRC 18.55.060(2). 8. The City Traffic Engineer conducted a concurrency test to determine if the new trips generated by the subdivision would result in failures to the city’s level of service. The test concluded that 36 new PM peak hour trips will be generated with no failures and a Certificate of Reserve Capacity was issued on December 7, 2022 (Exhibit I). 9. The site is bounded by 341st St SW to the north and 344th St SW along the south property boarders. Extension of 19th Ave SW will connect SW 341st ST to SW 344th ST Individual vehicular access points to the lots will be provided via individual driveway access from new internal public right of way and private access tracts. Twin Trails Preliminary Plat 21-104105-00-SU Hearing Examiner Staff Report Page 9 of 11 10. Required half street improvements are designed in accordance with Federal Way Comprehensive Plan roadway cross sections. The plat infrastructure improvements include new public internal roadways, existing public right-of-way improvements, associated utilities, and landscaping. The new internal roadways will be constructed to a Type W standard section. The new 19th Ave SW extension to SW 344th Street will be construction to a Type ‘S’ standard section. Additionally, half street improvements will be provided along the adjacent existing rights-of way. This includes the south half of SW 341st Pl to complete a Type ‘S’ road section, the east half of 19th Ave SW along to complete a Type ‘S’ road section, and the north half of SW 344th St to a Type ‘K’ road section. In addition, internal circulation provides four (4) private access tracts to accommodate a limited number of lots. 11. The applicant is subject to the city’s transportation impact fee (TIF) that will be assessed and collected by the applicant when the building permit is issued for each lot, using the fee schedule then in effect. 12. The applicant provided a school access analysis (Exhibit J) that demonstrate safe walking and bus routes serving the proposed subdivision. 13. Development of the site will create additional runoff from new impervious surfaces such as streets, driveways, sidewalks and rooftops. Storm drainage facilities are being designed in accordance with the 2021 KCSWDM and the city’s amendments to the manual. The applicant’s preliminary Technical Information Report (TIR) (Exhibit D), provides analysis of needed stormwater facilities for the subject property. Final approval of the storm drainage facilities, as shown on the clearing grading and utility plan and detailed in the TIR, will occur following Public Works Department engineering review. The storm drainage facilities must be constructed per city code requirements, prior to final plat approval and recording of the subdivision. 14. The preliminary plat was reviewed and determined to be consistent with all preliminary plat decision criteria set forth in FWRC 18.35.70(3)(a) through (e), including consistency with the comprehensive plan; consistency with all applicable provisions of the chapter, including those adopted by reference from the comprehensive plan; consistency with the public health, safety, and welfare; consistency with the design criteria listed in FWRC 18.05.020; and consistency with the development standards in FWRC Chapter 18.55, and FWRC 18.60.030 through 18.60.120. 15. The preliminary plat application was reviewed for consistency with all applicable state and local codes, policies and regulations, including the Federal Way Comprehensive Plan (FWCP); Federal Way City Code (FWRC) Title 14, “Environmental Policy”; Title 16, “Surface Water Management”; Tile 18, “Subdivisions”; Title 19, “Zoning and Development Code”; Chapter 19.145, “Environmentally Critical Areas”; Chapter 19.135, “Development Improvements”; and the 2021 King County Surface Water Design Manual. As proposed and recommended by staff, the preliminary plat is consistent with the FWCP and all other applicable codes and regulations. 16. As required by RCW 58.17.110, the preliminary plat makes appropriate provisions for the public health, safety, and general welfare and for such open spaces, drainage Twin Trails Preliminary Plat 21-104105-00-SU Hearing Examiner Staff Report Page 10 of 11 ways, streets or roads, alleys, other public ways, transit stops, potable water supplies, sanitary wastes, parks and recreation, playgrounds, schools and schoolgrounds and all other relevant facts, including sidewalks and other planning features that assure safe walking conditions for students who only walk to and from school; and the public use and interest will be served by the platting of such subdivision and dedication. 17. Water and sewer facilities are available from the Lakehaven Water & Sewer District and are adequate to serve the proposed development. It is the applicant’s responsibility to secure all necessary water and sewer services from the utility provider. 18. South King Fire & Rescue will require additional fire hydrants. Specific location of new hydrants will be determined during engineering review. Fire sprinklers are required for Lots 25, 26 and 27 due to limited access and no turnaround. The remainder of the lots will be determined for fire sprinklers upon building plans submittal. 19. As proposed and recommended by staff, approval and development of the proposed preliminary plat will ensure consistency and compatibility with existing surrounding single-family residential uses and densities. XI. RECOMMENDATION Based on review of this application, the DNS and pertinent decisional criteria, the Department of Community Development recommends approval of the preliminary plat subject to the following conditions: 1. The following notes are to be affixed to the final plat: “At time of building permit, each individual lot will be responsible for providing replacement trees in accordance with FWRC 19.120.130 (2) and FWRC 19.120.150.” “Open space tracts shall be owned in undivided interest among the owners of the lots within the Twin Trails Subdivision.” 2. Pursuant to the FWRC 18.40.050, prior to final plat approval and recording, all required and approved improvements will be constructed, or the improvements appropriately bonded, per city code requirements. 3. The open space tract shall be owned in common undivided interest by all property owners within the land division as members of a homeowners’ association or corporation as set out in a declaration of covenants and restrictions, and approved by the city prior to recording of the final plat. Twin Trails Preliminary Plat 21-104105-00-SU Hearing Examiner Staff Report Page 11 of 11 ___________________________ LIST OF EXHIBITS* A: Preliminary Plat Plan Set, dated 11-21-22 B: Notice of Application, dated 12-3-23 C: Environmental Determination of Nonsignificance, date 3-3-23 D: Preliminary TIR & Downstream Analysis, dated revised 11-17-23 E. Geotechnical Engineering Study and Addendum, dated 8-23-21 F. Wetland and Fish and Wildlife Assessment, dated 4-16-23 G. Certificate of Water Availability, Date H. Certificate of Sewer Availability, Date I. Capacity Reserve Certificate, dated 12-7-22 J. Safe Walking to School Route, dated 10-6-21 K. Open Space Fee in Lieu Request, dated 10-6-21 L. South King Fire & Rescue, email dated 11-14-22 M. Waste Management, email dated 8-15-22 Transmitted to the parties listed hereafter: Federal Way Hearing Examiner Phil Olbrechts olbrechtslaw@gmail.com Prospect Development – Justin Holland 2913 5th Avenue NE, Ste 201 Puyallup, WA 98372 justin@prospectdevelop.com ESM Consulting Engineers, LLC – John Everett 33400 8th Ave S, Suite 201 Federal Way, WA 98003 John.Everett@esmcivil.com