Project Name: PETERSON
Project Address: 28805 5TH AVE S
Project Description: IBLUEBEAM - 4 kW solar panel installation on roof.
Electrical
Permit #:23-102532-00-EL
Inspection Request Line: (253) 835-3050
Parcel Number: 515298 0090
Owner
Applicant
Contractor
RICHARD PETERSON
BRS PERMITTING
B R S FIELD OPS LLC
28805 5TH AVE S
1403 N RESEARCH WAY
BRSFIFO820N3 (8/23/24)
FEDERAL WAY WA 98003
OREM UT 84097
1403 N RESEARCH WAY
OREM UT 84097
Additional Permit Information
Is this an Online or O.T.C. application? .................. No
Electrical Fixtures
Alt. Serv./Feeder: 0 to 200 aml
CONDITIONS:
FIRE APPROVAL CONDITIONS:
Upon completion of installation, the following photographs shall be emailed to
planreview@southkingfire.org and alarms@southkingfire.org
- Finished installation showing 36" access from the ground and 18" clearance at roof peak.
- Location of shutoff switch with signage.
- Photo of the front of the house showing the address or street side view.
Email the photographs at least 2 business days before requesting electrical final.
Due to size limitations, save photos on a single page and save as a .pdf before sending.
You will receive a response back from SKFR once the permit has been approved by SKFR so you can
schedule your electrical final inspection.
If no response from SKFR within 2 business days, call 253-946-7348 to check status.
PERMIT EXPIRES Tuesday, 21 November, 2023
Permit Issued on Thursday, May 25, 2023
I hereby certify that the above information is correct and that the construction on the above described property
and the occupancy and the use will be in accordance with the laws, rules and regulations of the State of
Wa Cityof Federal Way.
FlUe
1 REPRINTED /
Owner or agent: Date:
� JUN - 7 2073
CITY of - --
Federal Way
THIS C.1RD IS TO RE11_JI\ O\-SITE
Construction Inspection Record
INSPECTION REQLTSTS: (253) 335-3050
Scheduled inspections may- be failed if this crud is not ou-site. DON OT LOSE THIS CARD. Inspections are listed as close to sequential order as possible
(read left to right. top to bottom). Please schedule inspections as appropriate. Work nitrst not be covered until it is approved. Check with Motu inspector if
you are unsure about any of the inspections or the inspection sequence. On -going inspections are logged on -the back of this card.
ELECTRICAL
0
L"FER Ground (4295)
❑
Ditch cover (4030)
E]
Slab/Concrete Floor (4255)
Approved
Approved
Approved to place concrete
By
Date
By
Date
By
Date
❑
Pool Bonding (4195)
❑
Temporary Power (4275)
❑
Service (4235)
Approved
Approved
Approved
By
Date
By
Date
By
Date
❑
Feeders/Sub-panels (4045)
❑
Rough Electrical (4225)
❑
Ceiling Cover (4020)
Approved
Approved
Approved
By
Date
By
Date
By
Date
F' al - Electrical (4055)
By
- ppra;rd
Date (Q
MECHANICAL
0
Mechanical Rough -in (4165)
❑
Gas Piping (4125)
❑
Final -Mechanical (4065)
Approved
Approved to release test
Approved
By
Date
Bv
Date
By
Date
PLUMBING
'❑
Plumbing Groundwork (4190)
0
Rough Plumbing (4230)
❑
Final - Plumbing (4075)
Approved to cover
Approved
Approved
By
Date
By
Date
13Y