Loading...
19-101014Contech Engineered Solutions LLC CV41 NTECH ii8i5NEGlenn ,OR9g Portland, OR 7z202o ENGINEERED SOLUTIONS RESUBMI www.ContechES.com November 13, 2019 Kassandra N. Zohn, E.I.T. Development Engineering, PLLC 821 Dock Street, Suite 207 Tacoma, WA 98402 DEC 0 2 2019 M.M UNrTD FEDERAL Wqy CO EVELOP'ME;NT Re: Filterra System Review — Northlake Court Project Dear Ms. Zohn: Contech Engineered Solutions, LLC has reviewed the plans prepared by Development Engineering, PLLC dated 11/17/17 for the Northlake Court Project. Based on the information provided for review, it appears that the Filterra system designed for the project meet the following criteria required as part of the GULD: 1. The 6x8 Filterra Peak Diversion system appears to have been designed according to the appropriate treatment flow rate and hydraulic conductivity of 70.92 in/hr allowed under the GULD. 2. The Peak Diversion configuration provides treatment and high flow bypass in one unit. The system appears to be specified to include all other components of the Filterra system including impermeable walls, media at proper depth, mulch layer, and approved plants; the system appears to be constructible; and the location of the Filterra on the site appears to allow adequate maintenance access. As a result, the Filters is expected to operate in accordance with the design intent as well as the Filterra GULD. Please note that Contech has not reviewed the WWHM model or hydraulics of the collection system upstream or downstream of the Filtena system for accuracy. We are pleased to work with you on this project and look forward to our continued interactions throughout the planning and installation process. Please do not hesitate to call if you have any questions or require more information. Sincerely, Renna Esmabe, E.I.T Stormwater Designer Contech Engineered Solutions, LLC 503-258-3189 1 REsmabe@conteches.com thl CITY OF Federal way Centered on opportunity July 2, 2019 Malkit Singh 37332 19th Place S Federal Way, WA 98003 CITY HALL 33325 8th Avenue South Federal Way, WA 98003-6325 (253) 835-7000 www.cityoffederalway.com Jim Ferrell, Mayor RE: Permit #19-101014-00-EN; Northlake Court Short Plat, Engineering Plan Review Dear Mr. Singh: The Public Works and Planning Department have reviewed the engineering plans submitted for the referenced project. Prior to our approval, the following items shall be addressed: Sheets C-1 through C-8, and C-10: 1) Add the City Approval Block, including the expiration note, to the lower right-hand corner of these sheets, and include the city Permit Number (noted above) in the space provided in the approval block. Sheet C-1: 1) Provide a vertical benchmark with elevation, including the description, location and datum. 2) The street trees are shown to be within the separate landscape tract — the trees shall be in the planter strip between the sidewalk and curb. There also needs to be trees shown along Military Road, north of the plat road. 3) The plat road will need to be in a separate tract. City policy is that storm water ponds/facilities within short plats are to be owned and maintained by the plat owners. Since the stormwater pond will be private, and a majority of the stormwater into the pond is coming from the plat road, the plat road will also need to be a private road in a separate tract. 4) Revise the right of way dedication line to cross the plat access road. Sheet C-2: 1) No Public Works comments at this time. Sheet C-3: 1) No Public Works comments at this time. \CFW-HLE I \Applications\CS DC\PROD\docs\save\ 156611 _79301 _18113154.DOC Sheet C-4: 1) Include the Wet Season Special Provisions notes from Appendix D of the 2016 King County Surface Water Design Manual (KCSWDM). 2) A Construction Storm Water Permit is required to be obtained from the State Department of Ecology (DOE). Provide a copy of the Construction Storm Water Pollution Prevention Plan (CSWPPP) to the City. 3) While it appears that the project may be exempt from having to provide a temporary sediment trap or pond, due to the direction of slope and proximity to the neighboring properties, a temporary sediment trap is recommended. The trap should be located away from the infiltration pond location. At a minimum, a sediment trap should be sized and shown on the plans, with a note that the trap shall be constructed if weather, time of year, and/or duration of construction activities, warrant it's installation. Sheet C-5: 1) No Public Works comments at this time. Sheet C-6: 1) Provide a vertical scale for the profile view. 2) Show and identify, on the plan view, the existing edge stripe and edge of pavement line. 3) Indicate that the curb return radiuses are 35-feet. 4) Provide a %-street cross-section for Military Road. The section should show all existing and proposed improvements, with dimensions, and include the pavement saw -cut line location. (Refer to redline plan). 5) Provide flow -line elevations (with STA/OFFSET) at the locations highlighted on the plan sheet. 6) Provide STA/OFFSET's for the locations shown on the plan sheet. 7) Show the existing ramp and asphalt transition that's located at the end of improvements constructed for the Northlake Rim plat, and indicate that it shall be removed, and replaced with sidewalk, and to match existing. 8) The curb and gutter at the south end of improvements should not have an angle point/taper. 9) Provide an enlarged detail of the proposed ramp/transition at the south end of improvments. 10) Indicate that the ramps at Military and plat entrance are to be per City standard detail 3-4, and include and reference the detail in the plan set. 11) Locate and show the existing overhead utility poles and down -guys that are along, and just south of, the property frontage. Add a note that the existing overhead utilities along the frontage are to be relocated underground. ,CFW FILE I' Applications`CSDC, PROD'docs'saveI 156611 79301 _ 18113154. DOC 12) Locate and show the existing fire hydrant along the frontage. 13) Refer to comments, above, regarding street trees. 14) It appears that some portion of Military Road, north of the plat road, might drain into the plat road and therefore enter the infiltration pond. Was the pond sized to take this runoff? Would it be beneficial to add a CB to the north of the plat road, and connect it to the CB near Military and S 330th Place? Sheet C-7: 1) Provide a vertical scale for the profile view. 2) Indicate what elevations are being given at the bottom of the profile view — are these existing/proposed centerline, or flow line, or something else? 3) Indicate the type of catch basin (CB) for CB's #1, 3, and 4. 4) Additional CB's are required at the end of the cul-de-sac. Refer to the 2016 King County Road Standards, page 7-4, item `K'. 5) Indicate the slope for the pipe between CB's #3 and 4. 6) It's not very clear how the Filterra unit can be installed as shown - It appears that the plant well will be located in the gutter line. 7) Provide the curb radiuses for the curbs entering the cul-de-sac. 8) A stop sign, street name/number sign, and private road sign are required at the intersection with Military Road. Include City standard details (enclosed). 9) Will individual lot driveway approaches be constructed as part of the roadway improvements? If so, please show them, and reference and include City standard detail drawing 3-6. If not, then a note should be added that indicates that the final lift of asphalt roadway will be installed only after all driveway approaches have been constructed. Additionally, the owner will be required to provide a bond that covers the estimated cost of the final lift. 10) Provide horizontal curve data for the road centerline. 11) Per the 2016 King County Surface Water Design Manual (KCSWDM), Section 5.2, page 5-50, a pre -settling facility is required upstream of the infiltration pond, that has the capacity of 0.25 times the basic water quality design volume. 12) An access road is required to the pond inlet structure, with the first 20-feet paved. 13) Add a second pond section that's cut 90 degrees to Section AA, but also include the inlet pipe and CB 1. 14) Add a rip -rap pad at the pond inlet, and provide a detail. • CFWFILEI Applications CSDOPROD'dots,save,156611_79301_I8113154.DOC Sheet C-8: 1) Refer to the comment above, regarding the Filterra unit. Sheet C-9: 1) No Public Works comments at this time. Sheet C-10: 1) Use the most current (2019, enclosed) City standard street section detail drawings. Highlight on detail 3-2K, the `Minor' arterial pavement section. 2) Add other City standard details to this sheet (or on additional sheets as necessary), as requested in comments above. Other: 1) The Technical Information Report (TIR) indicates the pond side slopes are 4:1, yet the plans indicate 3:1. Please either revise the plans or revise the pond analysis using 3:1 side slopes. 2) We will need a letter or other confirmation from Contech, indicating that they have reviewed and concur with the water quality facility design and layout. 3) A street lighting plan that meets the City standards, is required to be submitted to the City for review and approval, and will need to be a part of the final engineering approval. Please submit a street lighting plan, including City standard details. Details and a street light plan checklist are enclosed. 4) Bonding is required for all street frontage improvements along Military Road, as well as all on-, and off -site TESC measures. Please complete the enclosed Bond Quantities Worksheet with your next submittal. 5) The owner will need to complete and return either the enclosed Performance/Maintenance Bond or Assignment of Funds in Lieu of Bond information sheets, so that City staff can develop the bond documents. Planning Department comments (Leila Willoughby -Oakes, Associate Planner, 253-835-2644, leila.willoughby-oakes@cityoffederalway.com): 1. Please submit a preliminary landscaping plan Military Road South in a separate tract(s). T: evergreen and deciduous trees with large shn protection measures) and removal plans. depicting 10 feet of Type III landscaping along pe III landscaping is composed of a mixture of )s and ground cover, include tree retention (tree 2. The applicant to receive Forest Practices approval prior to clearing and grading activities. \CF W FILE I' Applications' CSDC` PROD'docs�save,15661 1 _79301 _ 131 13154. DOC 3. Provide information on any proposed grade changes that might adversely affect or endanger trees on the property and/or adjacent properties, and specifications to maintain them pursuant to FWRC 19.120.140. 4. Post site development work - contact the project planner for final short plat requirements in order to record. Submit an updated title report, recent within 30 days. Please revise the plans as necessary, and submit 3 copies of the revisions, along with all other requested information. If you have any questions on the Planning Department comments, please contact the project planner listed above. Questions regarding all other comments should be directed to the undersigned at (253) 835-2734, or kevin.peterson@,cityoffederatwU.com. Sincerely, Kevin Peterson Sr. Engineering Plans Reviewer KP:ss Enc: Redline plans City Standard details 3-2K, 3-2W, 3-2Z, 3-3, 3-4, 3-11, 3-38, 3-39, 3-39a, 3-39B, 3-40, 3-41, 3-45, 3-49, 3-50, 3-51, 3- 54, Street light review checklist, Bond Quantities Worksheet, Performance/Maintenance Bond Information Sheet, Assignment of funds in Lieu of Bond Information sheet c: Leila Willoughby -Oakes, Associate Planner Project file (kp) Day file `CFW FI LE I `,ApplicationvCSD0 PROD' dots, save, 15661 1 _79301 _ 1 S 1 13154. DOC CITY OF � Federal October 22, 2019 Malkit Singh 37332 19th Place S Federal Way, WA 98003 Way CITY HALL 33325 8th Avenue South Federal Way, WA 98003-6325 (253) 835-7000 www. cityoffederalway. com Jim Ferrell, Mayor RE: Permit #19-101014-00-EN; Northlake Court Short Plat, Engineering Plan Review Dear Mr. Singh: The Public Works and Planning Department have reviewed the revised engineering plans submitted on August 9th for the referenced project. Prior to our approval, the following items shall be addressed: Some of the following comments are repeated from our July 2, 2019 letter. The original comment(s) are in italic font. New and/or additional comments/questions are in standard font: Sheet C-6: 1) Revise the sidewalk configuration at the north end of the Military Road frontage improvements. There's an existing down -guy that falls within the new sidewalk. 2) It appears that some portion of Military Road, north of the plat road, might drain into the plat road and therefore enter the infiltration pond. Was the pond sized to take this runoff? Please provide a response. Sheet C-7: 1) It's still not clear how the Filterra unit will be capable of treating the storm water that's collected in CB's #3 and #4, given that the profile shows both the inlet and outlet pipes at the same invert elevation, and the detail does not seem to have the option of accepting a pipe as an inlet into the vault at an elevation that allows water to filter through the treatment media. 2) The vault is also located in the `wing' of the pond access driveway — it needs to be located outside of any portion of the driveway. 3) Revise the callout for the Filterra vault — it's currently called out as a Type 1 CB. 4) Provide additional horizontal curve data for the road centerline: PC (STA), PT (STA), Length, and DELTA angle. Other: The following comments are repeated from our July 2, 2019 letter. The original comment(s) are in italic font, with additional comments in standard font: 1) We will need a letter or other confirmation from Contech, indicating that they have reviewed and concur with the water quality facility design and layout. Please submit this at your earliest convenience. 2) A street lighting plan that meets the City standards, is required to be submitted to the City for review and approval, and will need to be a part of the final engineering approval. Please submit a street lighting plan, including City standard details. Details and a street light plan checklist are enclosed. A complete street lighting plan, that meets City standards, shall be prepared by an engineering firm that is qualified to prepare such plans. Please submit these plans at your earliest convenience. 3) Bonding is required for all street frontage improvements along Military Road, as well as all on-, and off -site TESC measures. Please complete the enclosed Bond Quantities Worksheet with your next submittal. This information was not provided with the last submittal. Please submit this at your earliest convenience. 4) The owner will need to complete and return either the enclosed Performance/Maintenance Bond or Assignment of Funds in Lieu of Bond information sheets, so that City staff can develop the bond documents. This information was not provided with the last submittal. Please submit this at your earliest convenience. Planning Department comments (Leila Willoughby -Oakes, Associate Planner, 253-835-2644, leila.willoughby-oakes@cityoffederalway.com): 1. Please submit a preliminary landscaping plan depicting 10 feet of Type III landscaping along Military Road South in a separate tract(s). Type III landscaping is composed of a mixture of evergreen and deciduous trees with large shrubs and ground cover, include tree retention (tree protection measures) and removal plans. This information was not provided with the last submittal. Please submit this at your earliest convenience. 2. The applicant to receive Forest Practices approval prior to clearing and grading activities. Please revise the plans as necessary, and submit 3 copies of the revisions, along with all other requested information. If you have any questions on the Planning Department comments, please contact the project planner listed above. Questions regarding all other comments should be directed to the undersigned at (253) 835-2734, or kevin.peterson@cityoffederalway.com. Sincerely, Vex m_ Kevin Peterson Sr. Engineering Plans Reviewer KP:ss Enc: Redline plans c: Leila Willoughby -Oakes, Associate Planner Project file (kp) Day file i DLv ELOPMENT ENGINEM, �G, PLLC August 6, 2019 Malkit Singh 37332 —19th Place South Federal Way, Washington 98003 2306 A Street Tacoma, Washington 98402 (253) 228-0513 www.de-civil.com Response Letter —City Comments Proposed Short Plat Military Road South Federal Way, Washington PN:1521049081 Job: 17-236 Military Plat.RL3 This letter provides our responses to comments received from the City of Federal Way dated July 2, 2019 for the Northlake Court plat. Public Works —Sheets C-1 throw h C-8 and C-10 1. City approval block added to all plan sheets. Public Works — Sheet C-1 1. Vertical benchmark and datum added. Street trees moved to be in the planter strip between sidewalk and curb (sheet C-2). Plat road now referred to as "tract D". 4. Proposed ROW designation now crosses the plat access road. Public Works — Sheet C-2 1. No comments to address. Public Works — Sheet C-3 1. No comments to address. Public Works — Sheet CA 1. Wet season special provision notes added (sheet C-11). 2. Noted that CSWPPP is required to be submitted to the city prior to receiving a construction stormwater permit. 3. Sediment trap depicted and sizing provided should it be necessary. Public Works — Sheet C-5 1. No comments to address. Public Works — Sheet C-6 1. Vertical scale added. 2. Existing edge of pavement added to plan view. 3. Curb radius (35 feet) added to both sides of driveway approach. 4. Half street cross section for Military road added (sheet C-10). 5. Flowline elevations added at all eight points indicated on redlined plans. See plan view and ramp details on sheet C-6. 6. Stations and offsets added at all eight points indicated on redlined plans. See plan view and ramp details on sheet C-6. 17-236 Military Plat.RL3 November 27, 2018 Page 2 7. Notes added at beginning and end of asphalt ramp improvements to match existing. 8. Angle point/taper removed, curb and gutter continues along same alignment. 9. Two ramp details added to show additional details and proposed ramps per city standard. 10. City of Federal Way standard detail drawing 3-4 added to plan sheet C-12. 11. Overhead utilities and guy poles depicted. 12. Existing fire hydrant added, see sheet C-9. 13. Fire hydrant and trees depicted on sheet C-9. Public Works - Sheet C-7 1. Vertical scale added. 2. Note added for which elevations are existing and which are proposed finished grade. 3. Type of catch basin added (all type 1). 4. Catch basin analysis to be provided by Contech. 5. Pipe slope between catch basins 3 and 4 added on plan view (sheet C-7). 6. Additional details for Contech Filterra system added. The system itself is a catch basin that has the option to have an additional line piped in for treatment. We will be piping in the upstream catch basins into this unit. Contech has several aesthetic options for their Filterra systems, some with trees or shrubs, and some with grasses located under the grate. 7. Additional curve radiuses added. 8. Stop sign callout and street sign/private road sign on sheet C-6. Both items depicted on sheet C- 7 without callout. 9. Driveway approaches will not be constructed at this time. Note added regarding final lift of asphalt roadway to be installed after driveway approaches have been constructed. Noted that owner will be required to prepare a bond for final lift. 10. Curve data added for road centerline. 11. The Contech Filterra system provides enhanced basic water quality treatment, thus meeting the requirement for presettling. 12. Access road added, note that first 20 feet must be paved. 13. Existing profile on sheet C-7 extended to include the entirety of the infiltration pond. No new profile has been added. 14. Rip rap pad and detail added. See sheet C-XX for rip rap detail. Public Works - Sheet C-8 1. Additional details for Contech Filterra system added. The system itself is a catch basin that has the option to have an additional line piped in for treatment. We will be piping in the upstream catch basins into this unit. Contech has several aesthetic options for their Filterra systems, some with trees or shrubs, and some with grasses located under the grate. Public Works - Sheet C-9 1. No comments to address. Public Works -Sheet C-10 1. Detail 3-2K added on sheet C-10 and titled Military Way Road section. 2. Details added to sheet set. Public Works - Other Comments 1. Plans revised to be 4:1 side slopes. 2. Letter from Contech provided; at time of submittal Contech has received plans for review to ensure system has adequate capacity. T � 17-236 Military Plat.RL3 November 27, 2018 Page 3 3. Lighting plan is now on sheet C-9. 4. Bond quantities worksheet completed and provided with submittal. 5. Owner has completed performance/maintenance bond information sheets. Planning — Other Comments 1. Landscaping plan completed and submitted by others. 2. Noted that applicant to receive forest practices approval prior to clearing and grading may commence. 3. No proposed grade changes are anticipated to adversely impactor endanger trees onsite or on neighboring properties. 4. Noted to contact project planner for final short plat requirements in order to record. We trust this is sufficient for your current needs. Should you have any questions, or require additional information, please contact us at your earliest convenience. Respectfully submitted, Development Engineering, PLLC Glen Coad, PE Owner KNZ Doc ID:17-236 Military Plat.RL3 DE -CIVIL, PLLC RESUBMITTED DEC 0 4 2018 Revised: November 28, 2018 March 2, 2018 Malkit Singh '31232-7� ' INTRODUCTION CfTY OF FEDERAL WAY COMMUNITY DEVELOPMENT Geotechnical Report Proposed Short Plat Military Road South Federal Way, Washington P N : 152104-9081 Job: 17-236 Military Plat.GR P.O. Box 446 Tacoma, WA 98401 (253) 228-0513 www.de-civil.com This report presents the results of our geotechnical investigation and engineering recommendations for the proposed short plat to be located on Military Road South in the city of Federal Way, Washington. We understand that you intend to short plat the property into 6 individual lots. Part of the site improvements will include the creation of the new lots, road improvements, stormwater infrastructure and general utility infrastructure. The general location of the site is shown on the attached Site Vicinity Map, Figure 1. Our understanding of the project is based on our discussions with you, and our November 22, 2017 site visit. We understand that you are in the process of subdividing the property for the purpose of constructing new residential building(s) on the additional lots. We further understand that the buildings will be constructed utilizing conventional wood framing and spread concrete footings. Clearing and grading is expected to be limited to that required to maintain access to the site. SCOPE The purpose of our services is to evaluate the surface and subsurface conditions at the site as a basis for assessing potential adverse impacts to and from the adjacent steeply sloped areas of the site. Specifically, our scope of services for the project included the following: 1. Reviewing the available geologic, hydrogeologic and geotechnical data for the site area. 2. Addressing the appropriate geotechnical regulatory requirements for the proposed site development. Subsurface explorations were completed as part of this assessment. SITE CONDITIONS Surface Conditions The subject site is located on Military Road South in the city of Federal Way, Washington. The site is irregular in shape, encompassing approximately 2.06 acres of area. The site is currently undeveloped and is well vegetated with trees. The site generally slopes down from southwest to northeast at slopes of 5 to 10 percent. Total topographic relief across the parcel is approximately 25 feet. The property is bounded by a residential neighborhood to the north and east, by a wooded residential property to the south, and by Military Road South to the west. 17-236 Military Plat.GR March 2, 2018 Page 2 Site Soils The USDA Natural Resource Conservation Service Web Soil Survey for King County mapped the soils in the area as Alderwood gravelly sandy loam (AgB, AgC), which derives from glacial drift outwash on slopes of 0 to 15 percent. These soils are known to have a "very low to moderately low" capacity to transmit water. Site Geology The Geologic Map of the Poverty Bay 7.5' Quadrangle, King and Pierce Counties, Washington, by Booth, Waldron, and Troost maps the site as being underlain by till (Qvt). Usually consisting of massive silt- or sand -rich matrices, till is deposited by glacial outwash. An excerpt of the above referenced map is included as Figure 4. Based on our site observations, the near surface soils area inconsistent with the mapped soils. Geologic Hazard Areas- per City of Federal Way Chapter 19.145 Article II The city of Federal Way defines "Geographically hazardous" areas as areas susceptible to erosion, land sliding, seismic, or geological events. Section 19.145.220 restricts development on or within 50 feet of a geologically hazardous area. The width of prescriptive setbacks from these hazardous areas is dependent upon the characteristics of the critical area. There are no geologically hazardous areas mapped on or near the property. There are no erosion hazards mapped on the site. The site is mapped as Alderwood, with slopes of no more than 20 percent. These soils are known to have a "slight" erosion hazard. Subsurface Explorations As mentioned on October 3, 2017 we were on site and observed the excavation a total of 6 test pits in the area of the proposed development. The test pits were excavated by a track mounted excavator operated by a licensed earthwork contractor. The test pits extended to maximum depth of approximately 10 feet below existing ground surface. The test pits were located in the field by our representative by pacing from existing site features such as property corners and adjacent roadways and fences. The approximate location of the test pits are indicated on the attached Site Plan Figure 2. A geotechnical engineer from our office continuously monitored the excavations, maintained logs of the subsurface conditions encountered in each test pit, obtained representative soil samples, and observed pertinent site features. Representative soil samples obtained from the test pits were placed in sealed plastic bags and taken to our laboratory for further examination and testing, as deemed appropriate. Based on our experience in the area and extent of our explorations in the area it is our opinion that the soils encountered in the test pits are generally representative of the soils at the site. Subsurface Conditions Our test pits encountered consistent subsurface conditions that somewhat contradicted the geological mapping stratigraphy. The stratigraphy across the site as observed in our test pits consisted of 1 foot of topsoil overlying loose to dense medium sand and gravel. We interpret the native surficial soils to be inconsistent with the soils mapped by USDA. The soils encountered were visually classified in accordance with the Unified Soil Classification System (USCS) described on Figure 5. The test pit logs are included as Figures 6. Groundwater Conditions During our October 3, 2017 explorations, no groundwater seepage was observed. Perched groundwater typically develops when the vertical infiltration of precipitation through a more permeable soil is slowed at depth by a deeper, less permeable soil type. Since no impermeable soil was encountered, we expect 17-236 Military Plat.GR March 2, 2018 Page 3 that perched groundwater sill not be present on the site. Fluctuations in the local groundwater levels will occur in response to precipitation patterns, off -site construction activities, and site utilization. CONCLUSIONS Based on our site evaluation, it is our opinion that the construction of the proposed building can be safely carried out without significant risk. Site Preparation Areas to be graded should be cleared of deleterious matter including any existing structures, foundations, abandoned utility lines, debris and vegetation. The portions of the site covered with vegetation should be stripped of any forest duff and organic -laden soils, based on our test pits, stripping depths of 1 to 2 feet should be anticipated. These materials can be stockpiled and later used for erosion control. Material that cannot be utilized on the site should be removed from the site. Where placement of fill material is required, the stripped/exposed subgrade areas should be compacted to a firm and unyielding surface prior to placement of any fill. Excavations for debris removal should be backfilled with structural fill compacted to the densities described in the "Structural Fill" section of this report. We recommend that a member of our staff evaluate the exposed subgrade conditions after removal of vegetation and topsoil stripping is completed and prior to placement of structural fill. The exposed subgrade soil should be proof -rolled with heavy rubber -tired equipment during dry weather or probed with a 1/2-inch-diameter steel rod during wet weather conditions. Any soft, loose, or otherwise unsuitable areas delineated during proof -rolling or probing should be recompacted, if practical, or over -excavated and replaced with structural fill, based on the recommendations of our site representative. The areas of old fill material should be evaluated during grading operations to determine if they need mitigation; recompaction or removal. Structural Fill All material placed as fill associated with mass grading, as utility trench backfill, under building areas, or under asphalt pavement should be placed as structural fill. The structural fill should be placed in horizontal lifts of appropriate thickness to allow adequate and uniform compaction of each lift. Fill should be compacted to at least 95 percent of MDD (maximum dry density as determined in accordance with ASTM D-1557). The appropriate lift thickness will depend on the fill characteristics and compaction equipment used. We recommend that the appropriate lift thickness be evaluated by our field representative during construction. The suitability of material for use as structural fill will depend on the gradation and moisture content of the soil. As the amount of fines (material passing US No. 200 sieve) increases, soil becomes increasingly sensitive to small changes in moisture content and adequate compaction becomes more difficult to achieve. During wet weather, we recommend use of well -graded sand and gravel with less than 5 percent (by weight) passing the US No. 200 sieve based on that fraction passing the 3/4-inch sieve, such as Gravel Backfill for Walls (9-03.12(2)). If prolonged dry weather prevails during the earthwork and foundation installation phase of construction, higher fines content (up to 10 to 12 percent) will be acceptable. Material placed for structural fill should be free of debris, organic matter, trash and cobbles greater than 6-inches in diameter. The moisture content of the fill material should be adjusted as necessary for proper compaction. 17-236 Military Plat.GR March 2, 2018 Page 4 Suitability of On -Site Materials as Fill During dry weather construction, any non -organic on -site soil may be considered for use as structural fill; provided it meets the criteria described above in the structural fill section and can be compacted as recommended. If the soil material is over -optimum in moisture content when excavated, it will be necessary to aerate or dry the soil prior to placement as structural fill. The native soils in the site generally consisted of fine sand and gravel. These soils are generally comparable to "common borrow" material and may be suitable for use as structural fill provided the moisture content is maintained within 3 percent of the optimum moisture level. We recommend that completed graded -areas be restricted from traffic or protected prior to wet weather conditions. The graded areas may be protected by paving, placing asphalt -treated base, a layer of free -draining material such as pit run sand and gravel or clean crushed rock material containing less than 5 percent fines, or some combination of the above. Temporary Excavations All job site safety issues and precautions are the responsibility of the contractor providing services/work. The following cut/fill slope guidelines are provided for planning purposes only. Temporary cut slopes will likely be necessary during grading operations or utility installation. All excavations at the site associated with confined spaces, such as utility trenches and retaining walls, must be completed in accordance with local, state, or federal requirements. Based on current Washington Industrial Safety and Health Act (WISHA, WAC 296-155-66401) regulations, the shallow upper soils on the site would be classified as Type C soils. According to WISHA, for temporary excavations of less than 20 feet in depth, the side slopes in Type C soils should be laid back at a slope inclination of 1%2H:1V or flatter from the toe to the crest of the slope. It should be recognized that slopes of this nature do ravel and require occasional maintenance. All exposed slope faces should be covered with a durable reinforced plastic membrane, jute matting, or other erosion control mats during construction to prevent slope raveling and rutting during periods of precipitation. These guidelines assume that all surface loads are kept at a minimum distance of at least one half the depth of the cut away from the top of the slope and that significant seepage is not present on the slope face. Flatter cut slopes will be necessary where significant raveling or seepage occurs, or if construction materials will be stockpiled along the slope crest. Where it is not feasible to slope the site soils back at these inclinations, a retaining structure should be considered. Where retaining structures are greater than 4-feet in height (bottom of footing to top of structure) or have slopes of greater than 15 percent above them, they should be engineered. This information is provided solely for the benefit of the owner and other design consultants and should not be construed to imply that Development Engineering, PLLC assumes responsibility for job site safety. It is understood that job site safety is the sole responsibility of the project contractor. Foundation Support Based on the subsurface soil conditions encountered across the site, we recommend that spread footings for the new buildings be founded on dense to very dense native soils or on structural fill that extends to suitable native soils. The soil at the base of the footing excavations should be disturbed as little as possible. All loose, soft or unsuitable material should be removed or recompacted, as appropriate. A representative from our firm 17-236 Military Plat.GR March 2, 2018 Page 5 should observe the foundation excavations to determine if suitable bearing surfaces have been prepared, particularly in the areas where the foundation will be situated on fill material. We recommend a minimum width of 2 feet for isolated footings and at least 16 inches for continuous wall footings. All footing elements should be embedded at least 18 inches below grade for frost protection. Footings founded as described above can be designed using an allowable soil bearing capacity of 2,000 psf (pounds per square foot) for combined dead and long-term live loads. The weight of the footing and any overlying backfill may be neglected. The allowable bearing value may be increased by one-third for transient loads such as those induced by seismic events or wind loads. Lateral loads may be resisted by friction on the base of footings and floor slabs and as passive pressure on the sides of footings. We recommend that an allowable coefficient of friction of 0.40 be used to calculate friction between the concrete and the underlying soil. Passive pressure may be determined using an allowable equivalent fluid density of 300 pcf (pounds per cubic foot). Factors of safety have been applied to these values. We estimate that settlements of footings designed and constructed as recommended will be less than 1 inch, for the anticipated load conditions, with differential settlements between comparably loaded footings of 1/2 inch or less. Most of the settlements should occur essentially as loads are being applied. However, disturbance of the foundation subgrade during construction could result in larger settlements than predicted. Floor Slab Support Slabs -on -grade, if constructed, should be supported on the medium dense native soils or on structural fill prepared as described above. Areas of significant organic debris should be removed. We recommend that floor slabs be directly underlain by a capillary break material with minimum 6-inch thickness of coarse sand, pea gravel, or gravel containing less than 3 percent fines. The drainage material should be placed in one lift and compacted to an unyielding condition. A synthetic vapor barrier is recommended to control moisture migration through the slabs. This is of particular importance where the foundation elements are underlain by the silty till, or where moisture migration through the slab is an issue, such as where adhesives are used to anchor carpet or tile to the slab. A subgrade modulus of 400 kcf (kips per cubic foot) may be used for floor slab design. We estimate that settlement of the floor slabs designed and constructed as recommended, will be 1/2 inch or less over a span of 50 feet. Pavement Subgrades Pavement subgrade areas should be prepared as previously described in the "Site Preparation" section of this report. The prepared subgrade should be evaluated by proof -rolling with a fully -loaded dump truck or equivalent point load equipment. Soft, loose or wet areas that are disclosed should be recompacted or removed, as appropriate. Over -excavated areas should be backfilled with compacted structural fill and sub -base material. Seismic According to the Seismic Zone Map of the United States contained in the current version of the IBC (International Building Code), the project site is located within Seismic Risk Zone 3. Based on the subsurface conditions observed at the site, we interpret the upland portion of the structural site 17-236 Military Plat.GR March 2, 2018 Page 6 conditions to correspond with a seismic Soil Profile type Sc, (Site Class "C") Table 1615.1.1 in the IBC documents. This is based on the likely range of equivalent SPT (Standard Penetration Test) blow counts for the soil types observed in the site area. Structures located at the site that are constructed in accordance with the appropriate seismic criteria will have the same risk as other similarly designed structures in the Puget Sound area. Site Drainage All ground surfaces, pavements and sidewalks at the site should be sloped away from structures. The lot should also be carefully graded to ensure positive drainage away from all structures and property lines. Surface water runoff from the roof area, driveways, perimeter footing drains, and wall drains, should be collected, tightlined, and conveyed to an appropriate discharge point. Based on our site evaluation, it is our opinion that the infiltration of stormwater at the site is feasible for preliminary design purposes we recommend that a long-term design infiltration rate of 8 inches per hour be used for sizing any on -site retention facilities if required. Roof infiltration trenches should be sized based on the "medium sand" soil classification. Pilot Infiltration Test On March 2, 2018 we returned to the site to perform a full-scale infiltration test, also known as a Pilot Infiltration Test (PIT). During the test we excavated a pit to the depth of approximately 3 feet exposing the existing sand and gravel soils. The test was located in the north east area of the site (see Figure 2 Site Plan) and was performed in general conformance with the City drainage manual requirements and determined an average field measured rate of 28.5 inches per hour. The correction factors should be 0.5 for testing, 0.65 for geometry and 0.9 for plugging, resulting in a long-term design infiltration rate of 8 inches per hour. After the test we excavated the bottom of the pit an additional 5 feet and found no evidence of groundwater or mounding after the test was performed. LID Feasibility The following table presents our recommendations for various Best Management Practices (BMPs) for various Low Impact Development (LID) BMPs. BMP Viable? Limitations or Infeasibility Criteria Lawn and Landscape Areas T5.13: Post Construction Soil Quality and Yes None. Depth Roofs T5.30: Full Dispersion No The site likely will not have sufficient room for the required dispersion flow paths. T5.10A: Downspout full infiltration Yes Infiltration appears to be feasible for the site, as systems. such roof drains may be tightlined to an individual infiltration trench. Bio Retention Yes This BMP also feasible for the same general reasons as for full infiltration. T5.10B Downspout Dispersion systems Limited This BMP may be feasible but will likely not be employed as additional mitigation will be required beyond the capacity of a dispersion system. T5.10C Perforate stub connections Limited Feasible but most likely not used. Other Hard Surfaces 17-236 Military.Plat.GR March 2, 2018 Page 7 T5.30 Full Dispersion No Sufficient native vegetation does not exist on the site given the.total amount of proposed development. T5.15 Permeable Surfacing Yes The site soils do support the use of permeable surfacing. Bio Retention Yes This BMP is also feasible for the same general reasons as for full infiltration. T5.12: Sheet Flow Dispersion Limited No flooding or erosion impacts are anticipated. T5.11 Concentrated flow dispersion However, this BMP is likely not feasible given the size of the lot and the limited available areas for dispersion of runoff. LIMITATIONS We have prepared this report for DMP Development and other members of the design team for use in evaluating a portion of this project. The data used in preparing this report and this report should be provided to prospective contractors for their bidding or estimating purposes only. Our report, conclusions and interpretations are based on data from others and limited site reconnaissance, and should not be construed as a warranty of the subsurface conditions. Variations in subsurface conditions are possible between the explorations and may also occur with time. A contingency for unanticipated conditions should be included in the budget and schedule. Sufficient monitoring, testing and consultation should be provided by our firm during construction to confirm that the conditions encountered are consistent with those indicated by the explorations, to provide recommendations for design changes should the conditions revealed during the work differ from those anticipated, and to evaluate whether earthwork and foundation installation activities comply with contract plans and specifications. The scope of our services does not include services related to environmental remediation and construc- tion safety precautions. Our recommendations are not intended to direct the contractor's methods, techniques, sequences or procedures, except as specifically described in our report for consideration in design. If there are any changes in the loads, grades, locations, configurations or type of facilities to be constructed, the conclusions and recommendations presented in this report may not be fully applicable. If such changes are made, we should be given the opportunity to review our recommendations and provide written modifications or verifications, as appropriate. 17-236 Military Plat.GR March 2, 2018 Page 8 Within the limitations of scope, schedule and budget, our services have been executed in accordance with generally accepted practices in this area at the time this report was prepared. No warranty, express or implied, should be understood. We trust this is sufficient for your current needs. Should you have any questions, or require additional information, please contact us at your earliest convenience. Respectfully submitted, Development Engineering, PLLC Glen Coad, PE Owner CH:WGC Doc ID:17-236 Military Plat.GR Attachments: Figure 1— Vicinity Map Figure 2 —Site Plan Figure 3 — SCS Soil Survey Figure 4 — USGS Geology Map Figure 5 — Soils Classification Chart Figure 6 — Soil Test Pit Logs Not to Scale DE -CIVIL, PLLC P.O. Box 446 Tacoma, WA 98401 Ph (253) 228-0513 www.de-civil.com Approximate Location Site Vicinity Map Military Plat XXX Military Rd S Federal Way, Washington Job No: 17-236 December 2017 Figure 1 Not to Scale Approximate Location DE -CIVIL, PLLC USDA Soils Map P.O. Box 446 Tacoma, WA 98401 Military Plat Ph (253) 228-0513 XXX Military Rd S www.de-civii.com Federal Way, Washington Job No: 17-236 1 December 2017 1 Figure 3 ti AN 10 Ii � Qw 1 �7t� + t _�. l " � le � � ' S r Approximate Location Not to Scale DE -CIVIL, PLLC Geological Map P.O. Box 446 Tacoma, WA 98401 Military Plat Ph (253) 228-0513 XXX Military Rd S www.de-civil.com Federal Way, Washington SOIL CLASSIFICATION CHART SYMBW TYPICAL MAJOR DWIONS ORAPlt LE"M DESMPTIONS • vrtv 004.E000MMS. ov u CAN 1 CLEAN • I..ie GWy SAIU4iYUlSS ' CRAWLGVANUS I AM .� . GIAMLY artn.o.4rrty e`r0' GP VDOfLYaatsoDt4Yw puKL•ti1TO K(ZrKi 9o1L5 o o v __ppp C'OAfchE Ga:AVElS VNTrr i 91-CrV' MCKPAIL -SAND - GR,tlkr0 rfCC.-A.n x�c FrvEB UT VGC7 ALS L$ rwaCT'a" RS�. NSWD C •.•] YAK �ArOtN (�(�` � rr "A G%Wfi • SAr.e .'.'� SWNaLLetLW SA'tOI tlUV.EiIY CIE" SAMOQ° br,.mi SAND 4'J-- �E�rW464. UTRCabMtfi lee iH.i SAMY I ! ' Sp 1 roorav:AUDCD 6Not. Scots Cdnv(.AY awl t rADre rrw+x+a BNID61vITH .S•t � TV SAW, wa•sar 06COAAM FINES arRT1Jo3 r;'ASW. to. • MrrpbWiwuwr C-YfY &Vft INW - MAY rt r/r'K1i Sc Mornpu _ I �47rr:�vC TALrS IIIXKSL9uR UL rurSY h1L MlMsxrn Iw�s-err .. - woa�.ea►.sriic:. �v SILTS lSUO LVM CL w:_+wrn,Aaro�r.9A.rC..Y rpm AMD LM TkW la C�.•i SAr1Cy CAYy W. R�•r GRAINED CLAYSu+�r;-ns SOIL$ OL caarvtrcwtrAw�c«awc Cln' CLAYS CS LDF OJKTICT' r�,a nKrceo..a- uwtnaersrc MH owowAmme rLTv=!i r.Ar _3 141 ecru WOO` AlTS Vv,o Lrr • � wO+a4rC Cur'L7 NF CLAYS LAcwlwn��w • r CH rsw.Tlurr DA"N C CLAYS "3a rE t? I OH YSDUI 10 MC+ p bTCW n1r�ItY ORCrANIG SOte• - P' j 'ur5.. rrw.9. OAy+uwC CON Ives s lNn+ d tilers NOTE: lAtA6-e rfibols are used to i+dcale baderine or dual UW dandwsst>�s Sampler Symbol Descriptions . Z44nch J.D. %pint barrel " Standard Penetration Tat (SPT) Shelby tube Piston rDirect.Push ® Bulk or grab Blovroount Is recorded for driven samplers as the number Of bows required to advance sampler 12 inches (or distance noledi• See exploration log for hammer weight and drop_ A'P' Indicates sampler pushed using the weight of the WH rig. ADDITIONAL MATERIAL SYMBOLS SYMBOLS TYPICAL GRAPH LETTC DESCII P ONS CC Cement Concrete AC j Asphalt Concrete CR Crushed Rudd Quarry Spalls TS I Forest DuAGW Measured groundwater level In exploration, well, or plezorneter T Groundwater observed at time of exploration Parched water observed at time of exploration W Measured free product in well or _ plozometer Stratigraphic Contact Df6tina contact between soil strata or geologic unks - Gradual change between roil strata or geologic units — — — Approximate ICCOQicn of soli strolls change within a geologic son unit Labgra1ory J Field Tests %F Percent Ores AL AtterboM limits CA Chemical snelysb CP Laboratory compttldien test CS Consolidation test DS Dlreet shear KA ttydromelloranalysls UC Moisture content MD M olswre content and dry density OC Organic content PM Permeability or hydraulic conductivity PP Polite! penetrometer SA Sieve analysis TX TriaxW romprvssion uC Unconfined compression VS vans shear Sheen Cla62i6sation NS No Visible Sheen SS Slight Sheen MS Moderate Steen NS Navy sheen NT Not Tested N07E. The -m:er rust safer w the r,==<on un the mpoet Yost a'ld lro'%s of exDbry5oM !or a proper Lmderstandrrg of rubs;rfam card lime L%.-rxrcc*nz on dw 'o-r app3 only al the spoor tY: axobrati ani to v a ll-ne die e,tptoraP.o n ware rnada: fty are not warranlod to be rmprosr.,'.nfi v Cf SLbaL." face Cen0131X s W. alhcr UcarunS or I,TAS DE -CIVIL, PLLC P.O. Box 446 CY Tacoma, WA 98401 Ph (253) 228-0513 www.de-civii.com Soil Classification Chart Military Plat XXX Military Rd S Federal Way, Washington Job No: 17-236 December 2017 Figure 5 Test Pit TP-1 Location: (See Figure 2) Depth ft. Soil Type Description 0 — 0.5 Topsoil 0.5 — 2.0 SM Weathered Till 2.5-6.0 SM Till Terminated at 6 feet below ground surface. No caving or seepage observed. Test Pit TP-2 Location: (See Figure 2) Depth ft. Soil Type Description 0 — 1.0 Topsoil 1.0-10.0 SM Brown sand and gravel (loose) Terminated at 10 feet below ground surface. No caving or seepage observed. Test Pit TP-3 Location: (See Figure 2) Depth ft. Soil Type Description 0 — 1.0 Topsoil 1.0 — 8.0 SM Tan silty sand, gravel and cobble (dense) Terminated at 8.0 feet below ground surface. No caving or seepage observed. Logged by WGC,10/3/17 DE -CIVIL, PLLC P.O. Box 446 Tacoma, WA 98401 Ph (253) 228-0513 www.de-civil.com Test Pit Logs Military Plat XXX Military Rd S Federal Way, Washington Job No: 17-236 1 December 2017 1 Figure 6 Test Pit TP-4 Location: (See Figure 2) Depth ft. Soil Type Description 0 — 1.0 Topsoil 1.0— 10.0 SM Tan sand and gravel (loose) Terminated at 10.0 feet below ground surface. No caving or seepage observed. Test Pit TP-5 Location: (See Figure 2) Depth ft. Soil Type Description 0 — 1.0 Topsoil 1.0 — 3.0 SM grey sand and gravel (slightly cemented) to (loose) 3.0 — 9.0 SM sand and gravel (loose) to (medium dense) Terminated at 9 feet below ground surface. No caving or seepage observed. Logged by WGC,10/3/17 DE -CIVIL, PLLC P.O. Box 446 Tacoma, WA 98401 Ph (253) 228-0513 www.de-civii.com Test Pit Logs Military Plat XXX Military Rd S Federal Way, Washington Test Pit TP-6 Location: (See Figure 2) Depth ft. Soil Type Descri tion 0 — 1.0 Topsoil 1.0 — 3.0 SM sand and gravel w/ silt (slightly cemented) 3.0 — 5.0 SW grey silty sand, with gravel and cobbles (dense, cemented) Terminated at 3.0 feet below ground surface. No caving or seepage observed. Logged by WGC,10/3/17 DE -CIVIL, PLLC P.O. Box 446 Tacoma, WA 98401 Ph (253) 228-0513 www.de-civii.com Test Pit Logs Military Plat XXX Military Rd S Federal Way, Washington ,-�,EVel_DPMENT ENG,�I��RI NCi, �LLC P.O. Box 446 Tacoma, WA 9840 Ph (253) 228-0513 www.de-civil.com May 31, 2019 Mr. Malkit Singh Infiltration Pond Capacity 13405 SE 236th PI Proposed Short Plat Kent, WA 98030 Military Road S Federal Way, Washington PN: 152104-9081 Job: 17-236 Military Plat.RL This letter provides our assessment of the capacity of the proposed infiltration pond for the proposed Northlake Court Plat located near 45t' Way S and Military Road in the City of Federal Way, Washington. The plat includes an infiltration pond in the northeast corner of the site to manage the runoff from the proposed road. At this time we have been unable to secure an off -site easement for the pond emergency overflow though any neighboring properties. Based on the WWHM calculations for the pond the 100yr peak water surface elevation is approximately 6 inches. Given that the freeboard of the pond as designed is over two feet it is our opinion that sufficient pond capacity is available to mitigate for the lack of an emergency overflow. We trust this is sufficient for your current needs. Should you have any questions, or require additional information, please contact us at your earliest convenience. Respectfully -submitted, Development Engineering, PLLC -4� J Glen Goad, PE Owner WGC Doc ID: 17-236 Military Plat.EL RF EaVE® PERMI'�APPLICATION CITY OF PERMIT CENTER + 33325 8th Avenue South + Federal Way, WA 98003-6325 Federal AA v MAR 0 5 2019 253-835-2607 + FAX 253-835-2609 + permitcente cDcityoffederalway.com CITY OF FEDERAL WAY 'OMT" 'T1 PERMIT NU TIER TARGET DATE SUITE/UNIT # SITE ADDRESS XxX PROJECT VALUATION TYPE OF PERMIT NAME OF PROJECT PROJECT DESCRIPTION Detailed description of work to be included on this permit only PROPERTY OWNER CONTRACTOR APPLICANT PROJECT CONTACT (The individual to receive and respond to all correspondence concerning this application) PROJECT FINANCING When value is $5,000 or more (RCW 19.27.095) ZONING ASSESSOR'S TAX/PARCEL N R S 9 r�` T.5 � L1 El BUILDING El PLUMBING El MECHANICAL El DEMOLITION ElFNGINEERING El FIRE PREVENTION llol?- '��� e- � Lf/L7— MAILING ADDRESS *2 _-2, t. eta . 2-7 NAME --7- R MAILING ADDRESS 1 CITY WA STATE CONTRACTOR'S LICENSE # NAME �J MAILING ADDRESS CITY NAME ADDRESS CITY NAME MAILING ADDRESS, CITY, STATE, ZIP ZIP IS f p D STATE ZIP EXPIRATION DATE I I STATE I ZIP STATE I ZIP PRIMARY PHONE 23 -a IZ E-MAIL 1, PHONE E-MAIL FAX FEDERAL WAY BUSINESS LICENSE # PRIMARY PHONE E-MAIL FAX PRIMARY PHONE E-MAIL FAX OWNER -FINANCED PHONE I certify under penalty of perjury that I am the property owner or authorized agent of the property owner. I certify that to the best of my knowledge, the information submitted in support of this permit application is true and correct. I certify that I will comply with all applicable City of Federal Way regulations pertaining to the work authorized by the issuance of a permit. I understand that the issuance of this permit does not remove the owner's responsibility for compliance with local, state, or federal Iaws regulating construction or environmental laws. I further agree to hold harmless the City of Federal Way as to any claim (including costs, expenses, and attorneys' fees incurred in the investigation and defense of such claim), which may be made by any person, including the undersigned, and filed against the city, but only where such claim arises out of the reliance of the city, including its officers and employees, upon the accuracy of the information supplied to the city as a part of this applicatio t. SIGNATURE: J—DATE r r PRINT NAME: — Bulletin #100 — January 29, 2016 Page 1 of 2 k:\Handouts\Permit Application MECHANICAL PERMIT Indicate how many or each ttjpl AIR HANDLING UNITS AIR CONDITIONER BOILERS COMPRESSORS DUCTING to be installed or relocated as FANS FIREPLACE INSERTS .... FURNACES GAS LOG SETS GAS PIPING PLUMBING PERMIT Indicate how marty of each iMe of fwure to be installed or rely BATHTUBS (or Tub/Shower Combo) LAVS (Handsinks) DISHWASHERS RAINWATER SYSTEMS DRAINS SHOWERS DRINKING FOUNTAINS SINKS (Kitchen/Utility) HOSE BIBBS SUMPS GENERAL INFORMATION VALUE OF MECHANICAL WORK f this ra'ect. Do not inClude existing flxtureS to remain GAS PIPE OUTLETS OTHER (Describe) HOODS (Commercial) HOT WATER TANKS (Gas) REFRIGERATION SYST WOODSTOVES VALUE OF PLUMBING WORK as part o this project. Do not include exfstinq ►5x cares to remain. TOILETS WATER PIPING URINALS OTHER (Describe) VACUUM BREAKERS WATER HEATERS (Electric) WASHING MACHINES TOTAL FIXTURES CRITICAL AREAS ON PROPERTY? WATER PURVEYOR SEVIERDPURVEYOR VALUE OF EXISTING IMPROVEMENTS -e 4kw1--N EXISTING/PREVIOUS USE LOT SIZE (In Square Feet) EXISTING FIRE SPRINKLER SYSTEM? I PROPOSED FIRE SUPPRESSION SYSTEM? ❑ Yes ❑ No ❑ Yes ❑ No RESIDENTIAL - NEW OR ADDITION AREA DESCRIPTION (in square feet) EXISTING PROPOSED BASEMENT FIRST FLOOR (or Mobile Home) SECOND FLOOR COVERED ENTRY DECK GARAGE ❑ CARPORT ❑ OTHER (describe) Area Totals EXISTING PROPOSED TOTAL J FOR OFFICE USE TOTAL "NEW HOMES ONLY" ESTIMATED SELLING PRICE $ T OF BEDROOMS COMMERCIAL - NEW/ADDITION AREA DESCRIPTION Area in Occupancy Group(s) s S uare Feet P Y P() Construction # of Additional Information Type Stories NEW BUILDING ADDITION COMMERCIAL - REMODEL/TENANT IMPROVEMENTS AREA DESCRIPTION Area in Occupancy Group(s) s Square Feet P Y P() Construction # of Additional Information I)Ta Stories TOTAL BUILDING TENANT AREA ONLY L_ PROJECT AREA ONLY Bulletin #100 — January 29, 2016 Page 2 of 2 k:\Handouts\Permit Application