22-105830City of Federal Way
Community Development Dept.
33325 8th Ave S
Federal Way, WA 98003
Ph: (253) 835-2607 Fax: (253) 835-2609
Project Name: SOUTH CAMPUS ESTATES LOT 7
Project Address: 427 SW 366TH ST
Project Description: 60A UG Temp Pole & Job Shack Wiring
m
Electrical
Permit #:22-105830-00-EL
Inspection Request Line: (253) 835-3050
Parcel Number: SOUTH CAMPUS
Owner
Applicant
Contractor
GEOFFREY SHERWINSOUTH CAMPUS
ERIN ORMANRICHARD C REED
RICHARD C REED ELECTRIC INC
DEVELOPMENT LLC
ELECTRIC INC
RICHACRO22KQ (5/18/24)
PO BOX 188
11012 CANYON RD E SUITE 8-958
PUYALLUP WA 98371
PUYALLUP WA 98375
] 1012 CANYON RD E SUITE 8958
PUYALLUP WA 98373
Additional Permit Information
Is this an Online or O.T.C. application?............ „ Yes
Electrical Fixtures
Circuits - Residential 1 Temp. Service: 0 - 60 amps (A 1
PERMIT EXPIRES Sunday, 18 June, 2023
Permit Issued on Tuesday, December 20, 2022
I hereby certify that the above information is correct and that the construction on the above described property
and the occupancy and the use will be in accordance with the laws, rules and regulations of the State of
Washington and the City of Federal Way.
Owner or agent: V Date:
'4A crtr ow
Federal Way
THIS C LRD IS TO REALUN ON -SITE
Construction Inspection Record
INSPECTION REQUESTS: (253) 335-3050
Scheduled inspections may be failed if this card is not on -site. DO NOT LOSE THIS CARD. Inspections are listed as close to sequential order as possible
(read left to right. top to bottom). Please schedule inspections as appropriate. Work must not be covered until it is approved. Check with your inspector if
you are unsure about any of the inspections or the inspection sequence. On -going inspections are logged on the back of this card.
ELECTRICAL
❑
By
UFER Ground (4295)
Approved
Date
Q
By
Ditch cover (4030)
Approved
Date
❑
By
Slab/Concrete Floor (4255)
Approved to place concrete
Date
0
By
Pool Bonding (4195)
Approved
Date
❑
fly
By
Temporary Power (4275)
PN,,J,'Approved
Date 7,
❑
By
Service (4235)
Approved
Date
❑
By
E4
By
Feeders/Sub-panels (4045)
Approved
Date
Final - Electrical (4055)
Approved
Date
0
By
Rough Electrical (4225)
Approved
Date
❑
By
Ceiling Cover (4020)
Approved
Date
MECHANICAL
❑ Mechanical Rough -in (4165) ❑ Gas Piping (4125) ❑ Final - Mechanical (4065)
Approved Approved to release test Approved
By Date By Date By Date
PLUMBING
t❑ Plumbing Groundwork (4190)
❑ Rough Plumbing (4230)
❑� Final - Plumbing (4075)
Approved to cover
Approved
Approved
By Date
By Date
By Date