12 - Joint Use Operations and Maint. Facility Update2024 City Council Retreat JOINT USE OPERATIONS AND MAITENANCE FACILITY 2/2/2024 Overview • Land Acquisition Update • Design Status • Overall Schedule • Discussion of expansion for City Hall Staff Land Acquisition Quick Facts: • 12 parcels to be acquired 53osihS[ • All have executed purchase and sale agreements • 7 have closed • Ramaininu nnrrplc nrp iinrigmr 1 831111hS1 Land Acquisition - Budget Spent to date: • Property Acquisition: $3.0 million • Relocation Costs: $370 thousand Under contract: • Property Acquisition: $2.8 million • Relocation Costs: In negotiation Design Status • Property Acquisition: — Utility capping — Asbestos abatement — Overall cleanup • 30% design at February LUTC • Land Use submitted • Utility coordination ongoing • Building permit submission by March 15 Design Status Interstate 5 Ma (n �!m 28tq Ave S gwgN� Existing Fire Station Design Status Office Building CEr----- Design Status Office Building L 9- OF 0 oo'o0 00 'I 0 001100 °oo loo �Q�O01loo 001 ool � ooll® ��� M o i �■� P r>�a a - II 12 I I I I I I i I I I I ao=ER�------;-- Ic_ i t 1 mn^ C _ gy ■ yI• G `� ■ ■ ■ '� R�r I IW' ■ Np ww. ■ IL I� 1 �I■ I � I�� u 1 _ jesign Sta 3intenance i3micimp Design Status Maintenance Building I I it I I I I r- - - - - - - - - 1 - ---- - - - - ------------------ 4 I 1 li I 1 I i -__-__-__-__-__-__• I _ _ . .... -__-_; � __-__-__-__-__-__-__- K ---- ---------------- L------ ------ __- Ol r - '�C I� 0i 1 1 1 Overall Schedule • 30% Design Report — February LUTC and Council • 85% Design Report — May LUTC and Council Land Use Permitting — In process Building Permit Application — March 2024 Bidding Process — Spring 2024 Council Award — Late Spring / Early Summer 2024 Expansion for City Hall Staff Design Parameters: • Relocate all Public Works, Parks, and 1 small department staff from City Hall (approximately 60 people) • Expand parking to accommodate increased employee count • Review already incorporated design elements and resize as needed (kitchen, conference rooms, bathrooms, etc.) • Look at options to expand building footprint out verse building up Expansion for City Hall Staff Findings: • Need 60 additional parking spaces -feasible to add • Expand out or up -More cost efficient to add a second story — Adds an elevator — Bathrooms stacked on top of lower level — Reduces footings, structure, and overall cladding — Preserves the ability to expand the building out in the future Expansion for City Hall Staff - m f{f {��f off 1f - N� parking s frrl_1 ---------- i OJ1_[II1.I f ��m -W Ig 1 Expansion for City Hall Staff Second story superimposed over first floor: Y Expansion for City Hall Staff Costs: • Additional infrastructure: (parking, stormwater, utilities, lighting) • Building Costs: (design, construction, FF&E) Budgetary Price: $600,000 $%300,000 $10'?000'?000 Expansion for City Hall Staff Advantages: • Create operational location and backup redundancy • More cost efficient than building a new City Hall • Create additional room within the existing City Hall for other departments to expand Disadvantages: • Decentralize city staff over two primary locations • People may come to City Hall to speak to multiple departments • May presuppose conversations about the future replacement of City Hall Expansion for City Hall Staff Mayor's Recommendation Public Works Departr 2/2/2024 19