23-103391City of Federal Way
Community Development Dept.
33325 8th Ave 5
Federal Way, WA 98003
Ph: (253) 835-2607 Fax: (253) 635-2609
Project Name: AVANA STAR LAKE APARTMENTS BUILDING 47
Project Address: 2405 S STAR LAKE RD
Project Description: BLUEBEAM - Fire damage repair.
Buildilrig - Multi Family
Permit #:23-103391-00-MF
Inspection Request Line: (253) 835-3050
Parcel Number: 720480 01 1 1
Owner
Applicant
Contractor
Lender
GEP X STAR LAKE LLC
CHRIS BACUSPACIFIC
BELFOR USA GROUP INC
OWNER IS LENDER
465 MEETING ST SUITE 500
ENGINEERING TECHNOLOGIES
4320 S 131 ST PL SUITE 100
CHARLESTON SC 29403
2150 N 107TH ST SUITE 320
SEATTLE WA 98168
SEATTLE WA 98133
Census Category: 434 - Residential alt/add - no change in number of units
Includes.
#1
#2
#3
#4
Occupancy Class:
Construction ape:
Occupancy Load:
Floor Area (sq. ft.)
Additional Permit Information
Mechanical to be Included? ........................... I ........ , No Plumbing Work Valuation?..................................... 0
Mechanical Work Valuation? ...................... I ... ........ 0 Number of Stories ... :...:......................................... I. I
Is this an Online or O.T.C. application?. ................. No Permit for Building Shell Only?............................ No
Plumbing to be included? ........................................ No
Total Valuation: 60,000.00
No Fixtures Associated With This Permit 11
PERMIT EXPIRES Tuesday, 23 January, 2024
Permit Issued on Thursday, July 27, 2023
I hereby certify that the above information is correct and that the construction on the above described property
and the occupancy and the use will be in accordance with the laws, rules and regulations of the State of
City of Federal Way.
Owner or agent: FILE
Date:
r
THIS CARD IS TO REMAIN ON -SITE
CITY OF
Construction Inspection Record
Federal Way
INSPECTION REQUESTS: (253) 835-3050
PERMIT #: 23 103391 00
Address: 2405 S STAR LAKE RD Bldg 47
Project: GEP X STAR LAKE
LLC FEDERAL WAY WA 98003
Scheduled inspections may be failed if this card is not on -site.
DO NOT LOSE THIS CARD. Inspections are listed as close to sequential order as possible
(read left to right, top to bottom). Please schedule inspections as appropriate. Work must not be covered until it is approved. Check with your inspector if
you are unsure about any of the inspections or the inspection sequence. On -going inspections are logged on the back of this card.
❑ Footings/Setback (4110) ❑
Foundation Wall (4115) 0 Drainage/Downspout (4040)
Approved to place concrete
Approved to place concrete Approved to backfill
By Date By
Date By Date
Re -steel (4215) ❑
Slab/Concrete Floor (4255) Q Underfloor Framing (4285)
Approved to place concrete or grout
Approved to place concrete Approved to sheath floor
By Date By
Date By Date
Q Floor Sheathing (4105) ❑
Shear Walls (4245) ❑ Roof Sheathing (4220)
Approved to install flooring
Approved to install siding Approved to install roof
By O Date
By Date By
Date
❑ Fire/Draft Stops (4095)
Approved
By 0 Date
I-' Insulation (4150)
Approved to install wallboard
By G Date
Final - S K F & R (4060)
Approved
1s Gypsum Wallboard Nailing (4130) 14 Suspended Ceiling Grid (4265)
Approved to install mud & tape Approved to drop tile
By jj Date ��[Z12f By Date
16
By Date By
C)
Final - Building (4050)
Approved
Date
co�,��►V
Rough Electrical
Final Electrical
Right of Way
Approved
Approved
Approved
By
Date
By
Date
By
Date
CITY OF Building Division
33325 Eighth Avenue"South
FederM Way Federal Way, 98003-6325
Phone 253-835-2607 Faxx 253-835835-2609
CORRECTION NOTICE
ADDRESS: ��0� . ' �_ (_V� Ve PERMIT#: I C j GZ - ( c
IF YOU HAVE QUESTIONS CALL 2 (253) 835-�
WHEN CORRECTIONS HAVE BEEN MADE, CALL (253) 835-3050 FOR RE -INSPECTION. SEE BACK OF CARD
FOR DETAILS. NOTE: ELECTRICAL CORRECTIONS ARE REQUIRED TO BE MADE WITHIN 15 DAYS.
Z
DATE INSPECTOR
DO NOT REMOVE THIS NOTICE
Page of