LUTC PKT 08-05-2013August 5, 2013
5:30 p.m.
City of Federai Way
City Council
Land Use/Transportation Committee
City Hall
Council Chambers
MEETING AGENDA
1. CALL TO ORDER
2. PUB�IC COMMENT (3 minutes)
3. COMMITTEE BUSINESS
Topic Title/Description
A. Approval of Minutes: July 1, 2013
8 Enterprise'13 Neighborhood Traffic Safety
Project
� Silver Lake'13 Neighborhood Traffic Safety
Project
p Safety Improvements Projects —
Authorization to Award
E Transportation Demand Management
Implementation Agreement with WSDOT
F Lakota Middle School — 13th Avenue SW
Sidewalk Connection Grant Acceptance
G. School Zone Enhancements Status Update
Action
Presenter Page or Info
Upton 3 Action
Preston S Action
Preston 9 Action
Long 13 Action
Long 17 Action
Perez 27 Action
Perez 33 Action
Council Date
Time
N/A 5 min
September 3, 2013 5 min
Consent
September 3, 2013 5 min
Consent
August 6, 2013 S min
Consent
September 3, 2013 5 min
Consent
September 3, 2013 5 min
Consent
August 6, 2013 5 min
Business
4. OTHER
5. FUTURE MEETINGS/AGENDA ITEMS:
The next LUTC meeting will be Monday, September 9, 2013 at 5:30 p.m. in City Hall Council Chambers.
6. ADJOURN
Committee Members City Staff
Bo6 Celski, Chair Cary M. Roe, P. E., Director of Parks, Public Works and Emergency Management
leanne Burbidge, Member Shawna Upton, Administrative Assistant II
Diana Noble-Gu/lifo�d, Member 253-835-2703
This page left blank intentionally.
July 1, 2013
5:30 p.m.
City of Federal Way
City Council
Land Use/Transportation Committee
City Hall
Council Chambers
MEETING SUMMARY
Committee Members in Attendance: Committee Chair Bob Celski and Committee members Diana Noble-Gulliford and
Jeanne Burbidge.
Staff in Attendance: Deputy Public Works Director Marwan Salloum, City Traffic Engineer Rick Perez, Principal Planner
Margaret Clark, Assistant City Attorney Peter Beckwith, and Administrative Assistant II Shawna Upton.
1. CALL TO ORDER
Committee Chair Celski called the meeting to order at 5:30 PM.
2. PUBLIC COMMENT
There was no public comment received.
3. BUSINESS ITEMS
Topic TitleJDescription
I�
C:
C.
Approval of the June 3, 2013 LUTC Minutes
Committee approved the ]une 3, 2013 LUTC minutes as presented.
Moved: Burbidge Seconded: Noble-Gulliford Passed: Unanimously, 3-0
Acceptance of Transportation Grant Funding - WTSC
City Traffic Engineer Perez presented information on this item. Mr. Perez summarized that
on April 25, 2013 Council authorized staff to submit a grant to the Washington Traffic
Safety Commission for school zone flashers at Sacajawea to provide advanced notice to
drivers of when the 20mph school zone speed limit is in effect. The grant has been
approved by the Commission. Staff is seeking Council authorization to accept the grant.
Committee forwarded Option #1 as presented.
Moved: Burbidge Seconded: Noble-Gulliford
2013 Comprehensive Plan Amendments
Passed: Unanimously, 3-0
Principal Planner Margaret Clark provided a background timeline of legal notices, public
meetings and requests for public comments regarding the comprehensive plan
amendments and provided a presentation discussing specifics of the rezoning requests.
The Federal Way School District has requested to be rezoned so improvements can be
made to Federal Way High School to better serve the needs of the students and increase
their presence on the street frontage. Lakeview Professional Building requested to be
rezoned to allow for building multi-family units on the site. Greg & Leanne Summers are
requesting two vacant parcels be rezoned to Single-Family-High-Density Residential to be
consistent with the properties to the east.
Forward
to Council
NJA
July 16, 2013
Consent
July 16, 2013
Ordinance
(15f Reading)
Committee Members City Staff
Bob Ce/ski, Chair Cary M. Roe, P. �, Di�ector of Parks, Pub/ic Works and Eme�gency Management
Jeanne Burbidge, Membe� . Shawna Upton, Administrative Assistant II
Diana Noble-Gulliford, Member 253-8.35-2703
All three requests are consistent with the overall vision of the Comprehensive Plan.
Discussion continued regarding, flexibility in the comprehensive plan, setbacks, and
potential impacts with future development of Sound Transit alignments along Pacif+c
Highway South.
Committee forwarded Option #1 as amended.
Moved: Noble-Gulliford Seconded: Burbidge Passed: Unanimously, 3-0
4. OTHER
5. FUTURE MEETINGS/AGENDA ITEMS:
The next LUTC meeting will be Monday, August 1, 2013 at 5:30 p.m. in City Hall Council Chambers.
6. AD]OURN
The meeting adjourned at 5:51 PM.
COMMITTEE APPROVAL:
Bob Celski, Chair
Jeanne Burbidge, Member
Attest:
Shawna Upton, Administrative Assistant II
Diana Noble-Gulliford, Member
Committee Members City Staff
Bob Celski, Chair Cary M. Roe, P.�, Directo� of Pa�ks, Public Wo�ks and Emergency Management
Jeanne Bu�bidge, Membe� Shawna Upton, Administrative Assistant II
Diana Noble-Gullifo�d, Member 253-835-2703
COLTNCIL MEETING DATE: September 3, 2013
CITY OF FEDERAL WAY
CITY COUNCIL
AGENDA BILL
ITEM #:
Subject: Enterprise 2012 NTS — 8th Ave SW (SW 356th St to SW 3615` St)
POLICY QUEST[ON: Should the Council approve the installation of three speed humps on 8`h Avenue SW
between SW 356`h Street and SW 3615` Street?
COMM[TTEE: Land Use and Transportation Committee
MEETING DATE: August 5, 2013
CATEGORY:
� Consent ❑ Ordinance ❑ Public Hearing
❑ City Council Business ❑ Resolution ❑ Other
STAFF REPORT BY: Enk Preston, P.E. — Senior Traffic Engineer � DEPT: Public Works
_ _. _.. _. . _. _ _ _ _ _ _ ._
Attachments: Land Use and Transportation Committee memorandum dated August 5, 2013
Options Considered:
1. Authorize the installation of three speed humps on 8`h Avenue SW between SW 356"' Street and SW
3615` Street.
2. Do not authorize the installation of the proposed traffic calming devices and provide direction to staff.
MAYOR'S RECOMMENDATION: Mayor recommends forwarding Option 1 to the September 3, 2013 City Council
Consent Agenda for approval.
MAYOR APPROVAL: _/�6��� � DIRECTOR APPROVAL:
Commi e Council
COMMITTEE RECOMMENDAT[ON: I move to forward Option 1 to the September 3, 2013 consent agenda for
approval.
Bob Celski, Chair Jeanne Burbidge, Member Diana Noble-Gulliford, Member
PROPOSED COUNC[L MoTION: "I move approval of the installation of three speed humps on 8`�' Avenue SW
between SW 356`�` Street and SW 361 s` Street. "
BELOW TO BE COMPLETED BY CITY CLERKS OFFICE)
COUNC[L aCT10N:
❑ APPROVED
❑ DENIED
❑ TABLED/DEFERRED/NO ACTION
❑ NIOVEU TO SECOND READING (ordinances only)
REVtSED—a8� 1Z:2010
5
COUNC[L B[LL #
l�T reading
Enactment rcading
ORDINAIYCE t#
RESOLUTION #
CITY OF FEDERAL WAY
MEMORANDUM
DATE: August 5, 2013
TO: Land Use and Transportation Committee
VIA: Skip Priest, Mayor
FROM• Cary M. Roe, P.E., Director of Parks, Public Works, and Emergency Managemen��/f%�
' Erik Preston, Seniar Traffic Engineer �UI
SUBJECT: Enterprise NTS 2012 — 8`h Ave SW (SW 356`" St to SW 36/I"' St)
BACKGROUND:
Residents along 8`h Ave SW between SW 356`h Street and SW 360`h Street submitted a petition requesting the
installation of speed humps or other traffic calming devices to control vehicle speeds in an effort to improve
vehicular and pedestrian safety along 8`� Ave SW. A traffic study was conducted and the results are as follo�vs:
• Roadway Classification : Minor Collector
• Average Daily Traf�c (ADT): 1,421
• 8�`h percentile speed: 35.8 mph
Based on the current adopted NTS installation criteria (per table below), 8`h Avenue SW scored 3.0 total
severity points. This meets the minimum 3.0 severity point to qualify for the installation of traffic
calming devices.
Table 2
Minor Collector Street NTS Criteria
Point 85th Percentile Average Daily Location 5-Year Collision Histo
Scale Speed Traffic (ADT) School/Park Total In�u Fatal
0.0 0- 25 0- 1,000 No 1 - -
0.5 26 - 27 1,001 — 1,800 Yes 2 - -
1.0 28 - 29 1,801 — 2,600 - 3 1 -
1.5 30 - 31 2,601 — 3,400 - 4 - -
2.0 32 - 33 3,401 — 4,200 - 5 2 1
2.5 34 - 35 4,201 — 5,000 - 6 - -
3.0 36+ 5, 001 + - 7+ 3+ 2+
A neighborhood traffic safety meeting was held on May 30, 2013. The attending group consensus was to
install three speed humps on 8`h Avenue SW bet�veen SW 356t° St and SW 3615` St as spacing and grades
allow.
C7
July 13, 2013
Enterprise NTS
Page 2
Traffic Division staff evaluated possible speed hump locations and proposed the following;
A) Just south of SW 358`h Street,
B) 35840 8`h Ave SW and
C) 36030 8`h Ave SW.
The speed hump locations were based upon driveway placement, intersection spacing, and p(acement for
optimal effectiveness against speeding. Proposed speed hump locations have been marked on the street.
In accordance with established NTS policies, staff sent ballots to property owners and occupants within
600 feet of the proposed traffic calming device locations and also to those with the proposal located along
their sole access route. The following table summarizes the ballot results:
� 1 �
Ba(lots Sent 166
Ballots Returned 41 25%
Unde(iverable 14
Yes Votes 35 85%
No Votes 6 15%
Returned w/o Response 0 0%
One of the insta((ation criteria requires a 51% majority approval of the returned ballots. Based on the
ballot results represented in the above table, the balloting exceeds this majority.
The estimated cost of this project is approximately $10,500, which falls within the $15,000 per
neighborhood per year budget limitation policy. The current allocated NTS budget per year is $50,000
with $20,000 designated specifically for school NTS andlor school safety related improvements. Staff
recommends approving the installation of three speed humps on 8`h Avenue SW between SW 356`h Street
and SW 36�s` Street.
The proposed package should be effective in reducing speeds and improving vehicular and pedestrian
safety. However, there may be some negative impacts to the neighborhood including inconvenience,
noise and a slight increase in emergency response time.
cc: Project Filc
Dav File
This page left blank intentionaliy.
COLTNCIL MEETING DATE: September 3, 2013
_ _ _. . __ _. _ _ __ _ _ _..__. ._ _. _ __ _
CITY OF FEDERAL WAY
CITY COUNCIL
AGENDA BILL
ITEM #:
Subject: Silver Lake 2012 NTS — 12th Ave SW/SW 340th St
POLICY QUEST[OIY: Should the Council approve the installation of one traffic circle and two speed tables on
12`h Avenue SW near SW 340`h Street?
COMM[TTEE: Land Use and Transportation Committee
CATECORY:
� Consent
❑ City Council Business
❑ Ordinance
❑ Resolution
MEETIIYG DATE: August 5, 2013
❑ Pubtic Hearing
❑ Other
STAFF REPORT BY: Enk Preston, P.E Senior Traffic Engineer `� DEPT: Public Works _
_ _ _ __ _............ - _ _. _ _
Attachments: Land Use and Transportation Committee memorandum dated August 5, 2013
Options Considered:
1. Authorize the installation of one traffic circle and two speed tabies on 12`h Avenue SW between SW
Campus Drive and SW 3415` Street.
2. Do not authorize the installation of the proposed traffic calming devices and provide direction to staff.
_ .__ _ ._... _ _ __ _ _..._. _ __ _ _
MAYOR'S RECOMMENDATION: Mayor recommends forwarding Option 1 to the September 3, 2013 City Council
Consent Agenda for approval.
MAYOR APPROVAL: _i��� "� DIRECTOR APPROVAL: __ j�� y�'!�
om ee Council Initial
COMMITTEE RECOMMENDAT[ON: I move to forward Option 1 to the September 3, 2013 consent agenda for
approval.
Bob Celski, Chair Jeanne Burbidge, Member Diana Noble-Gulliford, Member
PROPOSED COUNC[[, MOT[ON: "I move approval of the installation of one traffic circle and two speed tables
on 12`�` Avenue SW between SW Campus Drive and SW 341s` Street. "
BELOW TO BE COMPLETED BY CITY CLERKS OFFlCE)
COUNCIL ACTION:
❑ APPROVED
❑ DENIED
❑ T.46LED/DEFERRED/NO AC"I'ION
❑ MOVED TO SECOND READ[NG (ordinances only)
REV [SED — 08/12/2010
�
COUNCIL BILL #
ls� reading
Enactment reading
ORDINANCE #
RESOLUT(ON #
CITY OF FEDERAL WAY
MEMORANDUM
DATE: August 5, 2013
TO: Land Use and Transportation Committee
VIA: Skip Priest, Mayor �
FROM• Cary M. Roe, P.E., Director of Parks, Publi Works, and Emergency Management �
' Erik Preston, Senior Traffic Enginee�G�
SUBJECT: Silver Lake NTS 2012 — I2`" Ave SW /SW 340`h St
BACKGROUND:
Residents near the intersection of 12`� Ave SW / SW 340`h St submitted a petition requesting the installation of a
roundabout or traffic calming devices to control vehicie speeds in an effort to improve vehicular and pedestrian
safety near the intersection of 12`h Ave SW / SW 340`h St. A traffic study was conducted and the results are as
follows:
• Average Daily Tra�c (ADT): 2, 779
• 85`h percentile speed- 31.1 mph
• �-year Collision History_ 1, No injuries
Based on the current adopted NTS installation criteria (per Table 1 below), 8`h Avenue SW scored 3.0
total severiry points. This meets the minimum 3.0 severity point to qualify for the installation of traffic
calming devices.
Table 1
Minor Collector Street NTS Criteria
Point 85th Percentile Average Daily Location 5-Year Collision Histo
Scale Speed Traffic (ADT) School/Park Total In�u Fatal
0.0 0- 25 0- 1,000 No 1 - -
0_5 26 - 27 1,001 — 1,800 Yes 2 - -
1.0 28 - 29 1,801 — 2,600 - 3 1 -
1.5 30 - 31 2,601 — 3,400 - 4 - -
2.0 32 - 33 3,401 — 4,200 - 5 2 1
2.5 34 - 35 4,201 — 5,000 - 6 - -
3.0 36+ 5,001+ - 7+ 3+ 2+
A neighborhood traffic safety meeting was held on June 6, 2013. The attending group consensus was to
install one traffie circle at the intersection of 12`� Avenue SW and SW 340`h Street and two speed tables on
12`� Avenue SW near SW 340`� Street as spacing and grades allow.
10
July 22, 2013
Silver Lake NTS
Page 2
Traffic Division staff evaluated possible speed table locations and proposed the following three traffic
calming elements and their locations;
A) one 32' diameter traffic circle at 12`� Ave SW / SW 340`� Street,
B) a speed table on 12`� Ave SW, 215 feet north of SW 340`� Street and
C) a speed table on 12`'' Ave SW, 330 feet south of SW 340"' Street.
The speed table locations were based upon driveway placement, roadway grade limitations (less than 8%),
intersection spacing, and placement for optimal effectiveness against speeding. Proposed traffic circle and
speed table locations have been marked on the street and approved by fire department staff.
In accordance with established NTS policies, staff sent ballots to property owners and occupants within
600 feet of the proposed traffic calming device tocations and also to those with the proposal located along
their sole access route. The following table summarizes the ballot results:
� 1 �
Ballots Sent 54
Ballots Returned 19 35%
Undeliverable 1
Yes Votes 17 89%
No Votes 2 1 1%
Returned w/o Res onse 0 0%
One of the installation criteria requires a 51% majority approva( of the returned ballots. Based on the
baliot results represented in the above table, the balloting exceeds this majority.
The estimated cost of this project is approximately $12,000, which fatls within the $15,000 per
neighborhood per year budget limitation policy. The current allocated NTS budget per year is $50,000
with $20,000 designated specifically for school NTS and/or school safety related improvements. Staff
recommends approving the installation of one traffic circle and two speed humps on 12`h Avenue SW
between Campus Drive and SW 3415` Street.
The proposed package should be effective in reducing speeds and improving vehicular and pedestrian
safety. However, there may be some negaTive impacts to the neighborhood including inconvenience,
noise and a slight increase in emergency response time.
ce: Project File
Day File
11
This page left blank intentionaliy.
��
COUNCIL MEETING DATE. August 6, 2013
CITY OF FEDERAL WAY
CITY COUNCIL
AGENDA BILL
ITEM #:
SUBJECT: Safety Improvement Projects — Authorization to Award
POL[CX QUESTION: Should the City Council authorize staff to award the Safety Innprovement Projects to the
towest responsive, responsible bidder?
COMMITTEE: Land Use and Transportation Committee
CATEGORY:
� Consent
❑ City Council Business
��
Ordinance
Reso(ution
MEETING DATE: AUguSt S, 2O 13
❑ Public Hearing
❑ Other
STAFF REPORT BY: Sarady Long, Senior Transportation_Planning_Enginee _ DEPT: Public Works
- --
Attachments: - Memorandum to the Land Use and Transportation Committee dated August 5, 2013.
- Bid Tabulation
Options Considered:
l. Au�horize staff to award the Safety Improvement Projects to Transportation Systems, Inc., the lowest
responsive, responsible bidder in the amount of $810,445.00 and approve a 5% contingency of $40,522
for a total of $850,967.00 and authorize the Mayor to execute the contract.
2. Do not award the Safety Improvernent Projects and provide direction to staff.
MAYOR'S RECOMMENDAT[ON: Mayor recommends forwarding Option 1 to the August 6, 20t3 City Councii
Consent Agenda for approval.
MAYOR APPROVAL: DIRECTOR APPROVAL: �
Commlt e Council Committee Council
CONINfITTEE RECONiMENDATION: Forward Option 1 to the August 6, 2013 Council Consent Agenda for approvai.
Bob Celski, Chair
Jeanne Burbidge, Member Diana Noble-Gulliford, Member
PROPOSED COUNCIL MOTION: "I move to authorize staff to award the Safety Improvement Projects to
Transportation Systems, Inc., 1he lowest responsrve, responsible biclder in the amount of �810, 44�. 00 and approve
a S% contingency of $40, 522. 00 for a total of $850, 967 00 and authorize the Mayor to execute the contract "
(BELOW TO BE COMPLETED BYCITYCLERKS OFFICE)
COCI�ICIL ACTION:
❑ APPROVED COUNCIL BILL #
� DENIED l'T reading
❑ T 16LED1DEFF,RRED/NO ACTION Enactment reading
❑ MOVED TO SECOND READ(NG (ordinances only) ORDI�'ANCF. tt
RE VISED - 02/06/2006 RESOLUTION #
13
CITY OF FEDERAL WAY
MEMORANDUM
DATE: August 5, 2013
TO: Land Use and Transportation Committee
VIA: Skip Priest, Mayor
FROM• Cary M. Roe, P.E., Director of Parks, Public Works and Emergency Management L��
' Sarady Long, Senior Transportation Planning Engineer�
SUBJECT: Safety Improvement Projects — Authorization to Award
BACKGROUND:
One (1) bid was received and opened on July 24, 2013, for the Safety Improvement Projects. Please see
attached Bid Tabulation Summary. The lowest responsive, responsible bidder is Transportation Systems,
Inc. with a total bid of $810,445.00. The low bid received was approximately (1%) below the engineers
estimate for the total project cost (Schedule A, B and C).
Reference checks on Transportation Systems, Inc. by City staff indicates that the contractor has
performed similar work. As a result, City staff believes Transportation Systems can successfully
complete this project to the City's satisfaction. Therefore, the lowest responsive, responsible bidder is
Transportation Systems, Inc. in the amount of $810,445.00.
PR(l_TF(`T F,CTiMATF,n F,XPF,NDiTiTRF.S:
Schedule "A" Schedule B Schedule C
Citywide Safety S 320`� St Safety SR 99 Safety Total Schedule
Improvement Improvement Improvement A, B and C
Project Project Project
Design $86,186 $41,734 $33,063 $160,983
Construction Cost (Low Bid) $464,024 $228,607 $117,814 $810,441
5% Construction Contingency $23,201 $ I 1,430 $5,891 $40,522
Consh-uction Management $42,000 $7,000 $7,000 $56,000
TOTAL PROJECT COSTS $615,411 $288,771 �163,768 $1,067,950
PRn.TF'f'T AVAiLABLE FUNDING:
City Funds $0.00 $0.00 $0.00 $0.00
City Safety Program Grant Funding $350,000 $258,600 $174,000 $782,600
(Federal
Quick Response Highway Safety $363,200 $0.00 $0.00 $363,200
Improvement Grant (Federal)
TOTAL AVt�ILABLE BUnGET $713,200 $258,600 $I74,000 $1,145,800
TOTAL PROJECT FUNDING BALANCE ��
The S 320T� Street Safety [mprovement Project (Schedule — B) total project cost is $30,171 above the available
grant funding budget. Staff is working with WSDOT to transfer fund from Schedule A— Citywide Safety
improvement Project to this project. This request was approved on July 25, 2013.
14
SAFETYIMPROVEMENTPROJECTS
RFB No. 13-108
BID OPENING DATE JUNE 24, 2013
Bid of Project Bid #1
Vendor Name ---> Transportation Systems Engineers Estimate
Location ----------> S.imner lNA
•
• � • •
SCHEDULE A- CITYWIDE SAFETY IMPROVEMENT PROJECT
A-1 Minor Change EST 1 $5,000.00 $5,000.00 $5,000.00 $5,000.00
A-2 SPCC Plan LS 1 $15,000.00 $15,000.00 $500.00 $500.00
A-3 Mobilization LS 1 $40,500.00 $40,500.00 $40,000.00 $40,000.00
A-4 Project Temporary traffic Control LS 1 $60,000.00 $60,000.00 $90,850.00 $90,850.00
A-5 Off-Duty Uniformed Police Officer FA 1 $17,000.00 $17,000.00 $17,000.00 $17,000.00
A-6 Traffic Signal system Modifications - 1st Ave S& S 320th St, Complete LS 1 $21,800.00 $21,800.00 $18,800.00 $18,800.00
A-7 Traffic Signal system Modifications - 21 st Ave SW & SW 320th St, Complete LS 1 $50,000.00 $50,000.00 $54,800.00 $54,800.00
A-8 Traffic Signal system Modifications - 11th PI S& S 320th St, Complete LS 1 $17,930.00 $17,930.00 $18,300.00 $18,300.00
A-9 Traffic Signal system Modifications - 8th Ave SW & SW 356th St, Complete LS 1 $21,320.00 $21,320.00 $20,300.00 $20,300.00
A-10 Traffic Signal system Modifications - 8th Ave S& S 320th St, Complete LS 1 $30,119.00 $30,119.00 $32,300.00 $32,300.00
A-11 Traffic Signal system Modifications - SR 161 & S 352nd St, Complete LS 1 $22,863.00 $22,863.00 $18,800.00 $18,800.00
A-12 Traffic Signal system Modifications - 6th Ave SW & SW Campus Drive, Complete LS 1 $25,870.00 $25,870.00 $20,300.00 $20,300.00
A-13 Traffic Signal system Modifications - 20th Ave S& S 312th St, Complete LS 1 $24,170.00 $24,170.00 $23,550.00 $23,55Qrp0
A-14 Traffic Signal system Modifications - 1 st Ave S& SW 356th St, Complete LS 1 $20,380.00 $20,380.00 $30,700.00 $30,70b�0
A-15 Traffic Signal system Modifications - Weyerhaeuser Way & S 320th St, Complete LS 1 $20,000.00 $20,000.00 $14,650.00 $14,650.00
A-16 Traffic Signal system Modifications - 1 st Ave S& S 330th St, Complete LS 1 $29,757.00 $29,757.00 $30,600.00 $30,600.00
A-17 Traffic Signal system Modifications - 21st Ave SW & SW Dash Point Rd, Complete LS 1 $16,900.00 $16,900.00 $23,800.00 $23,800.00
A-18 Retroreflective Backplate Tape - Complete LS 1 $15,815.00 $15,815.00 $61,150.00 $61,150.00
A19 Directional Borin - 8th Ave S& S 320th St LF 80 $120.00 $9,600.00 $110.00 $8,800.00
' TQ'�Ai.5CHEDUL�A' "i$464,024.00 $530,200.00
(birJ items inc[ude sales tax)
SCHEDULE B- SOUTH 320TH STREET SAFETY IMPROVEMENT PROJECT
B-1 Minor Change EST 1 $5,000.00 $5,000.00 $5,000.00 $5,000.00
B-2 SPCC Plan LS 1 $1,750.00 $1,750.00 $500.00 $500.00
B-3 Mobilization LS 1 $26,000.00 $26,000.00 $11,700.00 $11,700.00
B-4 Project Temporary traffic Control LS 1 $28,000.00 $28,000.00 $15,000.00 $15,000.00
B-5 Off-Duty Uniformed Police Officer FA 1 $1,800.00 $1,800.00 $1,800.00 $1,800.00
B-6 Traffic Signal System Modifications - S 320th St & 25th Ave S, Complete LS 1 $29,157.00 $29,157.00 $31,300.00 $31,300.00
B-7 Retroreflective Backplate Tape - S 320th St & 23rd Ave S, Complete LS 1 $2,350.00 $2,350.00 $3,000.00 $3,000.00
B-8 Retroreflective Backplate Tape - S 320th St & 25th Ave S, Complete LS 1 $2,800.00 $2,800.00 $1,000.00 $1,000.00
B-9 Overhead Lane Assignment sign - Southbound 23rd Ave S at S 320th St, Complete LS 1 $36,600.00 $36,600.00 $27,000.00 $27,000.00
8-10 Overhead Lane Assignment sign - Northbound 23rd Ave S at S 320th St, Complete LS 1 $36,750.00 $36,750.00 $29,000.00 $29,000.00
8-11 Overhead lane Assignment Sign - Eastbound S 320th St at I-5 Ramps, Complete LS 1 $38,000.00 $38,000.00 $31,000.00 $31,000.00
B-12 APS Push Button S stem - S 320th St & 25th Ave S, Com lete LS 1 $20,400.00 $20,400.00 $19,150.00 $19,150.00
? ' 7QTAE: SCH�C1��,�, �i ',! < I , : ;: ' ; $228,607.00 5175�450.00
Page 1 of 2
SAFETYIMPROVEMENTPROJECTS
RFB No. 13-108
BID OPENING DATE JUNE 24, 2013
Bid of Project Bid #1
Vendor Name ---> Transportation Systems Engineers Estimate
Location ----------> Sumner, WA
-•
• � • •
bid items inelude sales tax
SCHEDULE C- SR 99 SAFETY IMPROVEMENT PROJECT
C-1 Minor Change EST 1 $5,000.00 $5,000.00 $5,000.00 $5,000.00
C-2 SPCC Plan LS 1 $300.00 $300.00 $500.00 $500.00
C-3 Mobilization LS 1 $3,150.00 $3,150.00 $11,700.00 $11,700.00
C-4 Project Temporary traffic Control LS 1 $7,500.00 $7,500.00 $15,000.00 $15,000.00
C-5 Off-Duty Uniformed Police Officer FA 1 $1,800.00 $1,800.00 $1,800.00 $1,800.00
C-6 Traffic Signal System Modifications - Pacific Highway S& S 324th St, Complete LS 1 $29,999.00 $29,999.00 $22,700.00 $22,700.00
C-7 Traffic Signal System Modifications - Pacific Highway S& S 330th St, Complete LS 1 $24,865.00 $24,865.00 $25,200.00 $25,200.00
C-8 Retroreflective Backplate Tape - Pacific Highway S& S 320th St, Compiete LS 1 $2,900.00 $2,900.00 $3,500.00 $3,500.00
C-9 Retroreflective Backplate Tape - Pacific Highway S& S 324th St, Complete LS 1 $2,000.00 $2,000.00 $1,500.00 $1,500.00
C-10 Retroreflective Backplate Tape - Pacific Highway S& S 330th St, Complete LS 1 $1,800.00 $1,800.00 $1,100.00 $1,100.00
C-11 Overhead Lane Assignment si n- Westbound S 324th St at Pacific Hi hwa S, Complete LS 1 $38,500.00 $38,500.00 $26,000.00 $26,000.00
�'C3Ti4t. $CWEpULE C ' $117,814.00 $114,OOQ�00
jb�d iter�ts Ir�+CIudE s�ie$ f3x) �'
TOikt� SCHEDU'L,� A t:� +C > ��:� � Q;�F'�.tif3 �;... � 818��i�p:Ot1'
Cor�traCfor TotaF.
_ , _.
Bid Form Yes
Addendum acknowledgement Yes
Bid Schedule Yes
Bid Signature Yes
Bid Bond Yes
Subcontractor List N/A
Combined Affidavit Yes
DBE Utilization Certificate N/A
DBE Written Confirmation N/A
DBE Good Faith Effort Documentation NIA
Page 2 of 2
COiJNCIL MEETING DATE: September 3, 2013
CITY OF FEDERAL WAY
CITY COUNCIL
AGENDA BILL
SUB.tECT: Transportation Demand Management Implementation Agreement with WSDOT
ITEM #:
POL[CY QUESTION: Should the Council authorize the Mayor to enter into an agreement with the Washington
State Department of Transportation (WSDOT) allowing the State to reimburse the City its proportionate share
of the technical assistance funding for implementing the State Commute Trip Reduction (CTR) law?
COMMITTEE: Land Use and Transportation Committee
CATEGORY:
� Consent
❑ City Council Business
��
Ordinance
Resolution
MEETIKG DATE: Aug. 5, 2013
❑ Public Hearing
❑ Other
STAFF REPORT BY Sarady Long, Senior Trans. Planning Engineer� DEPT Public Works
Attachments: Memorandum to the Land Use and Transportation Committee dated August 5, 2013.
Exhibit 1; Project Scope of Work
Options Considered:
1. Authorize the Mayor to enter into an agreement with
of $38,869 for the 2013 — 2015 biennium.
WSDOT to accept state CTR technical funds in amount
2. Do not authorize the Mayor to enter into an agreement with WSDOT and implement CTR program as
required by state law and local CTR ordinance without the State CTR technical fund. The City would need
to allocate budget in the amount of $38,869 for the 2013 — 2015 biennium.
MAYOR'S RECOMMENDAT[ON: Mayor recommends forwarding Option 1 to the September 3, 2013 City Council
Consent Agenda for approval.
MAYOR APPROVAL: �����(/� DIRECTOR APPROVAL: (% ���
Co�nnuttee Council Committee Council
COMMITTEE RECOMMEIVDAT[ON: I move to forward Option 1 to the September 3, 2013 consent agenda for
approval.
Bob Celski, Chair Jeanne Burbidge, Member Diana Noble-Gulliford,
Member
PROPOSED COUNCIL MOT[ON: "I move approval and authorize the Mayor to enter into an agreement with
WSDOT to accept the state CTR technical fund in amount of �38, 869 for the 2013 — 201 S biennium. "
(BELOW TO BE COMPLETED SYClTYCLERKS OFFLCE)
COUNC[L ACTION:
❑ APPROL'ED
❑ DENIED
❑ TABLEDIDEFERRED/NO ACT[ON
❑ MOVED TO SECOND READING (ordinances only)
REVISED-08112/2010
17
COUNCIL BILL #
(ST reading
Enactment reading
ORDINANCE #
RESOLUTION#
CITY OF FEDERAL WAY
MEMORANDUM
DATE: August 5�', 2013
TO: Land Use and Transportation Committee
VIA: Skip Priest, Mayor
FROM• Cary M. Roe, P.E., Director of Parks, Public Works, and Emergency Manageme�i�
' Sarady Long, Senior Transportation Planning Engineer��
SUBJECT: Transportation Demand Management Implementation Agreement with WSDOT
BACKGROUND:
The Washington State Department of Transportation (WSDOT) provides technical assistance funding to
the City for developing and implementing the Commute Trip Reduction (CTR) programs as required by
State law. The CTR program requires a two-year agreement with WSDOT from July 1, 2013 through
June 30, 2015. The purpose of the agreement is to allow the State to reimburse the City its proportionate
share of the technical assistance funding. The work performed under this agreement is as described in the
attached EXHIBIT I, Project Scope of Work Commute Trip Reduction (CTR). The City's current CTR
agreement with WSDOT has expired and a new agreement is required to receive funding.
The agreement capped funding allocation to the City at $38,869.00 for the July l, 2013 through June 30,
2015 biennium. As in the past, due to workload and expertise the City will continue to use the funding
allocation from WSDOT to contract with King County for their CTR support services_ Staff will present
this contract to the LUTC and Council committee as a separate agenda item.
cc: Project File
Day File
- ,'-".:.�. .:. � �:::r � �.,,..�..�,.crr, .._, . ., .. .
.:.�:.:. � � i � . , .-,;.
� . ,._ . , �, . . . ... ,...:, i � ,:...:, t... . , . �.,�
. .. . . _ ., . �. _.� , S _ i. _. .. . ..
i
EXHIBIT 1
Project Scope of Work
Commute Trip Reduction (CTR}
1. Scope of Work
A. Administrative Work Plan
The CONTRACTOR agrees to submit to WSDOT an administrative work plan by the end of
the first quarter of this agreement or when the CONTRACTOR submits its first invoice,
whichever is sooner. The administrative work plan will include the following elements:
1. The work plan shall identify the deliverables, schedule, expected outcomes,
performance measures and the budget specific to strategies associated with this
AGREEMENT and other strategies as defined in the approved and locally
adopted CTR or GTEC plans. These plans may include, but are not limited to,
recruiting new employer worksites, reviewing employer programs, administering
surveys, reviewing program exemption requests, providing employer training,
providing incentives, performing promotion and marketing, and providing
emergency ride home and other commuter services.
2. The administrative work plan budget shall identify how the CONTRACTOR will
use the state funds provided in this AGREEMENT for each task. The work plan
shall also provide an estimate of the other financial resources not provided in this
AGREEMENT that will be used to complete each task.
3. The administrative work plan must be approved in writing by the WSDOT Project
Manager and signed by the CONTRACTOR, and shall be incorporated as a
written amendment to the AGREEMENT. The administrative work plan may be
amended based on mutual written agreement between the WSDOT Project
Manager and the CONTRACTOR and shall be incorporated as a written
amendment to this AGREEMENT.
B. Work to be Performed
The county or city, whichever applies, has enacted or will enact a Commute Trip Reduction
(CTR) ordinance in compliance with RCW 70.94.521 through RCW 70.94.555. The
CONTRACTOR agrees to implement a CTR program based on the approved administrative
work plan and the draft or adopted local CTR plan and to comply with all provisions of the
applicable county or city ordinance.
C. Use of State Funds for Incentives
The CONTRACTOR agrees to use State funds provided as part of this AGREEMENT in
accordance with incentives guidance to be provided by WSDOT.
D. Quarterly Progress Reports and Invoices
The CONTRACTOR agrees to submit to WSDOT complete quarterly progress reports, as
specified by WSDOT in Section 7— Progress Reports of the AGREEMENT, in E�ibit 2,
"Project Progress Report", and as integrated with the deliverables identified in the
administrative work plan, along with all invoices in accordance with Section 5—
Reimbursement and Payment of the AGREEMENT. All invoices shall be complete and
GCB 1561 19 Page 8 of 16
accurately reflect actual State funded expenditures. Only those activities identified in the
CONTRACTOR'S approved administrative work plan will be reimbursed by WSDOT.
E. Final Progress Report
The CONTRACTOR agrees to submit to WSDOT a final progress report, a template of
which is attached hereto as E�ibit 4, "Final Project Progress Report," to replace the last
quarterly progress report in the period of the AGREEMENT. The final progress report shall
provide an estimate of the other financial resources not provided in this AGREEMENT that
were used to complete each task and shall provide a list of the funds provided in this
AGREEMENT that were disbursed by the CONTRACTOR to its eligible contracting
partner(s).
F. Funding Distribution
The CONTRACTOR may distribute funds to local jurisdictions to include counties, cities,
transit agencies, Transportation Management Associations, and Metropolitan Planning
Organizations or other eligible organizations authorized to enter into agreements for the
purposes of implementing CTR and/or GTEC, plans as applicable, and ordinances as
autharized by RCW 70.94.527(5) and RCW 70.94.544.
G. Implementation Plans
The CONTRACTOR shall incorporate appropriate sections of the Project Scope of Work and
incentives guidance, as well as the approved administrative work plan, in all agreements with
eligible contracting partner(s), as necessary, to coordinate the development, implementation,
and administration of such CTR and/or GTEC plans, and compliance with applicable
ordinances.
H. Appeals and Modifications
The CONTRACTOR shall maintain an appeals process consistent with the Administrative
Procedures section contained in the CTR Guidelines which may be obtained from WSDOT
or found at http:�`/���%.��-sd�t.��-a.�ov/"Transit/CTR�Ia«�.htm.
I. Coordination with Regional Transportation Planning Organizations (RTPO)
The CONTRACTOR shall coordinate the development and implementation of its CTR
and/or GTEC plan and programs with the applicable regional transportation planning
organization (RTPO). The CONTRACTOR agrees to notify the RTPO of any substantial
changes to its plans and programs that could impact the success of the regional CTR plan.
The CONTRACTOR agrees to provide information about the progress of its CTR and/or
GTEC plan and programs to the RTPO upon request_
J. Survey Coordination
The CONTRACTOR agrees to coordinate with WSDOT and its contracting partners for
commute trip reduction employer surveys.
K. Planning Data
The CONTRACTOR agrees to provide WSDOT with the program goals established for
newly affected worksites when they are established by the local jurisdiction. The
CONTRACTOR agrees to provide WSDOT with updated program goals for affected
worksites and jurisdictions as requested. These updates shall be submitted electronically in a
format specified by WSDOT.
GCB 1561 2� Page 9 of 16
L. Database Updates
The CONTRACTOR agrees to provide WSDOT and the CONTRACTOR's contracting
partners with updated lists of affected or participating worksites, employee transportation
coordinators, and jurisdiction contacts, as requested. These updates will be submitted in a
format specified by WSDOT.
GCB1561 21 Page 10 of 16
EXHIBIT 2
Project Progress Report
Commute Trip Reduction (CTR) Quarterly Project Report
Reporting quarter: Date:
Organization: Agreement number:
Biennial Estimate of drive-alone trips to reduce to meet goal:
tar ets
Key •
deliverables:
(from
administrative
work lan)
Com leted activities this uarter
.
Planned activities for next uarter
.
Describe issues, risks or challen es and resolutions
.
Estimated ex enditures of state funds for this uarter
GCB1561 22 Page 11 of 16
��► W��FtlltglQfl SiA�@
tlepaetment t�f Tr2�nsportatian
Exhibit 3
Invoice Voucher
MINORITY BUSINESSES
MARK BOX(ES) IF APPROPRIATE
M � %
w � %
E �
VENDOR OR CLAIMANT (WARRANT TO BE PAYABLE TO) VENDOR'S CERTIFICATE. I here by certrfy under penalty of perjury ihat the items and
total listed herein are proper charges for materials, merchandise or services fumished ro
agency the State of Washington, and that all goods fumished and / or services rendered have
been provided wRhout disaimination on the grounds of race, rreed, cobr, national origin,
address sex or age.
CI�/, state ZIP BY (SIGNATURES IN INK)
contact name Phone # email
FEDERAL I.D. NUMBER OR SOCIAL SECURY7Y NUMBER 00-0000000 TITLE DATE
(FOR REPORTIN6PERSONAL SVCS. CONTRACT PAYMENT TO IRS)
� • � • ' • ' • • • - - � - • • - �
DATE CURRENT EXPENDITURES
�ESCRIPT�IQN EXPENDITURES TO DATE ,
TDM Implementation
AGREEAAEN
INVOICE
T
DFSCRIP'I'[01'
xxxx Transportation Demand Management Implementation BILLING PERIOD
(TDM)
ACCOUNTING CLASSIFICATION
ACCOUNT
JOBNUMBER WORKQP SUB
OJB OB:1
1 P0000-00 0723 NZ13
SIGNATURE OF APPROVING AUTHORITY
FOR PROCESSING BY
ORG.NUMBER
631020
DATE
DATE
CONTROLSECTION FEDERAI
EQUIPPAENTNUMBER NON-PARTICIPATING NETAMOUNT
OROER NUMBER
TOTAL� I
RECEIVING VERIFICATION
(SIGNATURE)
WARRANT NUMBER
DATE RECEIVED
VOUCHER NUMBER
GCB1561 23 Page 12 of 16
EXHIB IT 4
Final Project Progress Report
Commute Trip Reduction (CTR) Final Project Report
Biennium: 2013-2015 Date:
Organization: Agreement number: GCB
Biennial Estimate of drive-alone trips to reduce to meet goal:
targets •
Deiiverables: .
(from
administrative
work lan)
Describe our ro ress on each of our deliverables this biennium.
.
Did you meet your targets for this biennium? Why or why not?
What were your major successes this biennium? How did they help you make
ro ress toward the oals in our 'urisdiction's CTR lan s?
What were your major challenges this biennium? How did they hinder your
ro ress toward the oals in our 'urisdiction's CTR lan s?
.
How do you measure the performance of your strategies?
.
What did you learn this biennium?
.
What would help you be more successful in the future? Please be specific (If it's
more resources, how much and what would the be for, etc. .
For each of the strategies in your administrative work plan, describe your
expected outcomes, whether you met those outcomes, and why or why not.
Strategy Expected Performance Outcomes Why or why not?
outcomes measures met?
GCB1561 24 Page li of 14
If your organization used other financial resources besides state CTR funds to
implement the activities in your administrative work plan for this agreement,
please provide the information below.
Source of local funds Estimated funds spent How the funds were
this a reement used
Total local funds:
If your organization disbursed any state CTR funds to other organizations to
implement the activities in your administrative work plan for this agreement,
please list the tota! amount disbursed for the biennium below.
Organization Total disbursed this Purpose of disbursal
a reement
Total disbursement:
GCB 1561 � 5 Page I 4 of 14
This page left blank intentionally.
26
COUNCIL MEETING DATE: September 3, 2013
_ __ _ _ ___
_ _ . _ __
CITY OF FEDERAL WAY
CITY COUNCIL
AGENDA BILL
ITEM #:
SUB.IECT: Acceptance of Grant Funding for Transportation Improvement Projects
POt�[CY QUEST[o�1: Shoutd City Council authorize staff to accept Federal Grant Funding for Transportation
Improvement Proiects?
COMM[TTEE: Land Use and Transportation Committee MEETING DATE: August 5, 2013
CATEGORY:
� Consent ❑ Ordinance
❑ Public Hearing
❑ City Council Business � Resolution ❑ Other
STAFF REPORT BY: Rick Perez, P.E City Traffic Engineer DEPT: Public Works
___ _ _ _ _ _ ... __. ___ _ _ _....... - . ._ -_ _ _- _..._
Attachments: Land Use and Transportation Committee memorandum dated August 5, 2013
Options Considered:
1. Approve the attached resolutions to accept Federal Grant Funding for the 13`'' Avenue SW Sidewalk
Connection Project.
2. Do not approve the attached resolution to accept Federal Grant Funding and provide direction to staff.
____ _.... __ ._.. _ _ ___ --- ... -
M4YOR's RECOMMENDAT[ON: The Mayor recommends forwarding Option 1 to the September 3, 2013 Council
Consent Agenda for approval.
MAYOR APPROVAL: D[RECTOR APPROVAL: �
Com Counci! Committee Couacil
COMM�TTEE RECOMMEN�AT[o1v; Committee recommends forwarding Option 1 to the September 3, 2013
Council Consent Agenda for approval.
Bob Celski, Chair Jeanne Burbidge, Member Diana Noble-Gulliford, Member
PROPOSED COUNClL MOTlON.� "I move to approve the attached resolution to accepi Federal Grant Funding for
13`�' Avenue SW Sidewalk Connection P�oject. "
TO BE COMPLETED BY C[TY CLERKS OF
COUNCIL ACTION:
❑ APPROVED COUNCIL BILL #
❑ DENiED IsT reading
❑ TABLEDIDEFERRED/NO ACTION EnacYment reading �
❑ MOVED TO SECOND READ[NC (ordinances only) ORD[N:1NCE #
REV[$ED-02,�06i2006 RESOLUTION# �
k:\council\agdbilis\2013\09-03-13 acceptance of grant fundfng for transportation improvement projects - lakota 13th srts.doc
27
CITY OF FEDERAL WAY
MEMORANDUM
DATE: August 5, 2013
TO: City Council
VIA: Skip Priest, Mayor /��
FROM: Cary M. Roe, P.E., Director of Parks, Pub �c orks, and Emergency Managemenvt"„
Rick Perez, P.E., City Traffic Engineer �
SUBJECT: Grant Funding for Transportation Improvement Projects — Authorization to Accept
Grant Funding
BACKGROUND:
This memorandum provides the Council with the current status of the grant applications submitted in
2012 under the 2012 WSDOT Safe Routes to Schools Program and Pedestrian and Bicycle Safety
Program. A higher than expected federal funding allocation to Washington State allowed WSDOT to
reconsider these applications, resulting in the funding award of another project.
Project
(Funding Phase) Grant Funding Amount Required City
Match
Grant
14` Ave S: S 308` St to S 312" St $765,000
(Design and Construction) Previously awarded and
Pedestrian and Bicycle Safety (Federal Funds) accepted by Council on $0.00
January 15, 2013
Lakota Middle School Sidewalk — 13" Avenue SW:
SW 314`� Street — SW 316`� Street $270,ll9 $0.00
(Design and Construction) Newly Awarded
Adelaide Elementary School Sidewalk— 16r' Avenue No Grant Funding
SW: SW 304 Street — SW 306 Street
(Design and Construction) Awarded for this project
S 288` St: 19` Ave S to I-5 (Design and Construction)
(Design and Construction) No Grant Funding
Pedestrian and Bicycle Safety (State Fund) Awarded for this project
k:\lutc\2013\08-05-13 acceptance of grant funding - lakota 13th srts�c
RESOLUTION 1�10.
A RESOLUTION of the City Council of the City of Federal Way,
Washington, authorizing execution of Local Agency Agreement with
Washington State Department of Transportation regarding
improvement to Lakota 13th Avenue SW Sidewatk Connection Project in
the City of Federai Way, Washington.
WHEREAS, the City of Federal Way applied for several Pedestrian and Bicycle Safety and
Safe Routes to School Grant Program from the Washington State Department of Transportation for
the purpose of design and construction of Pedestrian and Bicycle Safety Improvements Projects
within the City; and
WHEREAS, the Washington State Department of Transportation agrees to grant the City of
Federal Way federal funds in the total amount of Two Hundred Seventy Thousand One Hundred
Nineteen and no/ 100 Dollars ($270,119.00) provided that the City Council authorizes the Mayor to
enter into the Local Agency Agreements; and
WHEREAS, by accepting said grant the City of Federal Way agrees to execute the Local
Agency Agreements;
NOW THEREFORE, THE CITY COUNCIL OF THE CITY OF FEDERAL WAY,
RESOLVES AS FOLLOWS:
Section i. Execution of Acceptance of the Local Agenc�Qreement_ The Mayor or his
designee is hereby authorized to execute the Local Agency Agreements regarding improvements to
the Lakota 13�' Avenue SW Sidewalk Connection Project in the City of Federal Way.
Section 2. Receipt of Federal Funds. The Mayor or his designee is hereby authorized to
Resolution No. 13-
29
Page ! of 3
Rev Ul0
receive the state and federal funds estimated to be Two Hundred Seventy Thousand One Hundred
Nineteen and 00/100 Do(lars ($270,i l9_00)_
Section 3. Matchin Fg� unds. Pursuant to the terms of the I,ocal Agency Agreement, the City
is not required to commit matching funds.
Section 4. Severability. If any section, sentence, clause or phrase of this resolution should be
held to be invalid or unconstitutional by-a court of competent jurisdiction, such invalidity or
unconstitutionaiity shall not affect the validity or constitutionality of any other section, sentence,
clause or phrase of this resolution.
Section 5. Corrections_ The City Clerk and the codifiers of this resolution are authorized to
make necessary corrections to this resolution including, but not limited to, the correction of
scrivenedclerical errors, references, resolution numbering, section/subsection numbers and any
references thereto.
Section 6. Ratification. Any act consistent with the authority and prior to the effective date
of this resolution is hereby ratified and affirmed.
Section 7. Effective Date. This resolution shall be effective immediately upon passage by
the Federal Way City Council.
Resolution No. 13-
[ci�l
Page 2 of 3
Rev 1/10
RESOLVED BY THE CITY COUNCIL OF THE CITY OF FEDERAL WAY,
WASHINGTON this day of September, 2013
CITY OF FEDERAL WAY
MAYOR, SKIP PRIEST
ATTEST:
CITY CLERK, CAROL MCNEILLY, CMC
APPROVED AS TO FORM:
CITY ATTORNEY, PATRICIA A. RICHARDSON
FILED WITH THE CITY CLERK:
PASSED BY THE CITY COUNCIL:
RESOLUTION NO.:
Resolution No. 13-
31
Puge 3 of 3
Rev 1/10
This page left blank intentionally.
32
COLTNCIL MEETING DATE: August 6, 2013
CITY OF FEDERAL WAY
CITY COUNCIL
AGENDA BILL
ITEM #:
__ _ _
SUBdECT: School Zone Enhancements Status Update
POL[CY QUEST[ON: Should the City Council approve the implementation plan to replace blank-out signs with
variable speed limit signs?
COMMITTEE: Land Use and Transportation Committee
CATEGORY:
❑ Consent
� City Council Business
�
�
Ordinance
Resolution
STAFF REPORT BY: Rick Perez, P.E., Traffic Engineer
MEETING DATE: August 5, 2013
❑ Public Hearing
❑ Other
DEPT: Public Works
Attachments: Land Use / Transportation Committee memorandum dated August 5, 2013.
Options Considered:
1. Authorize staff to replace the proposed blank-out signs with variable speed limit signs;
2. Do not authorize the proposed plan and provide direction to staff.
MAYOR RECOMMENDATfON: The Mayor recommends forwarding Option 1 to the August 6, 2013 City Council
Business Agenda for approval. n
MAYOR APPROVAL:
D[RECTOR APPROVAL: �._
Council Committee
COMMITTEE RECOMMENDATION: Forward Option 1 to the August 6, 2013 City Council Business Agenda for
approval.
Bob Celski, Chair Jeanne Burbidge, Member Diana Noble-Gulliford, Member
PROPOSED CO[IIVC[L MOT[ON: "I move approval of the implementation plan, replacing hlank-out signs with
variable speed limit signs. "
TO BE COMPLETED BY ClTY CLERKS OFFIC
COUNCIL ACTION:
❑ APPROVED
❑ DENIED
❑ TABLED/DEFERRED/NO ACTION
❑ MOVED TO SECOND READING (ordinances on[y)
REVISED — 02/06/2006
K:ACOUNC[L�AGDBItLS'�2013\0�-ZI-13 Schoo{ Zone Enhancements.docx
33
COUNC[L BIGL #
IST reading
Enactment reading
ORDINANCE #
RESOLUTIOIY #
CITY OF FEDERAL WAY
MEMORANDUM
DATE: August 5, 2013
TO: Land Use and Transportation Committee
VIA: Skip Priest, Mayor
FROM• Cary M. Roe, P.E irector of Parks, Public Works, and Emergency Management ��
' Rick Perez, P.E. �
SUBJECT: School Zone Enhancements Status Update
BACKGROUND:
On May 21, 2013, City Council approved a plan to enhance the visibility of school zone speed limits by
installing advance school speed limit signs, replacing existing school zone signs with oversize signs,
installing variable speed limit signs, and other miscellaneous equipment upgrades. The plan prioritized
these enhancements and authorized staff to implement the first year's upgrades prior to the beginning of
the 2013-14 school year to the greatest extent possible.
On July 16, 2013, City Council approved including the installation of these improvements at Sacajawea
Middle School into this year's implementation.
Thus this year's implementation includes the following improvements:
l. Saghalie Middle School: Oversize signs, variable speed limit signs, replace existing span wire
crosswalk sign on 21S` Avenue SW and existing pedestrian-actuated flashers on SW Campus
Drive with Rectangular Rapid Flashing Beacons
2. Spring Valley Montessori School: Oversize signs
3. Twin Lakes Elementary School: Oversize signs, variable speed limit signs
4. Brooklake School: Oversize signs
5. Panther Lake Elementary School: Oversize signs, variable speed limit signs
6. Sacajawea Middle School: Oversize signs, variable speed limit signs, new school zone flashers on
SR 509
The new signs are in the process of being fabricated and will be installed as soon as they are available.
The rectangular rapid flashing beacons for Saghalie and the new school zone flashers for Sacajawea have
been ordered and are expected to be delivered in mid-August and installed before school starts.
As we had highlighted, the variable speed limit signs have been more troublesome, which is why we were
unabie to commit to their completion prior to the start of the school year. Initially, staff had proposed
"blank-out" signs that would read "SPEED LIMIT 20" only when the school zone speed limit was in
34
August 5, 2013
School Zone Enhancements Status Update
Page 2
effect. The vendor WSDOT had used for freeway applications had difficulty in meeting delivery dates
and the equipment has not been very reliable.
The only other vendor of blank-out speed limit signs we've found has also been used by the City of
Renton, with approximately 150 blank-out signs (most are not speed limit signs). Renton is in the process
of replacing this vendor's signs due to slow deliveries, software bugs, and being non-responsive to service
requests. These signs have been particularly troublesome for their photo-enforced locations.
Therefore, staff is now proposing a different sign with a vendor that has a more accomplished track
record. This sign has a static SPEED LIMIT message with a variable digital readout for the numerical
value, and is programmed to read "20" when the school zone is in effect and defaults to any other speed
limit value the rest of the day. King County has a standing contract with this vendor and expects that we
would have these delivered and installed in October. Thus staff proposes to use these signs in lieu of the
blank-out signs.
cc: Project File
Day File
35