13-103252City of Federal Way
Community & Econ. Dev. Services -_
33325 8th Ave S
Federal Way, WA 98003
Ph: (253) 835-2607 Fax: (253) 835-2609'
Project Name: CAMPBELL
Project Address: 32913 18TH AVE SW
Building - Single Family
Permit #: 13 -103252 -00 -SF
Inspection Request Line: (253) 835-3050
Parcel Number. 010457 0640
Project Description: REP - Tear off existing roof; install 1/2" CDX sheathing and composition shingle roofing
system.
Owner
Aq licant
Contractor
Lender
THOMAS W CAMPBELL
CHETS ROOFING &
CHETS ROOFING &
OWNER IS LENDER
32913 18TH AVE SW
CONSTRUCTION
CONSTRUCTION
FEDERAL WAY WA 98023-6403
26301 79TH AVE S
CHETSRC924BB (1/4/14)
KENT WA 98032
26301 79TH AVE S
KENT WA 98032
Census Category: 555 - Non-structural roofing permits
Includes. #1 #2 #3 #4
Occupancy Class:
Construction Type:
Occupancy Load
Floor Area . ft. 0 1 0 0 0
Additional Permit Information
New / Additional Sq. Feet - 3rd Floor....................0
Mechanical to be Included?....................................No
New / Additional Sq. Feet - Basement...................0
Plumbing to be Included9......................................No
No Fixtures Associated With This Permit 11
PERMIT EXPIRES Sunday, January 19, 2014
Permit Issued on Tuesday, July 23, 2013
I hereby certify that the above information is correct and that the construction on the above described property and
the occupancy and the use will be in accordance with the laws, rules and regulations of the State of Washington
and the City of Federal Way.
Owner or agent: C 1 Date:
- 1
CITY OF
Federal Way
PERMIT #:
Project:
THIS CARD IS TO REMAIN ON-SITE
Construction Inspection Record
INSPECTION REQUESTS: (253) 835-3050
13 -103252 -00 -SF Address: 32913 18TH AVE SW
THOMAS W CAMPBELL FEDERAL WAY, WA 98023-6403
Scheduled inspections may be failed if this card is not on-site. DO NOT LOSE THIS CARD. Inspections are listed as close to sequential order as
possible (read left to right, top to bottom). Please schedule inspections as appropriate. Work must not be covered until it is approved. Check with your
inspector if you are unsure about any of the inspections or the inspection sequence. On-going inspections are logged on the back of this card.
0 Floor Sheathing (4105)Shear Walls (4245) Roof Sheathing (4220)
Approved to install flooring Approved to install siding Approved to install roofing
By Date By Date B�-6 S Date 7`.Z
Fire/Draft Stops (4095)
Approved
By Date
0 Interim Erosion Control (4370)
Approved
By Date
Prior to scheduling a Framing inspection;
Electrical, Plumbing & Mechanical Rough -in and
Fire/Draft Stop inspections must be signed -off and
approved. IBC 109.3.4
SWM Precon Site Mtg (4400)
Initial Erosion Control (4365)
Insulation (4150)
Underfloor Framing (4285)
Gypsum Wallboard Nailing (4130)
Approved
Approved to insulate
To be done prior to breaking ground
By
Approved to sheath floor
By
Date
By
Date
By
Date
0 Floor Sheathing (4105)Shear Walls (4245) Roof Sheathing (4220)
Approved to install flooring Approved to install siding Approved to install roofing
By Date By Date B�-6 S Date 7`.Z
Fire/Draft Stops (4095)
Approved
By Date
0 Interim Erosion Control (4370)
Approved
By Date
Prior to scheduling a Framing inspection;
Electrical, Plumbing & Mechanical Rough -in and
Fire/Draft Stop inspections must be signed -off and
approved. IBC 109.3.4
11
Framing (4120)
❑
Insulation (4150)
Gypsum Wallboard Nailing (4130)
Right of Way
Approved
Approved to insulate
Approved
By
Approved to install wallboard
Date
Approved to install mud & tape
By
Date
By
Date
By Date
11
Final Erosion Control (4375)
0
Final - Building (4050)
Approved
Right of Way
Approved
By
Approved
By
Date
Date
By
Date
Rough Electrical
Approved
Final Electrical
Approved
Right of Way
Approved
By
Date
By
Date
By
Date