11-10155340 ,
City of Federal Way
Community Development Services
P.O. Box 9718
Federal Way, WA 98063-9718
Ph: (253) 835-2607 Fax: (253) 835-2609
Project Name: BARRIGA LLENA
Project Address: 30420 PACIFIC HWY S Suite 2
Ouilding - Comkziercial
Permit #: 11 -101553 -00 -CO
CInspection Request Line: (253) 835-3050
Parcel Number: 092104 9107
Project Description: REP - Fire repair to kitchen, new insulation. Non-structural wall in bathroom to be
replaced. Separate electrical permit.
Owner
Applicant
Contracto
Lender
EUGENE LOHER
CHRIS ANABLE
POSSIBILITIES UNLIMITED
30406 PACIFIC HWY S UNIT A
ANABLE SOLUTIONS
POSSIU*0440K (1/21/12)
FEDERAL WAY, WA 98003-5129
PO BOX 747
28908 SW 371ST ST
RAVENSDALE WA 98051
FEDERAL WAY WA 98022
Census Category: 437 - Commercial alt / add / conversion
Includes: #1 #2 #3 #4
Occupancy Class:
Construction Type:
Occupancy Load:
Floor Areas . ft. 0 1 0 0 1 0
New / Additional Sq. Feet - 3rd Floor....................0
Mechanical to be Included?....................................No
New / Additional Sq. Feet - Basement...................0
Plumbing to be Included?.......................................No
CONDITIONS:
Subject to field inspection without plans
PERMIT EXPIRES Sunday, October 30, 2011
Permit Issued on Tuesday, May 3, 2011
I hereby certify that the above information is correct and that the construction on the above described property and
the occupancy and the use will be in accordance with the laws, rules and regulations of the State of Washington
C nd the City o Federal Way.
Owner or agent: Date:
F
I Npd,�&'D 8 /1511
CrrY OF
Federal Way
PERMIT #:
11 -101553 -00 -CO
THIS CARD IS TO REMAIN ON-SITE
Construction I>iection Record
INSPECTION REQ TS: (253) 835-3050
Address: 30420 PACIFIC HWY S Suite 2
Project: EUGENE LOHER FEDERAL WAY, WA
Scheduled inspections may be failed if this card is not on-site. DO NOT LOSE THIS CARD. Inspections are listed as close to sequential order as
possible (read left to right, top to bottom). Please schedule inspections as appropriate. Work must not be covered until it is approved. Check with your
inspector if you are unsure about any of the inspections or the inspection sequence. On-going inspections are logged on the back of this card.
SWM Precon Site Mtg (4400)Initial
Erosion Control (4365)
Footings/Setback (4110)
By
Approved
By
To be done prior to breaking ground
By
Approved to place concrete
By
Date
By
Date
By
Date
Foundation Wall (4115)
Drainage/Downspout (4040)Re-steel
(4215)
By
Approved to place concrete
By
Approved to backfill
By
Approved to place concrete or grout
By
Date
By
Date
By
Date
E]
❑
Slab/Concrete Floor (4255)
Underfloor Framing (4285)
❑
Floor Sheathing (4105)
Approved to place concrete
Approved to sheath floor
Approved to install flooring
By
Date
By
Date
By
Date
Shear Walls (4245)0
Roof Sheathing (4220)
Fire/Draft Stops (4095)
Approved to install siding
Approved to install roofing
Approved
By
Date
Date,5 -4—
By,,
Date f q,l
Prior to scheduling a Framing inspection;
Q
Interim Erosion Control (4370)
Framing (4120)
Approved
Electrical, Plumbing & Mechanical Rough -in and
Approved to insulate
By
Date
Fire/Draft Stop inspections must be signed -off and
By
Date ��
approved. IBC 109.3.4
Insulation (4150)
Gypsum Wallboard Nailing (4130)
Suspended Ceiling Grid (4265)
Approved to install wallboard
Approved to install mud & tape
Approved to drop tile
By
Date 7 -��. ��
By
Date �- 2�
By
Date
❑
Final - Fire Department (4060)
Final Erosion Control (4375)
Final - Building (4050)
Approved
Approved
Approved
By
/42Z Date `/u -P
By
Date
By `� Date
Rough Electrical
Approved
Final Electrical
Approved
Right of Way
Approved
By
Date
By
Date
By
Date