19-105882 N 1 •
Electrical
City of Federal Way ' LE Permit #:19-105882-00-EL
Community Development Dept. rill
33325 8th Ave S
Federal Way,WA 98003 Inspection Request Line: (253)835-3050
Ph:(253)835-2607 Fax:(253)835-2609
Project Name: EVERGREEN PROSTHETICS&ORTHOTICS
Project Address: 922 S 348TH ST Parcel Number: 114040 0020
Project Description: Tenant is Evergreen. Low voltage intrusion alarm takeover& add cellular communicator unit.
Owner Applicant Contractor
FEDERAL WAY DSKO LLC JENNIFER COVELLOA D T LLC A D T LLC(ELECTRICAL 06)
8880 SW NIMBUS AVE 11824 NORTH CREEK PKWY SUITE 105 ADTLLL*881D0(3/20/20)
BEAVERTON WA 97008 BOTHELL WA 98011 11824 NORTH CREEK PKWY SUITE 105
BOTHELL WA 98011
Additional Permit Information
Is this an Online or O.T.C.application9 Yes
,SITi �^ 3_o >uuyy. � �,'Pv� { -s s x:'. �I� � »aa " q-- ��_,�, �;
Low Voltage-Burglar Alarm 1 1
PERMIT EXPIRES Friday, 18 December,2020
Permit Issued on Thursday,December 19,2019
I hereby certify that the above information is correct and that the construction on the above described property
and the occupancy and the use will be in accordance with the laws, rules and regulations of the State of
Washington and the City of Federal Way.
Owner or agent: ONLINE Date:
, .. . , .
THIS CARD IS TO REMAIN ON-SITE
Construction Inspection Record
Federal Way INSPECTION REQUESTS:(253)835-3050
PERMIT#: 19 105882 00 Address: 922 S 348TH ST Bldg B
Project: FEDERAL WAY DSKO LLC FEDERAL WAY WA 98003-7051
Scheduled inspections may be failed if this card is not on-site. DO NOT LOSE THIS CARD. Inspections are listed as close to sequential order as possible
(read left to right,top to bottom). Please schedule inspections as appropriate. Work must not be covered until it is approved. Check with your inspector if
you are unsure about any of the inspections or the inspection sequence. On-going inspections are logged on the back of this card.
El UFER Ground(4295) ® Ditch cover(4030) 1:1 Slab/Concrete Floor(4255)
Approved I Approved Approved to place concrete
1
By Date ; By Date By Date
El Pool Bonding(4195) 1 0 Temporary Power(4275) IEl Service(4235)
Approved I Approved Approved
By Date By Date By Date
• Y �. .
® Feeders/Sub-panels(4045) ® Rough Electrical(4225) E1 Ceiling Cover(4020)
Approved Approved Approved
By Date By Date By Date
El Final-Electrical(4055)
Approved
By I Date /.2-A3,19
0 Rough Electrical El Final Electrical 0 Right of Way
Approved Approved Approved
By Date By Date By Date