Henry Lot 9043 Complete Letter20-104505-UP Doc ID 81078
COMMUNITY DEVELOPMENT DEPARTMENT
33325 8th Avenue South
Federal Way, WA 98003-6325
253-835-7000
www.cityoffederalway.com
Jim Ferrell, Mayor
Michelle Henry January 27, 2021
P & M Development LLC
35001 NE 147th Avenue
Yacolt, WA 98675
p.m.development@outlook.com
Re: Files #20-104505-UP & 21-100014-SE; LETTER OF COMPLETE APPLICATION
Henry Lot 9043, Parcel 142103 9043, Federal Way
Dear Michelle Henry:
The Community Development Department is in receipt of your January 8, 2021, Process III Master Land
Use (MLU) application. The proposal is for a Reasonable Use request for a single-family residence on a
vacant lot with critical areas. Pursuant to Federal Way Revised Code (FWRC) 19.15.045, and 14.10.020, within 28
days of receiving an application, the city shall determine whether all information and documentation required
for a complete application has been submitted.
NOTICE OF COMPLETE APPLICATION
Please consider this correspondence a formal Letter of Complete Application. Pursuant to FWRC 19.15.045
and 14.10.020, the application is deemed complete as of January 22, 2021. This determination of
completeness is based on a review of your submittal relative to applicable requirements referenced within
FWRC 19.15.040 and 14.10.020. The submittal requirements are not intended to determine if an application
conforms to city codes; they are used only to determine if all required materials have been submitted.
A 120-day time line for reviewing the Process III application has started as of this date. The city’s development
regulations allow the department 120 days from the date that an application is deemed complete to act on the
application. However, the 120-day time line will be stopped any time the city requests corrections and/or
additional information. You will be informed of the status of the 120-day time line when you are notified in
writing that corrections and/or additional information are needed.
CLOSING
Formal processing and review of your applications will now begin. You will be contacted soon regarding the
Notice of Application process. The Development Review Committee staff will continue to review the proposal
and will prepare initial technical review comments that will be forwarded to you in a separate correspondence at
a later date. Technical review comments may result in a request for additional information and revisions in
order to comply with applicable code requirements. If you have any questions regarding this letter or your
development project, please contact me at 253-569-1772, or chaney.skadsen@cityoffederalway.com.
Sincerely,
Chaney Skadsen
Associate Planner
c: Greg Kirk, Plans Examiner Sean Nichols, South King Fire & Rescue
Cole Elliott, Development Services Manager Brian Asbury, Lakehaven Water & Sewer District
Sarady Long, Senior Transportation Planning Engineer