21-102195-Certificate of Water Availability-06-03-2021-V12921049060 2921049091 wtr swr.docx (Form Update 3/13/20) Page 1 of 4
WATER CERTIFICATE OF AVAILABILITY
Lakehaven Water & Sewer District – Development Engineering Section
31623 – 1st Ave S PO Box 4249 Federal Way, WA 98063-4249
Email: DE@Lakehaven.org Telephone: 253-945-1581 or 253-945-1580
This certificate is intended to provide the applicant, land use agencies &/or public health departments with
information necessary to evaluate development proposals. Lakehaven Water & Sewer District, at its sole
discretion, reserves the right to delay, or deny, water service based upon capacity &/or supply limitations
in Lakehaven’s or Other Purveyor’s system facilities.
Proposed Land Use: Building Permit-SFR (2) Building Permit-MFR () Building Permit-Other
Subdivision () Short Subdivision () Binding Site Plan
Boundary Line Adjustment Other (specify/describe)
Tax Parcel Number(s): 2921049060, 2921049091 Site Address: 12XX S 359th St LWSD GIS Grid: J-13
Ex. Bldg. Area to Remain: N/A sf New Bldg. Area Proposed: 1,562 sf (ea. parcel)
WATER SYSTEM INFORMATION
1. Water service can be provided by service connection to an existing 6” diameter water main that is approximately 25-160
(+/-) feet from the site.
2. Water service for the site will require an improvement to LWSD’s water distribution system of:
a. feet of ” diameter water main to reach the site; and/or
b. The construction of a water distribution system on the site; and/or
c. A major portion of LWSD’s comprehensive water system plan would need to be implemented and/or
constructed; and/or
d. Other (describe): .
3. a. The existing water system is in conformance with LWSD’s Comprehensive Water System Plan.
b. The existing water system is not in conformance with LWSD’s Comprehensive Water System Plan and an
Amendment to this Plan will be required. This may cause a delay in issuance of land use approvals or permits.
4. a. The subject property is within the corporate limits of Lakehaven Water & Sewer District, or has been granted
Boundary Review Board approval for extension of water service outside of LWSD’s water service area.
b. Annexation or Boundary Review Board approval will be necessary to provide service.
5. Water service is subject to:
a. Payment of connection charges (to be determined by LWSD, for any new/modified service connection);
b. Proof or reservation of easement(s) as required by LWSD;
c. Other: The existing 5/8”x3/4” meter serving parcel 2921049060 needs to be evaluated under UPC & LWSD
standards, to determine if it’s adequate for the proposed use. LWSD Service Connection application required, for
any new/modified service connection. Private easement across parcel 2921049060 required for water supply line
for parcel 2921049091.
Comments/special conditions: Service pressure(s) greater than 80 psi indicated, Pressure Reducing Valve(s) indicated, contact local
building official for requirements &/or additional information.
The nearest fire hydrant is approximately 20-300 (+/-) feet from the Property (as marked on map on the back of this page).
System hydraulic model results (FF #366, copy attached), at no less than 20 psi, indicate that LWSD’s standard maximum allowable
liquid velocity of 10 ft/s is exceeded at a fire flow rate above 2,500 GPM for two (2) hours or more. This flow figure depicts the
theoretical performance of the water distribution system under high demand conditions. Fire flow rates greater than this may be
accommodated through water distribution system improvements, contact LWSD for additional information.
450 Pressure Zone Est. Meter Elevation(s)-GIS: High 200+/-, Low 194+/- Est. Pressure Range at Meter(s) (psi): 107-111
I hereby certify that the above water system information is true. This certification shall be valid for one (1) year from the date of
signature.
Name: BRIAN ASBURY Title: DEVELOPMENT ENGINEERING SUPERVISOR
Signature: Brian Asbury (e-signed) Date: 4/6/21