21-102066-UP-Trip Generation Estimate-2021-01-14-V1 TENW Transportation Engineering NorthWest Transportation Planning | Design | Traffic Impact & Operations 11400 SE 8th Street, Suite 200, Bellevue, WA 98004 | Office (425) 889-6747 MEMORANDUM DATE:January 14, 2021 TO:Sarady Long City of Federal Way FROM:Jeff Schramm / Curtis Chin, P.E. TENW SUBJECT:Trip Generation Estimate Smith Brothers Farms TENW Project No. 2020-249 This memorandum documents the trip generation estimate for the proposed Smith Brothers Farms project located at 34520 9th Avenue S in the City of Federal Way (see vicinity map in Attachment A). This memo includes a project description and project trip generation estimate. Project Description The proposed Smith Brothers Farms project would include development of an up to 58,000 square foot (SF) warehouse building for the storage and distribution of dairy products on a currently vacant site. Vehicular access to the project would be provided via one full access driveways on 9th Avenue S and one full access driveway on S 344th Street. A preliminary site plan is included in Attachment B. Trip Generation The trip generation estimates for the proposed Smith Brothers Farms project were based on methodology documented in the Institute of Transportation Engineers (ITE) Trip Generation Manual, 10th Edition for Land Use Code (LUC) 150 (Warehousing). Other land use categories were considered such as LUC 157 (High- Cube Cold Storage Warehouse). However, due to the size of the proposed warehouse the use of LUC 157 was determined to be not appropriate. In addition, the use of LUC 157 would result in less project trips. Therefore, LUC 150 was considered the most appropriate land use and may provide a conservative trip generation estimate. Table 1 summarizes the weekday trip generation estimates for daily, AM peak hour, and PM peak hour for the proposed project, as well as the Saturday peak hour trip generation. The detailed trip generation estimates are included in Attachment C. Trip Generation EstimateSmith Brothers Farms TENW January 14, 2021 Page 2 Table 1 Smith Brothers Farms – Trip Generation Summary New Trips Generated (PASSENGER VEHICLES) New Trips Generated (TRUCKS ONLY) Total Trips Generated (ALL VEHICLES) Time Period In Out Total In Out Total In Out Total Weekday: Daily 51 51 102 17 18 35 68 69 137 AM Peak Hour 24 7 31 1 0 1 25 7 32 PM Peak Hour 8 25 33 1 1 2 9 26 35 Saturday Peak Hour ------2 1 3 As shown in Table 1, the proposed Smith Brothers Farms project is estimated to generate 137 new weekday daily trips, with 32 new weekday AM peak hour trips (25 entering, 7 exiting), and 35 new weekday PM peak hour trips (9 entering, 26 exiting). The Saturday peak hour trip generation is estimated to be 3 trips. Since the project is estimated to generate less than 100 peak hour trips, the project would not be considered a major new development and a TIA would not be required. Also note that this trip generation information will be used for the project traffic concurrency application. If you have any questions regarding the information presented in this memorandum, please contact Curtis at chin@tenw.com. cc: Andrew Coates, KGIP Dustin Highland, Smith Brothers Farms, Inc. Attachments Trip Generation EstimateSmith Brothers Farms ATTACHMENT A Vicinity Map Trip Generation EstimateSmith Brothers Farms ATTACHMENT B Preliminary Site Plan Trip Generation EstimateSmith Brothers Farms ATTACHMENT C Trip Generation Calculations ITE Land Use Units 1 LUC 2 In Out Trip Rate 2 In Out Total Truck Trip Rate 2 In Out Enter Exit Total Enter Exit Total Daily Proposed Use: Warehousing 58,000 GFA 150 50%50%T = 1.58(X)+45.54 68 69 137 0.60 50%50%17 18 35 51 51 102 Daily Trips = 68 69 137 17 18 35 51 51 102 AM Peak Hour Proposed Use: Warehousing 58,000 GFA 150 77%23%T = 0.12(X)+25.32 25 7 32 0.02 52%48%1 0 1 24 7 31 AM Peak Hour Trips = 25 7 32 1 0 1 24 7 31 PM Peak Hour Proposed Use: Warehousing 58,000 GFA 150 27%73%T = 0.12(X)+27.82 9 26 35 0.03 52%48%1 1 2 8 25 33 PM Peak Hour Trips = 9 26 35 1 1 2 8 25 33 Saturday Peak Hour Proposed Use: Warehousing 3 58,000 GFA 150 64% 36% 0.05 2 1 3 - - - - - -- - - Saturday Peak Hour Trips = 2 1 3 - - - - - - Notes: 2 Land Use Code and trip rates based on ITE Trip Generation Manual, 10th Edition, 2017. 3 No data available regarding Saturday truck trips. 1 GFA = Gross Floor Area. Smith Brothers Farms - Federal Way Trip Generation Summary Directional Distribution Directional DistributionTrips Generated Truck Trip Generation Non-Truck Trip Generation 1/14/2021