Woodbridge Bld B HEX Report Appeal of Woodbridge Building “B” 17-104237-00-SE / Doc I.D. 81678 Staff Report to the Hearing Examiner Page 1 of 4 CITY OF FEDERAL WAY STAFF REPORT TO THE HEARING EXAMINER Appeal of Woodbridge Building “B” SEPA Mitigated Determination of Nonsignificance (MDNS) #20-3 (17-104237-SE) & Appeal of Use Process III Decision #21-3 (17-104236-UP) Staff Report Date: September 9, 2021 Although not part of the Hearing Examiner’s Pre-Hearing Order, this staff report is provided pursuant to Federal Way Revised Code (FWRC) 19.70.090. I. APPLICATION INFORMATION File Numbers: 17-104237-SE: Woodbridge Building “B” MDNS 17-104236-UP: Woodbridge Building “B” Use Process III Proponent: Federal Way Campus LLC, 11100 Santa Monica Blvd, Suite 850 Los Angeles, CA 90025 Project Location: 3120 South 344th Street, Federal Way, WA Project Description: Woodbridge Building “B,” construction of a 45-foot-tall, 214,050 square- foot general commodity warehouse with 245 parking spaces and associated site work, including wetland fill, on a 16.85-acre site (parcel 6142600200), along with improvements to the right-of-way for Weyerhaeuser Way South. II. STAFF REPORT CRITERIA Pursuant to FWRC 19.70.090(1), the director shall prepare a staff report concerning the application or agency decision appeal containing the following: (a) All pertinent application materials, including any notice of appeal and any agency decision. a. Response: Pertinent application materials, the notice of appeal, and the agency decision are included as attachments to this report. See Section III (Attachments), below. (b) All written comments regarding the matter received by the department prior to distribution of the staff report. a. Response: All written comments regarding the matter received by the department prior to the distribution of the staff report are included as attachments to this report. See Section III (Attachments), below. Appeal of Woodbridge Building “B” 17-104237-00-SE / Doc I.D. 81678 Staff Report to the Hearing Examiner Page 2 of 4 (c) An analysis of the application under any relevant provisions of this title and the comprehensive plan. a. Response: An analysis of the application under any relevant provisions of FWRC Title 19 and the comprehensive plan is included in the MDNS, the Staff Evaluation for Environmental Checklist, and the Use Process III Project Approval and Exhibit “A” (Findings for Project Approval), which are included as attachments to this report. See Section III (Attachments), below. (d) A statement of the facts found by the director and the conclusions drawn from those facts, including an analysis of any alleged errors or disputed findings or conclusions in an agency decision appeal. a. Response: A statement of the facts found by the director and conclusions drawn from those facts are included in the MDNS, the Staff Evaluation for Environmental Checklist, and the Use Process III Project Approval and Exhibit “A” (Findings for Project Approval), which are included as attachments to this report. See Section III (Attachments), below. Analysis of alleged errors and disputed findings or conclusions in the agency decision appeal will be presented during the appeal through prehearing motion practice, the hearing itself, and in any post-hearing briefing that may be required by the Hearing Examiner. (e) A recommendation on the matter. a. Response: Staff recommends the Woodbridge Building “B” MDNS (17-104237-SE) and Woodbridge Building “B” Use Process III Decision (17-104236-UP) be affirmed, and the appeals denied. III. ATTACHMENTS These documents are available online at the following link: https://docs.cityoffederalway.com/WebLink/Browse.aspx?id=865234&dbid=0&repo=CityofFederalWay Attachment 1 Pertinent Application Materials a) Built Environment Survey of the Former Weyerhaeuser Corporate Headquarters Campus for Compliance with Section 106 of the NHPA – Comments on SEPA Compliance for Woodbridge Building B, Cardno, July 27, 2020 b) Federal Way Campus, LLC Renaming of Current Land Use Projects, ESM Consulting Engineers LLC, February 8, 2019 c) Vision Analysis Greenline Building B, ESM Consulting Engineers LLC, October 9, 2018 d) Resubmittal File Nos. 17-104236-UP & 17-204237-SE, Greenline Building B, ESM Consulting Engineers LLC, August 15, 2018 e) Environmental Checklist, signed by Matt Reider, August 10, 2018 f) Greenline Building B Visual Impact Analysis, ESM Consulting Engineers LLC, August 10, 2018 g) Greenline Building “B” Development, Federal Way, Washington, Air Quality Report, Ramboll Environ US Corporation, June 2018 h) Greenline Building “B” Development, Federal Way, Washington Environmental Noise Report, Ramboll Environ US Corporation, July 2018 Appeal of Woodbridge Building “B” 17-104237-00-SE / Doc I.D. 81678 Staff Report to the Hearing Examiner Page 3 of 4 i) Technical Review Comments, ESM Consulting Engineers LLC, June 28, 2018 j) Project #TAL-1593, Tetra Tech, received June 28, 2018 k) Greenline Building B Preliminary Technical Information Report, ESM Consulting Engineers LLC, June 28, 2018 l) Buffer Averaging Plan Wetland Exemption Exhibit Sheet W1.1, Talasaea Consultants, Inc., received June 28, 2018 m) Design Narrative and Process III Decisional Criteria, ESM Consulting Engineers, June 27, 2018 n) Managed Forest Buffer Management Plan At the Greenline Building B Site Weyerhaeuser Way South, Federal Way, WA 98003, Gilles Consulting, revised June 26, 2018 o) Evaluation of Interior Trees at the Greenline Building B Site Weyerhaeuser Way South, Federal Way, WA 98003, Gilles Consulting, revised June 26, 2018 p) Tree Data for 32 Acre Site, Weyerhaeuser Way South, Federal Way, WA, Gilles Consulting, June 26, 2018 q) Response to Comments dated 13 December 2017, Talasaea Consultants, Inc., June 26, 2018 r) Critical Areas Report Files #17-104236-UP & File #17-104237-SE, Greenline Building B Federal Way, Washington, Talasaea Consultants, Inc., revised June 26, 2018 s) Revised Geotechnical Engineering Services Report Proposed Greenline Building B Development, Federal Way, Washington, GeoEngineers, June 21, 2018 t) Impervious Area Exhibit Sheet EN-02, ESM Consulting Engineers LLC, June 18, 2018 u) Design Brief, Exterior Elevations & Perspectives Sheet A1.0, by Craft Architects, June 18, 2018 v) Building Elevations Sheet A1.1, Craft Architects, June 18, 2018 w) Site Plan Sheet ST-01; Existing Conditions Sheet EX-01; Legend Sheet LG-01; Preliminary Drainage Grading and ROW Plan Sheet SD-01, Preliminary Landscape Plan Sheets LA-01; Landscape Details and Notes Sheet LA-02; Frontage Plan Sheet LA-03Clearing and Grading Plan Sheet GR-01; Site and Road Cross Sections Sheet GR-02; Truck Movement Study Sheets DT-01 & DT-02, and Tree/Vegetation Retention Plan Sheet TR-01, ESM Consulting Engineers LLC, June 18, 2018 x) IRG Greenline Buildings A and B Federal Way, WA Transportation Impact Study, TENW Transportation Engineering NorthWest, March 6, 2018 y) Preapplication Conference Summary, City of Federal Way, September 8, 2017 z) Master Land Use Application, received September 1, 2017 aa) Greenline Warehouse “B” Process III/IV Application With SEPA, ESM Consulting Engineers LLC, September 1, 2017 bb) Site Photographs, received September 1, 2017 cc) Geotechnical Engineering Services Report Weyerhaeuser Way South, 320th Street to SR 18 Weyerhaeuser Campus Property Federal Way, Washington, GeoEngineers, August 29, 2017 dd) Tree Counts on the Two 16-Acre Parcels…, Gilles Consulting, revised August 24, 2017 ee) My Credentials, Gilles Consulting, August 23, 2017 ff) Title Report Guarantee/Certificate No. 0105928-16, Chicago Title Insurance Company, August 8, 2017 Appeal of Woodbridge Building “B” 17-104237-00-SE / Doc I.D. 81678 Staff Report to the Hearing Examiner Page 4 of 4 gg) Water Certificate of Availability, Lakehaven Utility District, August 4, 2017 hh) Sewer Certificate of Availability, Lakehaven Utility District, August 4, 2017 Attachment 2 Background Documents a) 1994 Regulations b) Current Comprehensive Plan c) Weyerhaeuser Concomitant a. Ordinance No. 94-219 d) City Addendum to 2016 KCSWDM Attachment 3 SEPA Written Comments Attachment 4 UP III Written Comments Attachment 5 SEPA Decision a) MDNS, October 9, 2020 b) Staff Evaluation for Environmental Checklist with Exhibits, October 1, 2020 a. Exhibit A: Reduced Scale Site Plan b. Exhibit B: Vicinity Map c. Exhibit C: Environmental Checklist Attachment 6 UP III Decision a) Use Process III Project Approval Letter, July 6, 2021 b) Exhibit “A” Findings for Project Approval, June 24, 2021 c) Right-of-Way Modification Letter from City of Federal Way to ESM Consulting Engineers, June 22, 2018 d) Commercial Building Permit Checklist e) Approved Elevations f) Approved Site Plan g) Approved Landscape Plan Attachment 7 Notice of Appeal (SEPA), November 12, 2020 Attachment 8 Notice of Appeal (UP III), July 23, 2021 Attachment 9 Notice of Agency Decision Appeal Hearing Staff reserves the right to respond to matters raised subsequent to the writing of this report.