Loading...
22-100735-Bond Quantity Worksheet-04-13-2022-V1Public Works Department Item Unit Unit Price Quantity Price Quantity Price ROAD CONSTRUCTION Clearing & Grubbing LS Bid Estimate 0 Sawcutting LF 1.30 0 $0.00 Excavation & Embankment CY 18.00 0 $0.00 AC Pavement TN 70.00 0 $0.00 CSTC TN 20.00 0 $0.00 Cement Concrete Curb/Gutter LF 15.00 0 $0.00 Extruded Asphalt Curb LF 5.00 0 $0.00 Concrete Sidewalk SY 25.00 0 $0.00 Concrete driveway approach SY 45.00 0 $0.00 Monument in case EA 155.00 0 $0.00 Adjust ex. monument to grade EA 330.00 0 $0.00 Adjust ex. CB to grade EA 500.00 0 $0.00 DRAINAGE PIPE 6" Pipe LF 12.00 0 $0.00 8" Pipe LF 28.00 0 $0.00 12" Pipe LF 44.00 0 $0.00 18" Pipe LF 44.00 0 $0.00 24" Pipe LF 58.00 0 $0.00 36" Pipe LF 101.00 0 $0.00 48" Pipe LF 94.00 0 $0.00 54" Pipe LF 117.00 0 $0.00 60" Pipe LF 143.00 0 $0.00 72" Pipe LF 235.00 0 $0.00 CATCH BASINS Inlet & Grate EA 475.00 0 $0.00 CB Type I & Grate EA 900.00 0 $0.00 CB Type II 48" & Grate EA 1900.00 0 $0.00 CB Type II 54" & Grate EA 2000.00 0 $0.00 CB Type II 60” & Grate EA 3200.00 0 $0.00 CB Type II 72" & Grate EA 5000.00 0 $0.00 CB Type II 84” & Grate EA 9100.00 0 $0.00 CB Type II 96" & Grate EA Bid Estimate 0 Round solid locking lid EA 360.00 0 $0.00 Abandon existing cb EA 325.00 0 $0.00 Private On-Site Improvements Fill in those items which pertain to this project and return to the Public Works Department. BOND QUANTITIES WORKSHEET Site Address: To be Determined Project No.: 22-100735-EN Public Roadway Improvements Project Name: Woodbridge Building B Early Clear and Grading Plans I:\ESM-JOBS\1886\001\016-0011\document\Bond quantities worksheet for Building B.xls Last Revised: Page 1 Public Works Department Item Unit Unit Price Quantity Price Quantity Price Private On-Site Improvements Fill in those items which pertain to this project and return to the Public Works Department. Public Roadway Improvements RETENTION/DETENTION CONTROL Pond Excavation & Spillway CY 7.00 0 $0.00 Restrictor/Separator EA 750.00 0 $0.00 Vault EA Bid Estimate 0 Gravel Access Road LF 15.00 0 $0.00 Rip Rap Outfall Protection CY 17.00 0 $0.00 Bollards EA 500.00 0 $0.00 Fencing (around pond)LF 12.00 0 $0.00 Infiltration Trench w/12" Perf LF 18.00 0 $0.00 Flow Spreader LF 20.00 0 $0.00 Trash Racks EA 200.00 0 $0.00 WATER QUALITY Bioswale EA Bid Estimate 0 Wetvault EA Bid Estimate 0 Stormfilter Vault EA Bid Estimate 0 Stormwater wetland EA Bid Estimate 0 Sand Filter EA Bid Estimate 0 Catch basin inserts EA 800.00 0 $0.00 Oil/Water Separator EA Bid Estimate 0 High Flow Bypass EA Bid Estimate 0 RETAINING WALLS & STRUCTURES Retaining Walls SF 23.00 0 $0.00 Bridges LS Bid Estimate 0 TRAFFIC & LIGHTING Signalization LS Bid Estimate 0 Channelization LS Bid Estimate 0 Signs EA 100.00 0 $0.00 Streetlights (City Center)EA 5000.00 0 $0.00 Streetlights (Standard)EA 3000.00 0 $0.00 RIGHT-OF-WAY LANDSCAPING Street Trees EA 300.00 0 $0.00 Sod SY 10.00 0 $0.00 Shrubs (City Center)EA 6.00 0 $0.00 Tree Grates (City Center)EA 700.00 0 $0.00 I:\ESM-JOBS\1886\001\016-0011\document\Bond quantities worksheet for Building B.xls Last Revised: Page 2 Public Works Department Item Unit Unit Price Quantity Price Quantity Price Private On-Site Improvements Fill in those items which pertain to this project and return to the Public Works Department. Public Roadway Improvements SITE STABILIZATION/EROSION CONTROL Quarry Spalls TN 75.00 0 $0.00 200 $15,000.00 Seeding/Mulch Acre 3000.00 0 $0.00 1.85 $5,550.00 Silt Fence LF 4.00 0 $0.00 2173 $8,692.00 Netting Jute Mesh SY 13.00 0 $0.00 0 $0.00 Sediment Pond Standpipe EA 200.00 0 $0.00 2 $400.00 Sensitive Area Fencing LF 3.00 0 $0.00 2424 $7,272.00 Catch basin inserts EA 70.00 0 $0.00 0 $0.00 Subtotal Subtotal "A"$0.00 "B"$36,914.00 Signature Date 3/29/2022 Company Name ESM Consulting Engineers, LLC Telephone No. (253) 838-6113 $0.00 Private Erosion/Sedimentation Control (Subtotal "B"):$ 36,914.00 36,914.00 $7,383.00 $ 44,297.00 Cash Deposit:$0 $1,772 $0 $0 70%:$31,008.00 30%:$13,289.00 Public Roadway Improvements (Subtotal "A"): 5% (Up to $20,000) 4% ($20,001-%50,000) 3% (%50,001-$100,000) 2.5% ($100,001 and up) Subtotal ("A" + "B"): $ CONTINGENCY (20%): TOTAL BOND AMOUNT: The following information will be completed by the City of Federal Way Public Works Department: I:\ESM-JOBS\1886\001\016-0011\document\Bond quantities worksheet for Building B.xls Last Revised: Page 3