20-104946 InspectionTHIS CARD IS TO REMAIN ON -SITE
CITY OF
Construction Inspection Record
Federal Way INSPECTION REQUESTS: (253) 835-3050
PERMIT #: 20 104946 00 Address: 118 S 339TH CIR
Project: BINH NGUYEN FEDERAL WAY WA 98003-4538
Scheduled inspections may be failed if this card is not on -site. DO NOT LOSE THIS CARD. Inspections are listed as close to sequential order as possible
(read left to right, top to bottom). Please schedule inspections as appropriate. Work must not be covered until it is approved. Check with your inspector if
you are unsure about any of the inspections or the inspection sequence. On -going inspections are logged on the back of this card.
❑
Footings/Setback (4110)
0
Foundation Wall (4115)
3❑
Drainage/Downspout (4040)
Approved to place concrete
Approved to place concrete
Approved to backfill
By
Date
By
Date
By
Date
❑
Re -steel (4215)
❑
Plumbing Groundwork (4190)
❑
Slab/Concrete Floor (4255)
Approved to place concrete or grout
Approved to cover
Approved to place concrete
By
Date
By
Date
By
Date
❑
Underfloor Framing (4285)
®
Floor Sheathing (4105)
❑
Shear Walls (4245)
Approved to sheath floor
Approved to install flooring
Approved to install siding
By
Date
By
Date
By
Date
❑
Roof Sheathing (4220)
11
Rough Plumbing (4230)
❑
Mechanical Rough -in (4165)
Approved to install roofing
Approved
Approved
By
Date
By
Date
By
Date
❑
Gas Piping (4125)
14
Fire/Draft Stops (4095)
Approved to release test
Approved
By
Date
By
Date
Prior to scheduling a Framing inspection;
Electrical, Plumbing & Mechanical Rough -in
and Fire/Draft Stop inspections must be signed -
off and approved. IBC 109.3.4
15
Framing (4120)
16
Insulation (4150)
❑
Gypsum Wallboard Nailing (4130)
Approved to insulate
Approved to install wallboard
Approved to install mud & tape
By
Date
By
Date
By
Date
❑
Suspended Ceiling Grid (4265)
❑
Final - S K F & R (4060)
❑
Final - Planning
Approved to drop tile
Approved
Approved
By
Date
By
Date
By
Date
❑
Final - Mechanical (4065)
❑
Final - Plumbing (4075)
❑
Final - Building (4050)
Approved
Approved
Approved
By
Date
By
Date
By
Date
❑
Rough Electrical
❑
Final Electrical
❑
Right of Way
Approved
Approved
Approved
By
Date
By
Date
By
Date