Res 03-402RESOLUTION NO. 03-402
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
FEDERAL WAY, WASHINGTON, ACCEPTING THE
PRELIMINARY DESIGN OF THE COMMUNITY CENTER
AND DIRECTING PROJECT TO PROCEED TO FINAL
DESIGN
WHEREAS, the Federal Way City Council approved the planning process for a community
center, senior center, and pool facility as part of the city's 2003/2004 Capital Facilities Budget; and
WHEREAS, on February 18, 2003 the City Council adopted the Community Center/Senior
Center/Pool Work Program and Timeline as part of the Councils Resolution 03-382 directing the
implementation of steps agreed upon at the 2003 City Council Retreat; and
WHEREAS, on March 18, 2003 City Council appointed a citizen 20 member Advisory
Group to advise Council on site selection and program elements for the Center; and
WHEREAS, on July 15, 2003 city Council approved Celebration Park as the preferred site
for the location of the Community Center; and
WHEREAS, on September 2, 2003 City Council authorized:
A. The City Manager to proceed into schematic design for a Community Center that
is 77,540 total square feet with a building budget of 17.7 million that includes the
following program elements: (1) large community room, (2) classrooms, (3) 6-1ap
swimming pool, (4) large leisure pool, (5) 3-court gymnasium, (6) climbing wall,
(7) fitness area, (8) pre-school room, (9) senior lounge, (10) caf6, (11 ) game area,
Res. # 03-402 , Page 1
ORIGINAL
and (12) related support areas, and
B. The City Manager to proceed into schematic design for the extension of South
333rd street through Celebration Park to 9th Avenue South with a project budget
of $1 million to be paid for from the arterial street fund, and
C. The City Manager to prepare a bond ordinance for the project financing of the
community center in the amount not to exceed $15 million, and
D. The establishment a project contingency amount of 10% of the total project, and
E. The funding of the gap with additional REET collection in 2003, supplemented
by unallocated 2002 year end funds, the $17.7 million budget, the road funds, and
the contingency fund; and
WHEREAS, the city conducted twenty public meetings on the planning for the Community
Center; and
WHEREAS, on November 4, 2003, the City Council reviewed and commented on the
preliminary design of the Community Center; and
WHEREAS, City Council directed staff to prepare a resolution memorializing the City
Council's decision regarding the preliminary design to present at the November 18, 2003 regular
meeting of the City Council;
NOW THEREFORE, THE CITY COUNCIL OF THE CITY OF FEDERAL WAY,
HEREBY RESOLVES AS FOLLOWS:
Section 1. Preliminary Design. The City Council hereby accepts the attached preliminary
design for the Community Center and hereby directs the City Manager to authorize the project to
proceed into final design.
Res. # 03-402, , Page 2
Section 2. Final Design. The City Council will review the final design at approximately 30%,
50%, 85% and at 100% of design completion in future City Council meetings.
Section 3. Severability. If any section, sentence, clause or phrase of this resolution should be
held to be invalid or unconstitutional by a court of competent jurisdiction, such invalidity or
unconstitutionality shall not affect the validity or constitutionality of any other section, sentence,
clause or phrase of this resolution.
Section 4. Ratification. Any act consistent with the authority and prior to the effective date
of the resolution is hereby ratified and affirmed.
Section 5. Effective Date.
This resolution shall be effective immediately upon passage by
the Federal Way City Council.
RESOLVED BY THE CITY
WASHINGTON this 18th day of
COUNCIL OF THE CITY OF FEDERAL WAY,
November ,2003.
CITY OF FEDERAL WAY
TEST:
CITY CLERK, N. CHRISTINE GREEN, CMC
Res. # 03-a_0_v , Page 3
APPROVED AS TO FORM:
CITY ATTORNEY, PATRICIA A. RICHARDSON
FILED WITH THE CITY CLERK:
PASSED BY THE CITY COUNCIL:
RESOLUTION NO.:
11/07/03
11/18/03
03-602
K:~ResolutionsX2003 Proposed Comm. Center Reso
Res. # 03-/402 ., Page 4